Title Page
-
Site conducted
-
DATE
-
CONTRACTOR
-
LOCATION
1. TRAFFIC MANAGEMENT AND PPE
-
Works not to start until signage in place as per Approved Traffic Management Plan supplied by contractor
-
Correct use TMP onsite and is an aftercare needed?
-
Correct use and class of signage and barricades around site?
-
Evidence of traffic monitoring throughout day noted (prestart)?
-
All onsite wearing approriate PPE - vests or high vis clothing, gloves, glasses, hard hat around plant, hearing protection, long pants and long sleeves?
2. CLEARING - PREP WORK
-
Extent of area to be cleared to be pegged and inspected to identify any areas to be retained?
-
Are there any 'NO GO ZONE' or 'TREE PROTECTION AREAS' (and FENCED off)?
-
Removal of native trees must be in permit and not just on plans?
-
Dial Before You dig' completed and assets locations identfied/proven?
-
Material being disposed of as approved/agreed?
-
Dust kept to a minimum? Watercart ?
3. EARTHWORKS
-
Pavement subgrade inspected and approved prior to placing pavement material?
-
All services to be identified and proven/relocated as required?
-
Excavated area to correct depth ?
-
Dust kept to a minimum? Watercart ?
-
Make sure all pits have silt socks or similar infront of them if affected by site runoff
-
Any 'soft' spots removed and filled with agreed material?
-
Lot levels and grading is satisfactory?
-
Nature strips are free of debris? AND TOPSOILED?
4. DRAINAGE
-
Pipes and culverts conform to Australian Standards?
-
Worksafe informed of trenches in excess of 1.5m depth > shields?
-
Pipes not to be laid until trench and bedding approved ?
-
Verify proper line and grade for pipes prior?
-
Pipes Haunched and backfilled with appropriate material?
-
Pit bases compacted and level?
-
Pit lids levels are flush with FSL?
-
Terra Firma lids and grated lids locked and bolted down? and plugs installed?
-
Pits rendered where pipe enters pits ?
-
Step irons placed in pits? (if required) and at Correct spacings?
-
AGI pipes approved depth and inspected pouring of filter material(no fines, scoria)?
-
Correct pit cover installed?
-
Pit throat constructed to standards? Min. opening? between 90mm - 110mm
-
Soakage or Atlantis cells installed as per plans and specifications? (need photos)
-
All house drains and property inlets are installed, and house drain riser is in place?
-
Outfalls have grates to prevent entry and are locked with an acceptable Council key?
-
No subsidence has been identified.?
-
Rock beaching installed correctly?
5. INSPECTION OF PAVEMENT SUB GRADE
-
Stringing of Sub Base to take place prior to Base Course pavement starting? To make sure even depth.
-
Any 'soft' spots removed and filled with agreed material?
-
Proof roll, Compaction tests to take place prior to placement of base course?
-
Any rectification required?
-
Date
-
Completed by Council Construction Supervisor
-
Contractors represetative
6. INSPECTION OF PAVEMENT BASE COURSE
-
Contractor to confirm the Class and size of rock prior to placement?
-
Proof roll, Compaction tests and stringing of Base to take place prior to placement of Asphalt?
-
Base not contaminated with other materials and is clean (no soft spots)?
-
No cracking or deterioration of base?
-
Area kept free of vehicular traffic prior to asphalt?
-
Date
-
Completed by Council Construction Supervisor
-
Contractors represetative
7. CONCRETE KERB AND CHANNEL
-
Concrete not to be placed until formwork approved (for hand work)?
-
Correct levels/fall to pits?
-
Uniform and match existing (correct type of kerb)?
-
No cracks in kerb after pouring?
-
All areas backfilled and seeded as required?
-
Starter bars used to connect to existing kerb?
-
Kerb and channel is stamped indicating location of conduits and house drains.
-
Vehicle crossings need to inspected prior to pouring to check Bedding, levels, reinforcement and dowels
-
Thresholds and Islands need to inspected prior to pouring to check Bedding, levels, reinforcement and dowels
9. FOOTPATH AND CONCRETE WORKS
-
Concrete not to be placed until formwork approved?
-
Area boxed out to appropriate depth?
-
Crushed rock placed and compacted to apprpriate depth?
-
Placing of reinforcement inspected and approved type used?
-
Starter bars drilled in to exisiting path to join new path?
-
Any Slump tests required?
-
All areas backfilled, levelled and seeded as required?
-
Are tactiles installed as per plans?
-
Vehicle crossings as per standard drawings? inspected prior to pouring
10. HOT ASPHALT SURFACING
-
The placement of any asphalt layer shall not commence until consent to proceed is obtained from superintendent.
-
Profiling to adjoining seal on cross slope?
-
Area clean,dry and swept prior to placement of asphalt ?
-
Prime seal, Tack coat applied? (if stated on plans)
-
Correct asphalt mix design is being delivered to site?
-
Asphalt laid at correct Temp? check with heat gun
-
Cold joins heated up with gas torch?
-
Rollers, Compactors and multi's correct size?
-
Finished surface complies with drawings and standards?
-
After placement of asphalt is area free of left over asphalt, stones or emulsion?
11. LINEMARKING, SIGNAGE AND LIGHTING
-
Linemarking not to commence until mark-out is approved?
-
RRPMs installed at correct locations?
-
Confirm type of paint to be used (CAP, Thermo, Waterbourne, Solvent base paints) ?
-
Site clean and dry prior to painting?
-
Area protected until paint dry?
-
Any Overspray or need rectification ?
-
Any additional works required to match into existing linemarking?
-
Signage installed as per plans?
-
Light and sign poles are vertical.
-
Fire hydrants and fire plugs in place and marked in accordance with Fire Service Guidelines published by the fire authority and are at the correct level?
-
Service Authority assets are at the correct level?
PRACTICAL COMPLETION
-
DATE OF INSPECTION
-
Asset statement and as constructed plans have been provided? Dspec and Rspec?
-
WSUD Treatments - Test results to demonstrate Raingardens and Bioretention Systems built to design and functioning
-
Quality, Access and Public Safety - Practical completion Inspection Prior to consenting to commencement of the defects liability period
-
Omissions have been completed as per omissions and defects list.
-
Light and sign poles are vertical.?
-
No subsidence has been identified.
-
Site is generally tidy. (i.e., no rubbish, wheel ruts have been removed etc)?
-
No failure of infrastructure has been identified.?
-
Electronic surveillance of all pipe drains was carried out at the end of the Maintenance Period and information provided to Council.
-
Completed by Council Construction Supervisor
-
Witnessed by Engineering
-
Completed by Operations representative
-
Contractors represetative
END OF DEFECTS LIABILITY
-
DATE OF INSPECTION
-
Quality, Access and Public Safety - End of Defects liability inspection
-
Anything to repair prior ?
-
Completed by Council Construction Supervisor
-
Completed by Operations representative
-
Contractors represetative