Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
PROCEDURAL CHECKLIST
-
In use
VERIFICATION CHECKLIST
-
In use
TEST RESULTS
-
Attached to checklist
NON-CONFORMANCE
-
Identified by Contractor
NON-CONFORMANCE REPORT
-
Submitted
SETTING OUT Clause R 32.8
-
Services identified and protected
-
Alignment levels and grade set out correctly
MATERIALS Clause R 32.4
-
-
Pipe type and class
-
-
Pipe diameter
-
Bedding complies with Australian Standards
-
Selected backfill complies with As 3725
-
Ordinary backfill complies with R 23
TRENCH EXCAVATION Clause R32.9
-
-
Water diversion adequate
-
Embankment at correct height
-
Location correct
-
Trench walls vertical.
-
Trench width > pipe diameter plus 600 mm
-
Shored depth > 1.5m
-
Sides benched depth > 1.5m
TRENCH BASE Clause R 32.10
-
Base compacted to 95% standard
-
Foundation acceptable CBR > 8
-
Rock encountered
-
Additional excavation approved.
-
Replaced material density tested 96%
INSTALLATION Clause R 32.13,14 & 15
-
Bedding layers 150mm
-
Bedding cohesive 95% RD
-
Bedding cohesion less 70% density index.
-
Vibrating equipment
-
Pipes laid correctly from downstream.
-
Pipes joined correctly
-
Select backfill layers 200mm depth
-
Select backfill 95% relative density.
-
Select backfill 70% density index.
-
Ordinary backfill layers 200mm depth
-
Ordinary backfill 95% density standard.
-
End wall construction - pipes grouted.
-
Finished line and level 10mm tolerance.
NON-CONFORMANCE
-
Identified by audit
-
Report requested.
-
Signature