Title Page
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Scaffold status
Customer Survey
-
Quality of our work?
-
ESS staff approach?
-
Housekeeping and Waste Management?
-
SHEQ Compliance ?
-
Any compliant , issues or improvements?
-
Name and position of the person completing survey
Site Welfare Facilities
-
Is there a SHEQ policies in place and signed in the past year?
-
Is the Quality Policy in place for ESS?
-
Is the Environmental Policy in place for ESS?
-
Is the ESS environmental emergency procedure in place displayed in prominent location?
-
Is the ESS aspect and impacts record on site ?
-
Is there a Health and Safety Poster in place ?
-
Is there site related emergency procedures available?
-
Is there a training matrix/records available to see for staff?
-
Electrical safety - cable management in good working order no cables exposed ?
-
240 volts converted to 110 volts where required .i.e. workshops etc?
Site Management
-
Waste management in good working order .i.e. no food waste, waste segregated in designated skips/bins / removed from site etc?
-
Dust level low ?
-
All materials are stored safely ?
-
Fire hazards- .i.e. accumulation of waste/surplus materials/ obstructed access and egress points ?
DESIGN
-
Is the structure of a generic type TG20:compliant scaffold?
-
Does the structure require a design or engineers guidance ?
-
Evidence of design or engineers guidance
SCAFFOLD BASE
-
Are all baseplates and sole boards present ?
-
Are all baseplates on a solid and even surface ?
-
Are the standards protected with foam
-
Is there a fan installed over door ways
-
Signage in place
GEOMETRY
-
Are the ledger and standard joints staggered between lifts ?
-
Are the transoms correctly spaced ? Structural transoms installed at every ledger brace
PLATFORMS
-
Do any lifts appear overloaded or restricted access ?
-
Are scaffold boards free from defects ?
-
Are boards under 2.4m secure ?
BRACING
-
Are all facade bracings correct ?
-
Are all ledger bracings correct ?
-
Are all plan bracings correct ?
HANDRAILS + TOE BOARDS
-
Are all handrails present min 950mm and gaps not exceeding 470mm ?
-
Is boiler flue protected with handrails secured and at least 950mm ?
-
Are all toe boards in place, correctly fitted and at least 150mm high ?
ACCESS & LADDERS
-
Dose the ladder to first lift have a guard chain and padlock ?
-
Are all ladders free from defects and fitted correctly ?
-
Is the mid rail installed to ladder points ?
-
Are Ladder gates / hatches fitted to evert access point ?
TIES
-
Have ties been tested and recorded ?
-
Are ties fixed and correctly attached ?
-
Are there a sufficient amount of ties installed ?
BEAMS
-
Is the beam section erected to TG20 or Design
-
What dose not comply to TG20 or design?
SHEETING
-
Does the scaffold require debris net or plastic weather clad or brick guards ?
-
Is all debris net or weather clad fixed and secured in place correctly ?
ROPE AND WHEL
-
Wheel number <br>Is the Wheel and rope free from defects ?.
-
Are inspections available to see regarding lifting equipment ?
PROPERTY ACCESS
-
House keeping <br>Is scaffold and working area tidy / free from materials
-
Access to scaffold at rear of property?
-
Scaff tag