Title Page
-
Conducted on
-
Prepared by
-
Viscore ID
-
Is the job over or under $50k? (write over OR under in the space below)
-
Address:
-
CSA
-
Contractor/Tech
-
Is the auditee a Visionstream Contractor OR third party such as a developer?
Handover & Collateral Delivered to Chorus
1.000 Design
-
1.001 - All documentation lodged in itools e.g. scope, CDPs, RMA site plans, lay, hauling and grid plans
-
1.002 - iTools progress task dates updated<br>
-
1.003 - NetMAP design not in conflict with other design work<br>
-
1.004 - Network to be relinquished (in NetMAP) removed<br>
-
1.005 - NetMAP fibre reservations applied and removed when built<br>
-
1.006 - Historical records impacted by new design rectified, connectivity & integrity ok.<br>
-
1.007 - Build standards applied in design, Manhole & cable size, plant location, position<br>
-
1.009 - Spares considered and where required part of design<br>
-
1.010 - Consents: Permits received, eg RMA, RON, Bridge etc. All Fees Paid<br>
-
1.012 - Work priced correctly using Template, FS codes / quotes as applicable.<br>
-
1.022 - Billed tasks actually done<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments
2.000 Handover & Collateral Delivered to Chorus
-
2.002 - Commissioning information meets specified requirements<br>
-
2.003 - Timing correct for RFS and DDC. Recommits meet business rules<br>
-
2.004 - Compliance certificates available (RMA, PTW, RON, TMP, Electrical)<br>
-
2.005 - Deployment codes & Template pricing applied correctly - Fit for purpose solution<br>
-
2.006 - Work Plan / H&S /Technical Procedure / PTTN Accreditation approved / Access Card current<br>
-
2.007 - Spares visible and appropriate when required<br>
-
2.008 - NetMAP updated, integrity checked & confirmed. PRA passes<br>
-
2.009 - Bearer connectivity confirmed "end to end"<br>
-
2.010 - Graphical Records & Databases identified & updated<br>
-
2.015 - OTDR traces (all cable fibres @ 1310 & 1550nm wavelength) confirmed delivered to Chorus<br>
-
2.019 - All network items defined within the Chorus Network Specified Product (CNSP) process are used in the network. No non approved items used<br>
-
2.020 - Plant Damage Report (PDR) form completed<br>
-
2.021 - Cable Network Alteration (CNA) form completed and correct<br>
-
2.025 - As-builts accurately reflect what was built
-
Add media
-
Comments: Please refer to the relevant task code for any comments
4.000 Codes
-
4.004 - Correct Statement of Work codes used<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments
6.000 Work Areas & Safety
-
6.001 - Personal and site safety procedures observed<br>
-
6.002 - Hazards identified & recorded - Worksite audit form completed / Hazard Notices in place<br>
-
6.003 - TMP provided<br>
-
6.004 - Services located<br>
-
6.005 - Power and Gas clearances correct<br>
-
6.006 - Gas Detector - within current calibration certificate<br>
-
6.007 - Gas Detector - measures for O2, Flammable, Carbon Monoxide (& Hydrogen Sulphide in volcanic areas)<br>
-
6.008 - Network security correct (Exchange)<br>
-
6.009 - Joint Chamber / Manhole lids closed and secure<br>
-
6.012 - Temporary work clearly labelled and contains name, contact details, job ID of person involved. <br>
-
6.014 - Any defects to existing network outside of scope of project referred to be rectified in the future
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
7.000 Exchange Equipment
-
7.001 - Equipment positioned & installed correctly, ventilation unimpeded<br>
-
7.002 - Equipment anchored / mounted compliant with seismic needs<br>
-
7.003 - Equipment secure; Fastenings, Isolation, Earthing, Masking, Covers<br>
-
7.004 - Equipment & racks labelled correctly. Node name visible. TLRD system name visible.<br>
-
7.006 - Alarms connected & tested. Commissioning info confirmed<br>
-
7.008 - Conduits and pipework adequately routed & anchored<br>
-
7.009 - Cable tray earthing & isolation correct<br>
-
7.010 - Cable type & size and labelled OK. Installation neat and tidy<br>
-
7.011 - Cable and jumper terminations tidy & to required standard<br>
-
7.012 - UTP cables are supported and routed securely<br>
-
7.013 - Structured Cabling supported and routed securely, not tight bends, Velcro ties used<br>
-
7.017 - Trunking manages fibre cords within maximum capacity limits; drop off position OK, flexitube anchored at equip, fibre slack managed.<br>
-
7.018 - Fire & Smoke stopping around wall cable access holes<br>
-
7.023 - GPON installed into Access OFDF (GR3) Rack (upper placement used first)<br>
-
7.024 - GPON GR3 rack electrically isolated and earthed<br>
-
7.025 - GPON GR3 rack: Fibre cords on RHS, electrical on LHS<br>
11.000 OFDF & Exchange Fibre:
-
11.001 - All optical cables 100% support on horizontal & managed on vertical, no more than 400mm fibre cable to be unsupported<br>
-
11.002 - OFDF hardware secure: OFDF Drawer-Cable Trough-Guides-Rack<br>
-
11.003 - Network labelling correct at AOFDF and log completed<br>
-
11.004 - Optical cables & cords adequately managed within racks and shelves<br>
-
11.005 - OFDF Single Fibre Organiser tray not overfilled (<1.5m tails)<br>
-
11.007 - 30mm bending radius unconditionally observed at all locations
-
11.008 - Fibre pigtail label records 'from' OFDF ID and SFO number<br>
-
11.009 - Trunking manages fibre cords within maximum capacity limits; drop off position OK, flexitube anchored at equip<br>
-
11.010 - Protective caps on all unterminated connectors <br>
-
11.011 - Connectors cleaned and verified with Fibre Inspection Probe<br>
-
11.012 - Laser Safety labels (1M Safety) at OFDF (inside and front panel)<br>
-
11.013 - No fibre task waste, all optical (glass) ends safely contained
-
11.014 - Access OFDF patchcords routed within mandrels. Excess length stored at AOFDF end<br>
-
11.022 - Patch cords on the POLT are installed and labelled<br>
-
11.024 - Network labelling correct at AOFDF and log completed<br>
-
11.025 - Access OFDF patch-cords routed within mandrels. Excess length stored at AOFDF end<br>
-
11.026 - Patch cords on the POLT are installed and labelled<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments
12.000 Cable Well
-
12.001 - Main duct entry locations provide permanent seal from gas and water ingress<br>
-
12.002 - Cable or sub duct entry sealed to Feeder Duct<br>
-
12.003 - Cable exiting from sub duct sealed<br>
-
12.004 - Unused Feeder Ducts plugged/sealed<br>
-
12.005 - Cable management systems in place eg brackets, trays, support all cable & subduct services<br>
-
12.006 - Fibre joint closure secured. Excess length cable tails management loops provided and secure<br>
-
12.007 - NetMAP label on Fibre joint closure. Each fibre cable tail labelled with NetMAP label<br>
-
12.008 - Cable well manhole lids security maintained<br>
-
12.009 - Fire/Smoke/Gas Alarms monitored and in working order<br>
-
12.010 - Water pumps operative<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
13.000 Cable Haul
-
13.002 - Cable drum managed on site safely<br>
-
13.003 - Correct duct used, or changes recorded on As Builts<br>
-
13.004 - Pulling in cable guide used<br>
-
13.005 - Cable lubricated prior to pulling<br>
-
13.006 - Is the winch capable of controlling haul tension within 2KN for fibre<br>
-
13.007 - Ducts cleaned and tested<br>
-
13.008 - Correct method used blow / suck<br>
-
13.009 - Communication method adequate (H&S of staff)<br>
-
13.010 - Subduct (to be used) cut correctly and reamed<br>
-
13.011- Subducts in manholes/joint chambers managed/not obstructing manhole plant<br>
-
13.012 - Grouped PE subducts anchored at entry to MH<br>
-
13.013 - Spare PE subducts capped<br>
-
13.014 - Subduct with cables labelled<br>
-
13.015 - Correct subduct joiner used<br>
-
13.016 - ALL cable ends sealed with Heatshrink, coiled and secured ready for use<br>
-
13.020 - Fibre cables at intermediate manholes secured with split PE subduct to MH wall<br>
-
13.021 - MaxCell installation only between adjacent MH. MH working area not impeded<br>
-
13.022 - Fibre cable prepared for joint correctly in manholes (cable management tidy to cable loop brackets)<br>
-
13.023 - Manhole / joint chamber lids free of material / Bung in lifting hole / lid locked<br>
-
13.025 - RMA: Contaminated manhole water collected for disposal<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
14.000 Cable Removal
-
14.001 - Correct cables recovered.
-
14.002 - Withdrawing method correct <br>
-
14.003 - Cable recovered for disposal (Scrap process) correct<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
15.000 Cable & Duct Lay
-
15.001 - Ducts laid or directional drilled at least 1000mm in State Highway<br>
-
15.002 - Ducts laid or directional drilled between 450mm and 1000mm in footway <br>
-
15.003 - Ducts laid or directional drilled between 600mm and 1000mm in roadway <br>
-
15.004 - Duct alignment and configuration correct<br>
-
15.005 - Route position correct according to plan<br>
-
15.006 - Correct cables identified and installed<br>
-
15.007 - Cable ends sealed with heatshrink<br>
-
15.008 - Warning tape installed<br>
-
15.009 -Buried cable crossings - depth and protection<br>
-
15.010 - Reduced cover - protection installed<br>
-
15.015 - Manhole / joint chamber lids free of material / Bung in lifting hole / lid locked<br>
-
15.016 - Fibre Cable Installation: Metallic cable location cable installed<br>
-
15.017 - Location cable separated into RLG pillars either side of fibre joint location (pillar minex applied)<br>
-
15.020 - Bridge crossing: U channel, brackets, covers and pipe galvanised. All anchor bolts and fittings robust and secure<br>
-
15.021 - Route markers installed (Rural only)<br>
-
15.022 - Rural: 1/2 round installation (fibre cable) each side of culvert/ drain crossings<br>
-
15.023 - Rural: 1/2 round installation for rural fibre joint location<br>
-
15.024 - Rural: Private property owner aware cable within property boundaries<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
16.000 Microduct Directional Drill & Lay
-
16.001 - Microducts laid or directional drilled at least 1000mm in State Highway<br>
-
16.002 - Microducts laid or directional drilled between 450mm and 1000mm in footway <br>
-
16.003 - Microducts laid or directional drilled between 600mm and 1000mm in roadway <br>
-
16.004 - Microtrenched microduct laid at least 250mm<br>
-
16.005 - Duct alignment and configuration correct<br>
-
16.006 - Route position correct according to plan<br>
-
16.007 - All microduct ends of runs are sealed with end-caps, then a closure fitted<br>
-
16.008 - Microduct end on customer boundary end (including ROW) capped , wrapped in heatshrink and labelled, then either buried or housed in approved enclosure (eg Pedestal, Handhole). Marker peg left for ROW<br>
-
16.009 - Correct tools available and used for stripping and cutting microduct<br>
-
16.010 - Microduct joints to standard - approved enclosure, correct connectors, earth continuity maintained, water tight etc<br>
-
16.011 - Microduct joints at correct depth and not on a bend<br>
-
16.012 - Microduct joints protected<br>
-
16.013 - Microduct joints external to manholes. At customer boundaries for ROWs<br>
-
16.014 - Direct Install Microduct hauled towards cabinet<br>
-
16.015 - Direct Buried Microduct drilled or laid from cabinet out<br>
-
16.016 - Direct Buried Microduct not through manhole (can be ended in manhole for future use)<br>
-
16.017 - Warning tape installed<br>
-
16.018 - Buried crossings - depth and protection<br>
-
16.019 - Reduced cover - protection installed<br>
-
16.024 - Manhole / joint chamber lids free of material / Bung in lifting hole / lid locked<br>
-
16.026 - 1-way microduct correctly labelled<br>
-
16.027 - Locate peg installed at Buried lateral location or soft surface<br>
-
16.034 - 1-way microduct correctly labelled<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
17.000 Manhole, Joint Chamber & Ducts (new and existing)
-
17.001 - Manhole preparation, bedding, backfill compacted OK<br>
-
17.002 - Manhole sited correctly - To plan and parallel to boundary line<br>
-
17.003 - Manhole correctly sized as per Design Job Specification<br>
-
17.004 - Manhole frames flush to ground, no trip hazard<br>
-
17.005 - Manhole stripped of formwork, no protruding nails left<br>
-
17.006 - Manhole throat (where fitted) correct diameter & does not obstruct access<br>
-
17.008 - Concrete panel joints sealed to prevent silt and water ingress<br>
-
17.010 - All manhole duct entry grouted, duct reamed, sits flush to wall<br>
-
17.013 - Manhole cable management arms installed as required. Cable management correct<br>
-
17.014 - Manhole / joint chamber lids are locked, in working order and rubber bung fitted<br>
-
17.015 - Ducts entry positioned close to adjacent wall for easy cable management<br>
-
17.016 - Ducts sealed where necessary to prevent the ingress of water, moisture, gas, pests into buildings and cabinets<br>
-
17.018 - Cable or sub duct entry sealed to Feeder Duct<br>
-
17.019 - Cable exiting from sub duct sealed<br>
-
17.020 - Unused Feeder Ducts plugged/sealed<br>
-
17.021 - New ducts into existing manholes - correct hole size and location cut in manhole wall for new duct entry<br>
-
17.022 - Direct fibre feed hauling tape installed<br>
-
17.023 - Direct fibre feed hauling tape secured at each end<br>
-
17.024 - Direct fibre feed hauling tape correctly labelled<br>
-
17.027 - Pit correctly bedded - metal surrounding sides of pit compacted<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
18.000 Manhole Cable Management
-
18.001 - All cables managed tidily on brackets and arms<br>
-
18.003 - Fibre cable protection when required-tread plate/split subduct/bandit tape<br>
-
18.004 - Fibre closure secured to manhole wall with bracket<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
19.000 Fibre Jointing & Closure
-
19.001 - Joint Closure secured on manufacturers bracket <br>
-
19.002 - NetMAP label on closure & each cable tail<br>
-
19.003 - Laser safety label (Starburst) visible outside and inside closure<br>
-
19.004 - Heat shrink fittings correct (thermal paint change, glue exuding)<br>
-
19.005 - Mechanical closure fittings correct (fittings, seal)<br>
-
19.006 - Closure pressure valve fitted where closure is capable and has been tested<br>
-
19.007 - Non metallic strength member anchored. Metallic strength member isolated.<br>
-
19.008 - Unused tubes controlled, managed, secured without stress<br>
-
19.009 - Tubes secured onto organiser trays with metal tabbed cable ties, trays not overfilled<br>
-
19.010 - 30mm bending radius unconditionally observed at all locations<br>
-
19.012 - Heat shrink splice protectors secured from movement<br>
-
19.014 - No fibre task waste, all optical (glass) ends safely contained<br>
-
19.019 - Unused tubes controlled, managed, secured without stress<br>
-
19.020 - Heat shrink splice protectors secured from movement<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
24.000 SSA
-
24.001 - SSA cable binding to hardware correct<br>
-
24.002 - SSA cable erected correctly<br>
-
24.003 - SSA cable type and size correct<br>
-
24.004 - Earthing requirements (16mm/pipe/rod/C-Lok each end) correct when needed<br>
-
24.005 - End terminations and cable management correct<br>
-
24.006 - SSA tension & sag & twist (anti dancing) correct<br>
-
24.008 - Recovered wire or SSA uses scrap process<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
25.000 Poles
-
25.001 - All mechanical aids in good working order, regular checks<br>
-
25.002 - Vehicle transporting poles must have racks for pole security<br>
-
25.003 - Pole in good condition, no splits, burs<br>
-
25.004 - Pole manufacture label in place, Pole strength minimum 6kn<br>
-
25.005 - Pole vertical and height correct. Pole positioning and spacing correct<br>
-
25.007 - All new poles have Network pole tag installed 3m above ground<br>
-
25.008 - Breast & Heal block position correct for pull & loading on pole<br>
-
25.009 - Pole hole compacted every 150mm<br>
-
25.010 - Pole safe to climb (hammer/probe/dig)<br>
-
25.011 - All metal plant hot dipped galvanised & CNSP approved<br>
-
25.012 - Plant positioned correctly and safely, plant clearances correct<br>
-
25.013 - Stub poles or staying lines or screw anchors installed correctly<br>
-
25.014 - Unsafe poles labelled / marked for replacement/7 days<br>
-
25.015 - Unsafe poles noted in Hazardous Pole Register<br>
-
25.016 - Deeded poles shown in NetMAP Pole Editor<br>
-
25.017 - All tagged poles in NetMAP<br>
-
25.018 - Traffic Management Plan for pole install/removal<br>
-
25.021 - Network labelling in place to suit requirements<br>
-
25.041 - Pole vertical and height correct. Pole positioning and spacing correct<br>
-
25.042 - All tagged poles in NetMAP<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
43.000 Aerial Service Lead
-
43.001 - Correct Service Lead used<br>
-
43.002 - No In span joints (single ribbonet aerial)<br>
-
43.003 - Tension, sag correct<br>
-
43.004 - Correct fittings used and installed correctly (screw eyes, clamps, pole and buildings)<br>
-
43.005 - Lead-ins enter terminal correctly<br>
-
43.006 - White pipe only on poles, secured correctly<br>
-
43.007 - 600mm saddle spacing (wooden poles) or 1500mm bandit spacing (concrete poles)<br>
-
43.008 - Roadway crossing at correct height<br>
-
43.009 - Loops on poles tied<br>
-
43.010 - Existing double "D" (OA501) or OA45 replaced if altered<br>
-
43.011 - Lightning protection runs >500 metres<br>
-
43.012 - Correct building fittings used and installed correctly (screw eyes, clamps)<br>
-
43.013 - Servi seal secured in upright position and Gel Snap secured horizontally<br>
-
43.014 - Unused pairs capped<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
44.000 Service Lead
-
44.001 - Service Lead terminated correctly<br>
-
44.002 - 20mm pipe connected at Pedestal correctly - (bend into pedestal)<br>
-
44.003 - 20mm pipe connected at BDD correctly (50mm into BDD pit, 450mm deep)<br>
-
44.004 - 20mm pipe connected at RLG correctly (at base of DP, bend if room)<br>
-
44.005 - Individual pipe & cable for installs of <100 metre<br>
-
44.006 - Direct buried cable option (no pipe) for > 100 metre<br>
-
44.007 - Green 20mm installed in trench<br>
-
44.08 - Correct type of pipe above ground level<br>
-
44.09 - Depth correct<br>
-
44.010 - Power/ Gas clearances correct<br>
-
44.011 - Cable & pipe repair correct, and correct type of pipe used<br>
-
44.013 - Pipe connected at ETP correctly (not glued)<br>
-
44.014 - Overlay of Service Lead justified<br>
-
44.015 - Service Lead labelled correctly<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
45.000 ETP
-
45.001 - ETP physical alignment correct, all fittings secure, installation tidy<br>
-
45.002 - ETP location: (buried lead in-300-1500mm) (AE lead in on facia/under eaves)<br>
-
45.003 - ETP recessed (within cladding) location: 900-1500mm<br>
-
45.004 - Aerial lead in to ETP correct eg termination hardware, position, tidy appearance<br>
-
45.005 - 20mm pipe to ETP is white or grey only (not green)<br>
-
45.006 - 20mm pipe end (within ETP) is sealed with silicone and drainage holes left clear<br>
-
45.007 - Premise cabling exit via back of ETP<br>
-
45.008 - Premise cabling exit from ETP is sealed with silicone<br>
-
45.009 - All connections via gel filled connectors<br>
-
45.010 - Protected ETP: Lightning arrestors fitted in areas that require protection<br>
-
45.011 - Protected ETP: Earth wire (6mm/green coating) 100mm min. bend radius observed<br>
-
45.012 - Protected ETP: Earth wire kept straight to Copper or Stainless Steel Earth rod<br>
-
45.013 - Protected ETP: Earth wire connection to earth rod with C-Lok product only<br>
-
45.016 - Unused pairs capped<br>
-
45.017 - Ericsson 5/NEG203200 ETP installed<br>
-
45.018 - Correct ETP installed, tidily and secure<br>
-
45.019 - Locate wire installed, and terminated in ETP with redcaps (Fixed Fibre only)<br>
-
45.020 - Fibre Building penetrations sealed<br>
-
45.021 - Pipe or flexi duct fitted to building is secured and managed correctly<br>
-
45.022 - 50-20mm duct reducer fitted between 50mm underground green duct and 20mm above ground white pipe<br>
-
45.023 - Fixed Fibre or ABF tube housed in 20mm white or grey pipe or UV stabilised flexi pipe where fibre exits through bottom of ETP<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
55.000 Network Records
-
55.006 - Recording made to the appropriate standards<br>
-
55.026 - Correct sized cable has been drawn and labeled as per as-built and matches NetMAP<br>
-
55.028 - Adjoining sheets have been referenced, and references are consistent across FOG Plans<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
67.000 Customer OFDF
-
67.001 - OFDF in a CNSP approved enclosure<br>
-
67.002 - Fibre managed within OFDF OK<br>
-
67.003 - Fibre splicing within design tolerance<br>
-
67.004 - 30mm bending radius unconditionally observed at all locations<br>
-
67.005 - Protective caps on all unterminated connectors <br>
-
67.006 - Connectors cleaned and verified with Fibre Inspection Probe<br>
-
67.007 - Laser Safety labels (1M Safety) at OFDF (inside and front panel)<br>
-
67.008 - Fibre cable entry to building sealed and managed to OFDF OK<br>
-
67.009 - Flexi Pipe protects fibre under the floor or in the ceiling spaces, and is secured to building<br>
-
67.010 - LSZH fibre used<br>
-
67.011 - No fibre task waste, all optical (glass) ends safely contained<br>
-
67.014 - Optical power meter test at the ONT prior to plugging in the SC/A connector <br>
-
67.015 - Netmap label on OFDF lid<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
68.000 Fibre Access Terminal
-
68.001 - Entry tubes sealed<br>
-
68.002 - Two Fibres per tray only<br>
-
68.003 - Lead Cleaned and abraded <br>
-
68.004 - Rayblocks fitted to tubes (90mm) and and shrunk down to seal cable into the access tube (glue extruding)<br>
-
68.005 - Tube holder installed<br>
-
68.007 - Silica Gel Pack installed/replaced<br>
-
68.008 - Triangle symbols on the Dome and Base Match<br>
-
68.009 - All Latches are closed - ports blocked/sealed<br>
-
68.010 - O-Ring Installed<br>
-
68.011 - Fibre correctly managed within FAT and trays<br>
-
68.013 - Slack Managed in fibre management coil (1.5 - 2m)<br>
-
68.015 - Lid Locked and lock bung installed<br>
-
68.016 - 30mm bending radius unconditionally observed at all locations<br>
-
68.018 - Heat shrink splice protectors secured from movement<br>
-
68.019 - No fibre task waste, all optical (glass) ends safely contained<br>
-
68.021 - Fibre strain relief installed correctly<br>
-
68.026 - Tray labelled with cabinet, fibres and customer's address<br>
-
68.029 - Gel seal installed in correct closure entry point<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
72.000 Reinstatement
-
72.001 - Property damage made good<br>
-
72.002 - Ground reinstatement completed around poles<br>
-
72.003 - Reinstatement/ backfill satisfactory around Buried Service Lead<br>
-
72.007 - Excess vegetation removed<br>
-
72.011 - Reinstatement appropriate around cable haul<br>
-
72.014 - Any road markings damaged by works are restored<br>
-
72.017 - Reinstatement complete in Cable well<br>
-
72.018 - Ground reinstatement completed<br>
-
72.019 - Backfill compacted every 150mm<br>
-
72.020 - Surplus soil removed<br>
-
72.021- Reseal completed - Footway/vehicle resurfaced<br>
-
72.022 - Grass reinstated and replanted<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
73.000 Site Tidy
-
73.001 - Site tidy, no task waste - poles<br>
-
73.002 - Site tidy, no task waste - Cabinet internal<br>
-
73.003 - Site tidy, no task waste - Aerial Terminal<br>
-
73.004 - Site tidy, no task waste - Pillar Terminal/IFDB<br>
-
73.005 - Site tidy, no task waste - Pit<br>
-
73.006 - Site tidy, no task waste - PDS Terminal<br>
-
73.007 - Site tidy, no task waste - Aerial Service Lead<br>
-
73.008 - Site tidy, no task waste - Service Lead<br>
-
73.009 - Site tidy, no task waste - ETP <br>
-
73.014 - Site tidy, no task waste - Cable Haul<br>
-
73.017 - Site tidy, no task waste - MDF<br>
-
73.018 - Site tidy, no task waste - Cable well<br>
-
73.019 - Site tidy, no task waste - Cable & Duct Lay<br>
-
73.020 - Site tidy, no task waste - Manholes<br>
-
73.021 - Site tidy, no task waste - SSA<br>
-
73.022 - Site tidy, no task waste - Active Cabinet Battery Enclosure<br>
-
73.024 - Site tidy, no task waste - general<br>
-
73.025 - Equipment area tidy, task waste removed<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
77.000 UFB-Channel Flash 9 Installation
-
77.001 - 50mm of Inner Black Sheath past outer green sheath<br>
-
77.002 - Electrical tape applied over earth connection on Ribbonet cable<br>
-
77.003 - Earth wire managed and secured to pit wall<br>
-
77.004 - Microduct entry through pit wall secured with cable tie (top of drilled hole)<br>
-
77.005 - Heavy duty plastic floor material installed correctly (optional)<br>
-
77.006 - Micro Duct tubes routed correctly in pit - minimum bend radius not exceeded<br>
-
77.07 - All 5mm Microduct tubes have tube ID labels at the external joint<br>
-
77.008 - Velcro ties secured to the pit wall<br>
-
77.009 - Locking collar on closure is secured with locking bolt. ID label facing upwards<br>
-
77.010 - Closure ID label facing upwards<br>
-
77.011 - Correct Microduct connectors used to join and seal Microduct (5mm & 12mm)<br>
-
77.012 - Correct size gas blocks installed on 12mm Microducts outside of closure containing optic fibre cable.<br>
-
77.013 - All spare or unallocated 5mm & 12mm Microducts capped with duct end caps within closure and pit<br>
-
77.014 - All populated Microducts fitted divisible seal. Unused fitted with strain relief plugs or end stops<br>
-
77.015 - Correct size divisible gas seal used on Populated 12mm Microducts inside closure<br>
-
77.016 - Incoming & outgoing fibre cables in correct 12mm tubes<br>
-
77.017 - Closure base 'O' ring clean, dry undamaged & correctly seated. Spare 'O' ring in closure<br>
-
77.019 - Pit lid free of reinstatement materials (T/Seal cone)<br>
-
77.020 - All 5mm Microducts trimmed to 80mm in height from base<br>
-
77.021 - All 12mm Microducts trimmed to 40mm in height from base<br>
-
77.022 - Lid closure labelled correctly with netmap ID and facing upwards<br>
-
77.023 - 12 mm microduct carrying a cable is correctly labelled with netmap elements<br>
-
77.024 - Spiral wrap buffer tube protection installed and secured at the UMS with a cable tie<br>
-
77.025 - Metal lock zip tie securing fibres at base of organiser tray<br>
-
77.026 - Fibre routed and laid up correctly in trays<br>
-
77.027 - All microducts are labelled<br>
-
77.028 - SC Trays labelled on underside of tray with microduct, splitter and splitter leg number, address and distance to customer's site<br>
-
77.029 - Joint bundle wrapped in Eziwrap or A3 - 250 micron clear plastic and secured<br>
-
77.030 - SE Trays labelled on underside of tray with cable ID and distribution fibre designation & Fibre numbers. P touch labels used<br>
-
77.031 - Spiral wrap fan-out cord protection installed<br>
-
77.032 - Splitter and its input leg spice is installed on correct tray<br>
-
77.033 - Splitter fibre splice secured in splice holder<br>
-
77.034 - Figure 8 grommet port seated correctly in base<br>
-
77.035 - Cable sheath between 10mm and 20mm above grommet<br>
-
77.036 - Feeder fibre enters UMS on RHS and transitions to LHS of UMS then enters tray on RHS<br>
-
77.037 - Feeder side fibre labelled "FEED" with critchley labels<br>
-
77.039 - 1.2m of fibre in SC trays<br>
-
77.040 - Uncut buffer tubes stored between verticals within plastic sleeve<br>
-
77.041 - Spur cables, 48F, 116F or microcable installed with 19mm and No. 8 grommet<br>
-
77.042 - Microducts 1 - 26 enter through 3 RH ports (viewed from swing arm)<br>
-
77.044 - 100mm duct capped at pole<br>
-
77.045 - Direct buried ADSS fibre protected at pit entry with 500mm duct<br>
-
77.046 - Minimum bend radius achieved inside pit (149mm for 116f, 110 for 48f)<br>
-
77.047 - ADSS centre strength element cut to 90mm inside closure and secured<br>
-
77.048 - ADSS centre strength element secured to retention clamp<br>
-
77.049 - Correct number of SC trays installed<br>
-
77.050 - Correct number of SE trays installed<br>
-
77.051 - Enclosure support bracket in place<br>
-
77.052 - Tray retention strap in place<br>
-
77.053 - Lid in place on the top SC tray<br>
-
77.054 - Lid in place on the top SE tray<br>
-
77.055 - UMS tray cover in place<br>
-
77.056 - Red duct end caps in place on tubes 53 & 54<br>
-
77.080 - Micro duct tubes routed correctly in pit - minimum bend radius not exceeded - 50mm of inner black sheath past outer green sheath<br>
-
77.082 - Direct buried ADSS fibre protected at pit entry with 50mm duct<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.
78.000 Building Distributor
-
78.001 - Correct reducers used and protection installed, appropriate external pipe and fixings used<br>
-
78.002 - BUDI installed correctly - vertical, lid secure, labelled and coils managed correctly <br>
-
78.004 - Feeder/fibre cables labelled correctly. Incoming fibre secured to anchor point with foam and zip tie<br>
-
78.006 - All microducts labelled, capped and secured to wall or tray in riser<br>
-
78.007 - Microducts trimmed to the correct height 220mm from the base of the cabinet<br>
-
78.011 - Tray retention strap in place<br>
-
78.013 - Two fibres per tray only<br>
-
78.014 - Fibre routed and laid up correctly in tray. All unused connectors capped<br>
-
78.015 - Slack managed in fibre management coil. 30mm bend radius unconditionally observed at all locations<br>
-
78.017 - No fibre task waste, all optical (glass) ends safely contained<br>
-
78.021 - Network labelling in place to suit requirements<br>
-
78.023 - Splitter installed and labelled<br>
-
78.024 - Correct number and type of trays installed. Tray retention strap in place<br>
-
78.026 - Fire & smoke barriers reinstated in accordance to AS/NZS3000 Standard<br>
-
78.029 - GPON feeder fibres to future PON Splitters reserved in Netmap<br>
-
78.030 - MDU Lead-in Cables and IBDN recorded in Netmap <br>
-
78.034 - Duct tap off box secured to wall or tray in riser and labelled correctly. All tubes jointed correctly where they exit the top. Microduct Management Bend back to prevent the EPFU creeping down the riser. Back bend and tie on away side. <br>
-
78.036 - Outer door locks work smoothly and door closes without jamming<br>
-
78.037 - Feeder fibre installed and labelled correctly<br>
-
78.038 - Distribution Frame: Correct Trays installed & labelled<br>
-
78.039 - Distribution Frame: Data card inside drawer and labelled with the splitter, unit, level #<br>
-
78.043 - Correct number of mandrels installed. Patch cords correct length and routing<br>
-
78.044 - Minimum bend radius maintained when drawers are opened and closed<br>
-
78.045 - Splitter installed and labelled, and splitter legs secured in parking bay<br>
-
78.046 - Secured to wall/tray in riser<br>
-
78.047 - Window cut does not exceed the breakout unit<br>
-
78.048 - Cable protection cover installed on unused window<br>
-
78.049 - Gravity loop in place for all cables and secured neatly<br>
-
Add media
-
Comments: Please refer to the relevant task code for any comments.