Title Page
-
Principle Contractor/Contractor Name
-
Project Title / Description of Work
-
Site Location
-
Expected program start date
-
Expected program finish date
Plan
-
Are Key Dates identified and realistic in timescale on the CPP?
Working Together
-
Are project team members key roles and responsibilities clearly laid out?
-
Is it clear which risks are being managed by EDC and which the contractor is managing ?
-
Is it clear how will everyone on site will receive Health & Safety information?
-
Has the contractor got adequate Supervision and monitoring planned?
-
Is the lines of communication to any sub-contractors of the CCP clear?
Organise
-
Is there a layout plan for the site, e.g. Vehicle parking/movements, welfare?
-
Has appropriate signing (including safety signs), Lighting and Guarding been considered for the site?
-
Are welfare arrangements adequately planned ?
-
Has adjacent site use been considered, e.g. HGV's obstruction, evacuation of?
Management of Risks
-
Have CDM 2015 Schedule 3 risks been identified?
-
Work which puts workers at risk of burial under earthfalls, engulfment in swampland or falling from a height, where the risk is particularly aggravated by the nature of the work or processes used or by the environment at the place of work or site.
-
Work which puts workers at risk from chemical or biological substances constituting a particular danger to the health or safety of workers or involving a legal requirement for health monitoring.
-
Work involving ionizing radiation requiring the designation of controlled or supervised areas under regulation 16 of the Ionising Radiations Regulations 1999(1).
-
Work near high voltage power lines.
-
Work which exposes workers to the risk of drowning.
-
Work on wells, underground earthworks and tunnels.
-
Work carried out by divers having a system of air supply.
-
Work carried out by workers in caissons with a compressed air atmosphere.
-
Work involving the use of explosives
-
Work involving the assembly or dismantling of heavy prefabricated components.
-
Are any permit requirements clearly laid out?
-
Are site specific risk assessments and controls adequate for task being carried out?
-
If Temporary Works are required, has the Temporary Works design been checked by a competent person, registered on a Temporary Works register and been approved by the Temporary Works Coordinator?
-
Has the contractor an up to date site specific risk assessment that adequately identifies safety and environmental hazards?
Emergency Plan
-
Is there a process in place for reporting injuries?
-
Are response procedures in place for all identified emergency situations?
Conclusion
-
Overall is the CPP suitable and sufficient for the task being carried out
-
Question set completed by:
-
Signature