Title Page
-
Conducted on
-
Prepared by
-
Location
Monthly Site Inspection Checklist
-
Location:
-
Conducted by:
-
Date:
-
Follow-up inspection required:
-
Item #
I - Work Practices
-
Daily Toolbox talks (Tailboards) properly documented
-
Field Level Risk Assessment properly documented
-
Signage (Barriers / Warnings) in place
-
Emergency Numbers displayed
-
Safety Concerns / Issues addressed
-
Emergency exits clearly marked & easily accessible
-
Item #
-
II - WHMIS / TDG / Flammable Cabinet
-
All containers having controlled products (WHMIS) label
-
Safety Data Sheet (SDS) available for each hazardouschemical
-
Safety Data Sheet easily accessible by employees
-
All SDS kept up-to-date (3 years old)
-
Employees trained /informed about hazards related to chemicals
-
Appropriate PPE used while using chemicals
-
Flammables / Corrosives separate-stored in the applicable cabinet
-
Flammable / Corrosive cabinets are grounded properly
-
Nothing is stored over the flammable cabinets
-
Solid waste containers labelled
-
Hazardous waste containers labelled
-
Item #
III - Personal Protective Equipments (PPE)
-
CSA approved footwear worn as required
-
CSA / Client approved class hardhats used as required
-
PPE fitted and worn properly ie: fall protection
-
CSA approved Safety Glasses/Goggles worn as required
-
Suitable gloves for the activity
-
High visibility vests / coveralls used as required
-
Respirator: Fit Tested, users trained and stored properly
-
Face shields worn appropriate to the task ie: Grinding / Welding
-
Hearing protection worn as required
-
Other PPE worn as required ie barrier cream, leathers, etc
-
Signs posted at locations where protection is required
-
Item #
IV - Forklift and Crane Operation
-
Only trained & certified Froklift operators are operating the forklift
-
Forklift inspection logbook filled as required
-
Crane inspection logbook filled as required
-
Crane lift plan prepared for lifting > 15 000 lbs
-
Crane is operated by only trained crane operator
-
Rigging only done by qualified person
-
Slings and Rigging (Labelled, Secured and Inspected)
-
V - Housekeeping
-
Walkways free of tripping hazards ie: extension cords, welding cables
-
Accumulation of combustile materials (boxes, paper, etc.)kept to a minimum in inappropriate areas
-
Walkways free of chemicals, oils or water
-
Garbage bins are cleaned at the end of the day
-
Lunch room clean and tidy
-
Areas free of nails and protruding objects
-
Exactos kept in down and locked position when not in use
-
All openings properly covered and protected
-
Storage/metal shelves bolted down and properly secured to prevent them from falling over
VI - Material Handling
-
Materials stacked / stored to prevent sliding or collapsing
-
Equipment available to assist in moving materials (ex.dolly)
-
All employees using an electric pallet lift or a lift truck certified
-
Employees received Safe Lifting/Back Safety Training
VII - Equipment / Tools
-
All grinder, saw, drill gruards in place and stored properly
-
Disc / Stone size is correct for the grinder
-
Powe, hydraulic, pneumatic tools used in a safe manner
-
Whip checks in place for pneumatic tools
-
Item #
VIII - Machine Guarding
-
Machines/equipment/hand tool with exposed moving parts have appropriate guardings
-
Indication of what PPE to use and warning signs on machine
-
Operational emergency stop well identified on the machine
-
Shield or guards in place to prevent and protect the employees from flying debris from machine
-
Welders are using double protection (safety glasses and face shield)
-
Item #
IX - Accidents: Medical Aid
-
Lost Time
First Aid
-
Nearmiss
-
Weekly first aid inspection is in place & complete
-
Emergency equipment readily available
-
All accidents & incidents are reported
-
Item #
X - Emergency Preparedness and Response
-
First aid kit seal is intact. Inventory contents if broken
-
First aid / RTW report forms available in the first aid room
-
List of the first aiders posted in the first aid room / job board
-
Date of first aiders' certification is adequate
-
A first aider is available at all times
-
First aid room / kit is tidy and organized
-
First aid kits accessible and clearly identified
-
First aid register available
-
Spill kits available near the chemicals use
-
Eye wash bottles / station is located near the chemical use
-
Eye wash station(s) available and inspected
-
If eye wash station is not connected to the municipal water system, expiration date on the equipment or the date of the last liquid change adequate
-
Fire extinguishers are in working order and inspected
-
Fire extinguishers clearly identified (sign)
-
Employees trained in the use of fire extinguishers
-
Fire safety / evacuation plan established
-
Operating fire/smoke detection system functionnal
-
Written emergency preparedness / medical emergency plan in place
-
Item #
XI - Electrical
-
GFCI's in place when required
-
Circuit breakers or fuse panels properly labeled, kept closed and accessible
-
Extension cords kept out of wet areas
-
Certified electricians used for electrical work
-
Appropriate permanent wiring preventing the excessive use of extension cords
-
Switches, circuit breakers and switchboards installed in wet locations enclosed in weatherproof enclosures
-
Cords, panels, receptacles and plugs in good condition
-
Item #
XII - Compressed Gas Cylinders
-
Oxy & Acet are stored separately from each other
-
Bottles are properly secured
-
Item #
XIII - Welding / Hot Work / Fire Protection
-
Fire station / extinguishers clear of clutter
-
Inspection and tags up to date
-
Welding screens used
-
Hot work permits in place for the activity / current
-
Flash arrestors in place
-
Equipment available ie fire blankets, metal bucket, fire extinguishers, etc
-
Item #
XIV - Confined Space and Rescue
-
Entry permit, filled out properly by competently trained person
-
Rescue plan available
-
Entry permit posted outside the confined space
-
Item #
XV - Fall Protection
-
Fall protection used above 3m (10 feet)
-
All openings are covered with a guardrail
-
Written fall protection plan in place for work with no permanent guardrails
-
Handrails / Guardrails installed properly
-
Proper anchor points having capacity of 5000 lbs
-
Fall protection equipment inspected / maintained properly
-
Plywood covered openings appropriately marked
-
Item #
XVI - HSE Documentation / Work Practices
-
Tailboards properly documented
-
FLRA filled out / applicable for the task
-
Emergency numbers posted at conspicuous locations
-
Emergency escape routes designated and posted
-
Last version of the HSE policy posted at the site
-
Safety prevention program posted and available for consultation by employees and staff
-
Item #
-
XVII - Other
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
If any of the above items were checked as "No". A follow-up plan must be set up for it
-
Correctives actions (CA): CA to be SMART (Specific, Measurable, Achivable, Realistic, Time sensitive)Each cause has to be link to a corrective action identified in the analysis table
-
Item #
Corrective / Preventive Measures
-
Responsible
-
Time Frame
Identification # (Information to be transferred in the Corrective Action Tracking Spreadsheet
Starting
-
Ending
-
- CA -
-
- CA -
-
- CA -
-
- CA -