Information
-
Building
-
Room Number
-
Revisit Count
-
Conducted on
-
Prepared by
-
Witnessed By
-
Verify that all test reports have been submitted and reviewed for compliance with system performance specifications.
-
Verify that all equipment and cabling is consistent with approved submittals. All equipment, cabling, and fasteners used should be approved through the project submittal process.
-
Verify that the system was build in accordance with approved Shop-Drawings.
-
Verify that all Crestron firmware is consistent with the version defined in the "Crestron Campus Procedures Guide."
-
Verify that the touchpanel file version is consistent with the version defined in the "Crestron Campus Procedures Guide."
-
Verify that the central controller file version is consistent with the version defined in the "Crestron Campus Procedures Guide."
-
Verify that the scheduling panel is registered with Fusion and is schedulable via Outlook and locally at the room panel. Check for auto release of rooms containing a motion sensor.
-
Verify that all elements of the AV system are free of defect and/or damage.
-
Verify that AV equipment is installed at the location and/or in the rack or enclosure as defined in the project documentation. Equipment is installed per the elevation or other specification provided by the project documentation.
-
Verify that display(s) are plumb, level, and securely fastened. Display is installed per the elevation or other specification provided by the project documentation.
-
Verify that all AV equipment has been labeled in accordance with the requirements of the project documentation. All labeling must be consistent, durable, accurate and visible without dismantling of sub-assemblies, including but not limited to racks and desks.
-
Verify that all installed AV equipment is free from dirt, dust, water, or any other element that would compromise the performance and/or longevity of the AV system.
-
Verify that cables are dressed to ensure that all rack and site cables are installed to provide serviceability, safety, and aesthetics as defined in the project documentation.
-
Verify that all cables are identified by a unique ID as defined in the project documentation. Verify that this unique ID is displayed permanently at both ends of the cable, is legible, and is positioned where it can be seen without undue disturbance.
-
Verify that where appropriate, cable ties or hook-and-loop fasteners are used to secure the cables and that the correct type is used in the project as defined in the project documentation.
-
Verify that both site and rack cables have appropriate separation according to signal type and level as defined in the project documentation.
-
Verify that all network-connected equipment has the correct IP address, subnet mask, hostname, and gateway configuration as required for correct operation. Refer to Asset log for device settings.
-
Verify that all systems authentication credentials are configured correctly as defined in the AV Logical Standards document. Any temporary credential used during system installation should be removed.
-
Verify that remote management tools such as virtual touch panels, internal web applications, or manufacturer’s applications are configured and functional as required by the project documentation and/or manufacturer’s specification.
-
Verify that enterprise management tools such as central monitoring client/server or web-based application have been installed and connected to all systems they are required to monitor or control as specified in the project documentation. All functionality required by the project documentation, including, but not limited to, control monitoring and reporting has been verified.
-
Verify that all displayed images do not have pixel failures (bright or dead pixels) that exceed the requirements of the manufacturers specifications.
-
Verify that the analog video (VGA) and audio laptop connections are functioning properly. Verify that audio/video synchronization is maintained to ensure the proper time alignment of signals during playback. Test to be performed with XOM and third party laptops, signal generators are not to be used.
-
Verify that the digital (HDMI) video and audio laptop connections are functioning properly. Verify that audio/video synchronization is maintained to ensure the proper time alignment of signals during playback. Test to be performed with XOM and third party laptops, signal generators are not to be used.
-
Verify that all buttons of the touch panel interface are functioning as defined in the project documentation. This requires a button by button check of all system pages.
-
Verify proper functionality of the Help Desk SIP call function of the touch panel.
-
Verify that the audiovisual systems for normal operation on the resumption of power following a hard electrical power outage. Power loss recovery shall include the resumption state on power recovery. Resumption state shall be the control system start up condition/start page and resetting all devices to a known state as defined in the project documentation.