Slope Design
-
Have you confirmed the slope has been designed by a competent person using a defined engineering process?
Design Execution
-
Does the execution of the slope design align with the engineered design?
-
Have you completed the wall sign off process?
-
Have you implemented wall control blasting in accordance with the blast design?
-
Have you implemented batter angles that conform to the approved pit design?
Operating Practices
-
Have you completed a risk assessment and implemented controls for potential rock fall or ground failure?
-
Are you familiar with the Ground Control Management Plan?
-
Are you familiar with the systems in place to detect and react to potential ground instability and the normal wall stand off distance?
-
Have you completed Ground Control Awareness Training?
-
Have you used delineation controls to prevent personnel and equipment entering the area?
Monitoring and Response
-
Do you have a process to regularly interpret monitoring data and communicate ground control performance?
-
Do you have an up to date Ground Control Management Plan?
-
Do you have appropriate monitoring systems in place?
-
Do you have a Trigger Action Response Plan in place?
-
Additional comments/observation
Observation
-
Add observations/comments here.
Signatures
-
I hereby certify that all information is accurate and that an actual inspection was conducted.
-
Auditor's Printed Name & Signature