Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Records Inspection
-
Has the electrical installation report been completed in the last five years
-
When was the last installation report compleated
-
Is the summary of the condition of installation (section E of the report) marked as satisfactory.
-
If unsatisfactory have that next steps have been produced and escalated, with a clear time scale
-
Has the work been completed and a minor works certificate has been produced.
-
What date is the work due to be completed
Emergency Lighting
-
Has the Emergency Lighting inspection been completed in the last 6 months and test certificate Issued?
-
What was the date of the last inspection
-
Have all comments from the inspection been actioned
-
What comments are outstanding
Portable Appliance Test Certification
-
When was the last PAT test completed
-
Check five items of equipment to ensure that they have a valid test label
Fire Alarm System & Risk Assesment
-
When was the fire alarm system service conducted
-
Have all observations and recommendations been completed
-
Has the Fire Risk assessment been completed
Compressor and Water boiler
-
Has the the pressure system been tested in the last 12 months
Asbestos
-
Has The asbestos survey been completed within the last 12 months
Fork Lift Truck/ Reach Trucks
-
Do all fork Lift Truck/ Reach Trucks have valid LOLER certificate
Signiture
-
Sign to say you have completed this inspection