Information
-
Site Address
-
Job No.
-
Conducted on
-
Prepared by
Safety/General
Carpenter Details
-
Carpenter Company used on this job?
- Procut Building
- Dreamworks
- Liverpool
- Skinner Constructions
- Lifestyle
- Westbourne
- Other
-
Other, please note carpenter company if not on list.
General/Safety
-
1.01 Have you received a copy of the bracing detail? (Located in Job file under Construction/Bracing Detail)
-
1.02 Is site fencing intact? (No Damage)
-
1.03 Was Gate Locked?
-
1.04 Has all rubbish been placed in designated area including food scraps?
-
1.05 Has Timber Clean been conducted?
-
Book Timber Clean
Ground Floor
Pre Brick/Frame Inspection
-
1.01 Have all steel beams been adequately propped by scaffold?(T-bars over 3.6m to be propped by scaffold)
-
1.02 Have all trusses been installed?
-
1.03 Have all remaining timbers been stacked neatly?
-
1.04 Have you confirmed front entry door Brick dimensions?(note: verify dimensions for pivot door)
-
1.05 Has steel posts been braced within straps and blocked out with timber?
-
105.1 Have all bracing straps been tightened and secured to framework?
-
1.06 Are steel posts adequately bolted/welded?
-
1.06.1 Are all windows/sliding doors installed?
-
1.07 Will top plates to steel posts interfere with cornice/square set?(check type of cornice)
-
1.08 Are all dyna bolts adequately secured? (check for adequate washers)
-
1.09 Are all noggins in place?
-
1.10 Have bulkheads been installed correctly? (Note: Some Bulkheads to be supplied by frame manufacturer and installed by frame carpenter)
-
1.11 Have all windows been installed with galvanized bullet head nails? (note: collated framing nails are not acceptable)
-
1.12 Are sliding door sashes stacked neatly and secured?
-
1.13 Are glass panels free from scratches?
-
Complete iAuditor Back Charge Report and forward to relevant contractor
-
1.14 Are frames free from scratches/dents?
-
Complete iAuditor Back Charge Report and forward to relevant contractor
-
1.15 Are sliding door tracks protected?
-
1.16 Has rough in been completed?
-
1.17 Has bracing and triple grips been installed correctly? (Single/lower roof)
-
1.18 If niches are external walls, have they been blocked prior to brickwork?
-
1.19 Have double triple grips been installed to girder trusses? (Single/lower roof)
-
1.20 Have you accounted for any light points to brick piers? (Check electrical layout)
-
1.21 Can brickwork be started without pinning for brickwork? Note: less than 950
-
if No, you must book Surveyor
-
1.22 Has ground floor been swept and left over material stacked neatly?
-
1.23 Are there any carpentry items on the ground floor that have not been completed? (write list if applicable)
-
1.23.1 Have change of direction blocks been installed? (Lower roof/single storey)
-
1.23.2 Does any stud require packing due to internal play bracing?
-
1.23.3 Are all walls plumb and straight?
-
Single Storey Dwelling?
-
1.24 Has manhole been installed and location identified?
-
1.25 Have all shear blocks been installed?
COMMENTS
-
Can This Job be Paid?
-
Insert Any Comments
SIGN OFF
-
Site Manager Name
-
Complete next section for two storey.
First Floor
-
First Floor (please tick)
Pre Brick/Frame Inspection (First Floor)
-
1.01 Has first floor been swept and left over material stacked neatly?
-
1.02 Is void protection in place and ladder secured? (note: Ladder must protrude 900mm above platform)
-
1.03 Have all trusses been installed?
-
1.03.1 Are all noggins in place?
-
1.04 Have bulkheads been installed correctly? (Note: Some Bulkheads to be supplied by frame manufacturer and installed by frame carpenter)
-
1.05 Has manhole been installed and location identified?
-
1.06 Are all windows/sliding doors installed?
-
1.07 Have all windows been installed with galvanized bullet head nails? (note: collated framing nails are not acceptable)
-
1.08 Are sliding door sashes stacked neatly and secured?
-
1.09 Are there any scratches to glass panels?
-
Complete iAuditor Back Charge Report and forward to relevant contractor
-
1.10 Are there any scratches/dents to all frames?
-
Complete iAuditor Back Charge Report and forward to relevant contractor
-
1.11 Are sliding door tracks protected?
-
1.12 Has rough in been completed?
-
1.13 Have change of direction blocks been installed?
-
1.14 Has bracing and triple grips been installed correctly?
-
1.15 Have double triple grips been installed to girder trusses?
-
1.16 Have all bracing straps been tightened and secured to framework?
-
1.17 Have all shear blocks been installed?
-
1.18 If niches are external walls, have they been blocked prior to brickwork?
-
1.19 Has high load brackets been adequately bolted?
-
1.20 Has Dwarf wall to void been adequately secured? (stand alone dwarf wall is to be secured beyond flooring to LVL below)
-
1.21 Has safety handrail been used on job?
-
1.22 Are there any carpentry items that have not been completed? (write list if applicable)
COMMENTS
-
Can This Job be Paid?
-
Insert Any Comments
SIGN OFF
-
Site Manager Name