Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Plot Number
- 1.1
- 1.2
- 2.1
- 2.2
- 3.1
- 3.2
- 3.3
- 4.1
- 4.2
- 4.3
Weekly Fit Out Progress
Pre Fit Out Level 14
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 14
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All Trades)
Level 13
Pre Fit Out
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 13
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All Trades)
Pre Fit Out Level 12
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 12
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All Trades)
Pre Fit Out Level 11
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 11
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All Trades)
Pre Fit Out Level 10
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 10
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 09
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 09
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 08
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 08
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 07
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 07
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 06
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 06
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 05
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 05
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 04
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 04
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 03
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 03
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 02
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 02
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)
Pre Fit Out Level 01
-
Screed
-
Sole plates installed
-
Shutter and back fill
-
Flat Duct Install
-
SVP & RWP floor plate confirmation
Apartment Fit Out Level 01
-
Pre Drylining hold point
-
Drylining load out
-
Utility cupboard- Drylining and skim
-
Partition & 1st fix side
-
Noggins
-
Mechanical 1st Fix
-
Lagging
-
Electrical 1st Fix
-
Internal wall fire stop
-
Wall closure
-
2nd Fix Drylining
-
Apartment letter box fire stopping
-
Fire tape and Fire mastic (Above Ceiling)
-
Ceiling grid install
-
Fit sprinkler head and install
-
NHBC void inspection
-
Board Ceiling
-
Tape and Joint
-
Sanding down
-
Wedi/Duka board floor build up
-
Sealer/Mist coat
-
Bath Support batten
-
Kitchen Pre-Plumb
-
Shower tray/ Bath / WC basin install
-
HIU & Raditor installation
-
Kitchen tiling
-
2nd Fix plumbing
-
Water on / Flood test / SVP test
-
2nd Fix Electrical
-
Permanent Power Live Test
-
Pre Dec / Make good drylining
-
Pre Dec hold point
-
Pre Dec clean
-
Final Decoration & 1st Coat FED
-
Final Fix Electrical
-
Final Fix Plumbing
-
Builders clean
-
Test smoke head & Sounders
-
Access control system commissioning
-
Commission heating and cooling system
-
Domestic water (Temps & Flow rates)
-
FCU secondary air balancing
-
Fire Alarm system commissioning
-
Flood test condense from FCU
-
Flush, Clean and dose apartment
-
Heating and cooling controls commissioning
-
HIU Commissioning
-
MVHR vent commissioning
-
TV system commissioning
-
Functionality testing
-
HIU Ceiling grid installation
-
Carpet install
-
Fit wardrobe and HIU front
-
Mastic
-
BCSL snag
-
De snag (All trades)