Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site/Project Information
Site/Project Information
-
Please enter details of the project. (enter project type, duration, location, environment). Please confirm activities being undertaken at time of audit.
-
How many persons are working on this project at the TIME OF THE AUDIT and what type of work are they carrying out?
-
What resources are being used on the project at the TIME OF THE AUDIT?
-
Does the contractor hold a current CHAS certificate?
1.0 Site Documentation.
-
Is this section part of today's audit?
-
1.1 Is there a company general Heath & Safety Policy Statement displayed on site and available for inspection?
-
Is the policy signed & dated?
-
When was the policy last reviewed?
-
Has the policy been communicated to the workforce?
-
1.2 Is there a detailed H&S management plan available for the project?
-
In accordance with RAMs?
-
1.3 Has the project been notified to the appropriate authority?
-
Is a copy of the F10 displayed?
-
Upload Media.
-
1.4 Is there a Section 80 and 81 in place for this project?
-
Upload Media.
-
1.5 Is there a copy of the Refurbishment or Demolition Asbestos Survey on site?
-
1.6 Has a job specific Method Statement been developed for the work in progress?
-
Is it adequate for the work in hand?
-
1.7 Are there adequate risk assessments available for the work being undertaken on this project?
-
1.8 Are there adequate COSHH assessments for all hazardous substances on site?
-
1.10 Is there a copy of the employers liability insurance displayed on the wall?
-
What is the expiry date?
-
1.9 Is there a H&S poster displayed on the wall?
-
Has it been completed?
-
Upload Media.
-
1.11 Is there an adequate format for recording day-to-day activities and information on site?
-
Upload Media.
-
Observation relevant to section 1.
-
Upload Media.
2.0 Site organisation/Security
-
Is this section part of today's audit?
-
2.1 Does the site have a secure boundary with controlled access points?
-
Photo.
-
2.2 Are there adequate warning signs to comply with the Safety Signs Regulations?
-
Photo.
-
2.3 Is there an adequate emergency/fire/traffic management plan available for the site?<br>(A visual plan is acceptable)
-
Photo.
-
2.4 Does the site have adequate controls in place to prevent unauthorised access to the site?
-
Are they sufficient?
-
Upload Media.
-
2.5 Are site inductions being carried out and recorded?
-
2.6 Are regular Tool Box Talks being carried out to ensure good communication on all matters?
-
Are they sufficient?
-
2.7 Have any temporary works been identified?
-
Have the temporary works been designed and checked?
-
Can it be confirmed that suitable arrangements are in place for a Temporary Works Co-ordinator and Temporary Works Supervisor (including Heras fencing).
-
Upload Media.
-
Is there a permit to load/unload the temporary works?
-
Observations from section 2.
3.0 Competence and Training.
-
Is this section part of today's audit?
-
3.1 What is the total number of DEMOLITION OPERATIVES on site, including agency staff?
-
3.2 What is the total number of DEMOLITION PLANT OPERATIVES on site, including agency staff?
-
3.3 What is the total number of SUPERVISORS on site, including agency staff?
-
3.4 Are all DEMOLITION OPERATIVES and AGENCY STAFF adequately trained with CCDO competency based qualifications?
-
3.5 Are ALL DEMOLITION PLANT OPERATIVES and AGENCY STAFF adequately trained and in possession of CPCS (demolition specific) cards / qualifications
-
3.6 Does the company have a current training matrix for all employees?
-
Can the Site Supervisor access the matrix?
-
3.7 Are the site supervisors / managers suitably qualified to undertake their roles, with the appropriate level CCDO card (Gold & Black)?
-
Upload Media.
-
3.8 Have ALL operatives undertaken a recognised ASBESTOS AWARENESS or ASBESTOS REMOVAL course to a recognised standard?
-
3.9 Have ALL operatives undertaken a recognised Demolition Health & Safety Awareness course?
-
3.10 Does the company have access to competent H&S advice?
-
List providers of H&S advice and qualifications.
-
3.11 Have sub-contractors been pre-vetted at Head Office, prior to engagement?
-
Observations from section 3.
4.0 Inspections & Maintenance.
-
Is this section part of today's audit?
-
4.1 Does all the plant and equipment have relevant test certificates and inspection records (e.g. PUWER, LOLER)?
-
Have all maintenance and pre start inspections been carried out and recorded?
-
Upload Media.
-
4.2 Is all the plant and equipment used on site detailed on the site register?
-
4.3 Is the plant and equipment considered to be adequate and in a suitable condition for the work being undertaken?
-
Upload Media.
-
4.4 Have all the relevant electrical tests been undertaken on the equipment, including the welfare unit?
-
Upload Media.
-
Observations relating to section 4.
5.0 Working at height.
-
Is this section part of today's audit?
-
5.1 If work at height is necessary, has safe access been provided in line with the Working at Height Regulations?
-
Is it in accordance with the RAMS?
-
5.2 Where a scaffold has been provided, does a competent person inspect it on a regular basis?
-
Upload Media.
-
Is it a least every 7 days?
-
5.3 Where an aluminium scaffold tower is in use, has it been erected and inspected by a competent person prior to use?
-
Is the tower inspected before every use?
-
Upload Media.
-
5.4 Where fall arrest equipment is in use, has it been inspected, certificated and checked prior to use, and the findings recorded by a competent person?
-
Name of competent person.
-
Upload Media.
-
5.5 Have all operatives that are required to work at height had sufficient training?
-
5.6 Is a rescue plan in place?
-
Is the rescue plan sufficient?
-
Upload Media.
6.0 Asbestos removal NNLW (Notifiable Non Licenced Work and / or NLW (Non-Licenced Work)
-
Is this section part of today's audit?
-
Are there NNLW or NLW being carried out?
-
6.1 Can it be confirmed that suitable arrangements are in place within the H&S Policy?
-
6.2 Is there a NNLW Notification Number.
-
Enter Notification Number.
-
Upload Media.
-
Have external sub-contractors been engaged to undertake the Asbestos work?
-
6.3 Are all operatives adequately trained in NNLW asbestos techniques to IKATA standards?
-
6.4 Are operatives wearing the correct PPE/RPE for the work they are undertaking, and is it identified in the RAMS?
-
Upload Media.
-
6.5 Has the PPE/RPE been face fitted correctly?
-
6.6 Is the area suitably demarcated and are sufficient asbestos warning signs displayed?
-
Upload Media.
-
6.7 Are operatives handling ACM's in accordance with the RAMS?
-
6.8 Is the waste skip secure and lockable?
-
Upload Media.
-
6.9 Are the waste disposal documents being recorded correctly?
-
Upload Media.
-
6.10 Are the exposure records available on site?
-
Observations relating to section 6.
-
Upload Media.
7.0 Licenced Asbestos Removal
-
Is this section part of today's audit?
-
Are there Licenced Works being carried out?
-
7.1 Confirm that suitable arrangements are in place within the Health & Safety Policy.
-
7.2 If asbestos work is complete, review the clearance certificate. Is it satisfactory?
-
7.3 Is the ASB5 notification available for inspection?
-
Upload Media.
-
7.4 Is there a detailed method statement for the asbestos removal operation available for inspection?
-
7.5 Is the decontamination unit in position, fully certificated and operational?
-
Upload Media.
-
7.6 Are the asbestos removal works fully enclosed, with a 3 stage air lock and adequate viewing panels?
-
7.7 Are there records of air monitoring, clearance certification, face fit tests, operative and supervisor training, medicals and equipment inspections?
-
7.8 If removal works are being carried out, can you confirm the competence of the Sub-Contractor and Works Supervisor?
-
Observations relating to section 7.
8.0 Health Surveillance.
-
Is this section part of today's audit?
-
Are the employees using equipment that causes HAV concerns?
-
8.1 Has an adequate evaluation of Hand Arm vibration been carried out?
-
8.1.1 Are records being taken of operatives use?
-
8.2 Has a Hand Arm Vibration risk assessment been carried out?
-
8.3 Has an adequate evaluation of noise generating activities been carried out?
-
Are any hot works being carried out?
-
8.4 Have all operatives engaged in hot works had recent lead medicals, as well as being identified in the risk assessment?
-
8.5 Are suitable controls in place to protect operatives from health hazards i.e. ventilation, screening, suitable equipment, work rotation etc.?
-
8.6 Are operatives using PPE/RPE correctly/in line with the hazardous activities being undertaken?
-
8.7 Has RPE been correctly Face Fitted for the task in hand, including disposable masks?
-
8.8 Has the appropriate PPE/RPE been issued in accordance with RAMS?
-
8.9 Are there adequate arrangements in place for manual handling operations?
-
8.10 Confirm arrangements are in place (by means of a 'Service Agreement' or 'Letter of Appointment' to ensure compliance with health surveillance procedures for exposure to;<br>General Well Being.<br>Noise.<br>Dermatitis.<br>Repertory Issues.<br>Vibration.<br>Vision.<br>Musculoskeletal.
-
8.11 Does the company operate an Occupational Health Policy?
-
Observations relating to section 8.
-
Upload Media.
9.0 Lifting Operations.
-
Is this section part of today's audit?
-
Are there any lifting operation involved at the time of the audit?
-
9.1 Has a suitable lifting plan and method statement been developed for specific lifting activities?
-
9.2 Have Risk Assessments been completed for the lifting works?
-
9.3 Are persons carrying out the lifting operations competent to carry out their duties? i.e. appointed persons, lifting supervisor, slinger-signaller?
-
9.4 Are all appliances inspected weekly and thoroughly examined every 12 months by a competent person?
-
Upload Media.
-
9.5 Does the lifting gear/chains etc, on site have current test certifications?
-
Upload Media.
-
9.6 Are lifting operations being carried out in line with the lift plan?
-
9.6.1 Are the operations being conducted safely and meet current regulatory requirements?
-
9.7 Can you confirm that suitable arrangements are in place within the Health & Safety Policy?
-
Observations relating to section 9.
-
Upload Media.
10.0 Emergency Procedures and Equipment.
-
Is this section part of today's audit?
-
10.1 Is there adequate provision for first aid arrangements?
-
10.1.1 Name of first aider(s)?
-
10.2 Is a first aid kit on site which conforms to BS 8599 and it's contents all in date?
-
Upload Media.
-
10.3 Is there an emergency evacuation plan / procedure available for inspection?
-
Upload Media.
-
10.4 Is there a clearly marked muster/fire assembly point?
-
Upload Media.
-
10.5 Are there clearly marked fire points situated in prominent positions?
-
Upload Media.
-
10.6 Are all fire extinguishers suitable for the specific work areas and are they maintained correctly?
-
Upload Media.
-
10.7 Are there satisfactory arrangements for recording, reporting and investigating accidents and RIDDOR incidents?
-
Review and comment on recent accidents, investigations and remedial actions.
-
Observations relating to section 10.
-
Upload Media.
11.0 Demolition / Dismatling.
-
Is this section part of today's audit?
-
11.1 Are the correct demolition / dismantling procedures being carried out in accordance with the RAMS?
-
11.2 Are operatives / plant operators using the correct plant and equipment for the work in hand in accordance with the method statement?
-
11.3 Are hazardous working areas suitably cordoned off and / or controlled by a banksman?
-
11.4 Are all operatives working from a safe access point?
-
11.5 Are exclusion zones being correctly established and controlled in accordance with BS6187?
-
11.6 Are there Disconnection Certificates for Utilities?
-
Observation relating to section 11.
-
Upload Media.
12.0 Environmental issues.
-
Is this section part of today's audit?
-
12.1 Is dust being kept to a minimum and is dust suppression being used when required?
-
Upload Media.
-
12.2 Have all waterways, surface water drains, and sewers been identified, with precautions in place to avoid contamination of water courses etc.?
-
Upload Media.
-
12.3 Are nuisance noise levels and activities kept to a minimum and controlled to avoid problems to surrounding areas?
-
12.4 Are all other environmental issues affecting this project being handled in an environmentally safe manner (including bats, newts, flora and fauna)?
-
12.5 Does the company have an environmental statement in place?
-
12.6 Does the company have access to competent environmental advice?
-
Name of source of competent advice.
-
12.7 Does the company train employees on environmental issues? What evidence is available?
-
Comments.
-
12.8 Are all work area access and egress points clear of debris, cables, equipment etc.?
-
Observations relating to section 12.
-
Upload Media.
13.0 Welfare Arrangements.
-
Is this section part of today's audit?
-
13.1 Does the site have adequate toilet, washing and drying room facilities?
-
Upload Media.
-
13.2 Are there adequate provisions for both men and women if necessary?
-
13.3 Are welfare facilities clean, tidy and well provisioned?
-
Upload Media.
-
13.4 Is there adequate provision for drinking water?
-
Upload Media.
-
13.5 Are there adequate provisions for the preparation and eating of food?
-
Upload Media.
-
13.6 If the welfare is provided by a principle contractor, does the demolition contractor have the responsibility to maintain the standard of the welfare facility?
-
13.7 Can it be confirmed that suitable arrangements are in place within the Health & Safety Policy?
-
Observations relating to section 13.
-
Upload Media.
14.0 Waste Mangement
-
Is this section part of today's audit?
-
14.1 Is there a structure in place to adequately monitor, record and manage demolition arising's? i.e. DRIDS (Demolition & Refurbishment Information Sheets) system?
-
14.2 Is there an adequate register in place to record the movement of all materials from site?
-
14.3 Confirm the companies EA Waste Carriers Licence, Registration Number and Exp date.
-
Comments.
-
14.4 Is there a Materials Recovery Index % available for the project?
-
14.5 Is the waste retained on site stored in a safe manner prior to removal form site?
-
Upload Media.
-
14.6 Is waste being segregated into appropriate areas or containers to avoid unnecessary build up of waste materials?
-
Upload Media.
-
14.7 Is hazardous waste being correctly identifies, handled and disposed of?
-
Upload Media.
-
Observations relating to section 14.
-
Upload Media.
15.0 Monitor Observe Review Record (MORR)
-
15.1 Are there suitable arrangements in place, with supporting evidence, of regular performance reviews for health & safety e.g. workplace inspections, site inspections, completed audits, action plans for improvement, discussions/reports to senior managers, directors input etc./?
-
Comments.
16.0 Consultation.
-
16.1 Are systems in place to ensure effective two way communication between all employees and stakeholders, including non English speakers and those with communication difficulties?
-
Add media
-
16.2 Are there adequate systems in place which enable co-operation and co-ordination between differing contractors on site if needed?
-
Add media
-
16.3 Confirm that procedures are in place to communicate Heath & Safety issues with the workforce.
-
Add media
-
Observations relating to section 16.
Sign off.
-
Name of auditor.
-
Signature.
-
Name of Site Representative.
-
Signature.