Audit Title
-
Site conducted
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Scaffold Status
Design
-
Is the structure of a generic type TG20:Compliant Scaffold?
-
Does the structure require a design or engineers guidance?
-
Evidence of Design or Engineers Guidance
Scaffold Base
-
Are all baseplates and sole boards present?
-
Are all baseplates on a solid and even surface?
-
Are the standards protected with foam?
-
is there a fan installed over door ways?
-
Signage in place?
Geometry
-
Are the ledger and standard joints staggered between lifts?
-
Are the transoms correctly spaced 1.2m Max?
-
Are Structural transoms installed at every ledger brace every lift?
Platforms
-
Do any lifts appear overloaded?
-
Does the access comply, is the lift access 450mm or over
-
Are the scaffold boards free from defects?
-
Are boards under 2.4m secure?
-
Is top lift secured against adverse weather
-
Are all facade bracings correct?
-
Are all ledger bracings Correct?
-
Are all plan bracings correct?
-
Are all handrails present min 950mm and gaps not exceeding 470mm?
-
Are all toes boards in place, correctly fitted and at least 150mm high?
-
Is boiler flue protected with handrails secured and at least 950mm?
Access and Ladders
-
Does the ladder to first lift have a guard chain and padlock?
-
Are all ladders free from defect and fitted correctly?
-
Is the mid rail installed to ladder points and lifts?
-
Are Ladder gates/ hatches fitted to every access point?
-
Have ties been tested and recorded?
-
Are ties fixed and correctly attached?
-
Are there a sufficient amount of ties installed?
Beams
-
Is the beam section erected to TG20 or Design
Rope and Wheel
-
Wheel Number. Is the Rope and Wheel free from Defects
Property Access
-
Access to scaffold at rear of property?
-
Is Scaffold and working area tidy/ free from materials
Scaff Tag
-
Evidence of Scaff Tag