Title Page
-
Customer
-
Location
-
Country
-
Assigned Commissioner/Technician
-
Start Time
Product
-
Supernova Model
- DCF1 - 60 kW split charge
- DCF1 - 60 kW non-split charge
- DCF2 - 60 kW
- DCF2 - 120 kW
- DCF2 - 150 kW
- DCF4 - 220 kW
-
Serial Number (S/N)
-
Part Number (P/N)
Health & Safety
-
Has the installation information been reviewed prior to carrying out the work? (Geolocation, location pictures, supply cut points, specific security procedures, emergency procedures, existence of flammable/explosive gases).
-
Do you have isolated tools, correct Personal Protection Equipment(PPE), LOTO locking kit and everything in good condition to carry out the job safely?
-
Is the condition of the PPE correct: has the "blow test” been carried out on the dielectric gloves?
-
Are the work area conditions adequate to guarantee your safety? (visibility, weather (rain, storm, strong winds, etc)
-
IMPORTANT: check the conditions of the input cables in the charger. If they are not in good condition, STOP work.
Mechanical Inspection
-
External Overall Visual Inspection
-
Will it require a further visit?
-
Verify correct clearance around the charger
- DCF1: MINIMUM 70cm front, 40cm sides
- DCF2: MINIMUM 70cm front, 40cm sides, 100cm behind
- DCF4: MINIMUM 70cm front, 40cm sides, 100cm behind
-
Verify presence of left door lock and keys
-
Internal general visual inspection
-
Verify correct anchorage to the floor
-
Has the CMS been installed for the cables on both sides?
-
Verify inlet power cable entry plate with grommets fitted
-
Verify scupper covers closed / inlet cable cover or panel A cover is in place
-
Verify the charger is free from any traces of condensation or water ingress
-
Verify the weather stripping seal in all 3 doors
-
Quantity of Power Modules installed
-
Check correct closure of all doors
-
Has this been rectified?
-
Verify the presence of air filters on each side
-
Front door sensor position check
-
Front door rod guide check
-
EV gun stickers installed?
DCF1
DCF1 Specific check
-
Check QPM / back planes / copper bars
-
Has this been rectified?
Additional issues/comments
-
Additional issues/comments
DCF2
DCF2 Specific check
-
Verify that Panel A protective rubber strip is present
-
Check all DC cables (from DC bus bar to DC contactor) for damage/cuts
Electrical Inspection
-
Verify correct connection of input cables (L1-L2-L3-N-PE)
-
Has this been corrected?
-
Check the input cable section meets local & installation requirements
-
Verify tightness and connection of all internal cables
-
Has this been corrected?
-
Verify the presence of protections in main breaker panel
- MCB
- RCD
- SPD
- Fuse
- Other
Power up
-
Are the main power cables in the correct order?
-
Has this been rectified?
-
Are Supernova's main switch and protections OFF?
-
Turn on external main breaker
-
Has voltage been verified? (values to be provided on next page)
-
Turn on internal protections
-
Turn on Supernova main switch
Voltage checks
-
Input AC Voltage: L1-L2 (400V +/- 10%)
-
Input AC Voltage: L1-L3 (400V +/- 10%)
-
Input AC Voltage: L1-N (230V +/- 10%)
-
Input AC Voltage: L1-Earth (230V +/- 10%)
-
Input AC Voltage: L2-L3 (400V +/- 10%)
-
Input AC Voltage: L2-N (230V +/- 10%)
-
Input AC Voltage: L2-Earth (230V +/- 10%)
-
Input AC Voltage: L3-N (230V +/- 10%)
-
Input AC Voltage: L3-Earth (230V +/- 10%)
-
AC Voltage: Earth - Neutral (+/- 0V)
Update checks
-
Software version on arrival (Factory SW version)
-
Updated Software Version
-
Verify correct functionality of the 3 door sensors
-
Check HMI functionality
-
Has this been rectified?
-
Verify RFID reader functionality
-
Has this been rectified?
-
Verify beacon, holster & courtesy lights functionality
-
Has this been rectified?
-
Verify cooling fans functionality and noise
-
Has this been rectified?
Meter configuration
-
AC meter configuration checked?
-
Was AC meter configuration correct?
-
Has this been rectified?
-
Bender isometers configuration checked?
-
Were both Benders configured correctly? (or 1 in the case of DCF1 SN60)
-
Has this been rectified?
-
Trafox meter configuration checked? (DCF2 only)
-
Was Trafox configuration correct? (DCF2 only)
-
Has this been rectified?
Point of Sale
-
Point of Sale installed?
-
Brand:
-
Brand and model:
-
Payter SIM & SAM cards fitted?
-
Can the POS be verified as working correctly?
Connectivity
-
Wallbox telemetry connected
-
OCPP Connection method
-
Model
-
Configured from factory?
-
Have you configured it?
-
Which configuration (.tar) file has been used?
-
Was it configured correctly?
-
Which configuration (.tar) file has been used?
-
Configured
-
Signal strength (in dBm)
Charge tests
EV test
-
Type of charging test
-
Brand & model of EV(s) used
-
Charging session - Hose 1 <br>
-
Charging session - Hose 2
-
Split charge test (where possible)
Customer requirements
-
Charger left powered on?
-
Authorisation method
-
CPO URL and Charger ID
-
Has the connection with the client backend been validated?
-
Web Manager power limit set
Final Details
-
Add photos showing Supernova location
-
Add photos showing Supernova interior and exterior (Front, left and right side)
-
Add photo of sticker on the back of router
-
Add photos of the breaker panel and location
-
Commissioning validated by Wallbox DC Support? <br>+34 950 72 00 29 Global support / +61 2 9129 8353 Oceania support
-
OCPP connectivity also validated by Wallbox DC Support?
-
Call Wallbox DC Support before leaving site
-
OCPP connectivity also validated by Wallbox DC Support?
-
Additional comments
Acceptance
-
Customer signature
-
Wallbox Commissioner/Technician signature
-
Wallbox certification ID number (found on your training certificate)