Title Page

  • Site

  • Started on

  • Inspected by

  • Subcontractor

  • Foreman

  • Works Certified

  • Competed on

PRE WORK CHECKS

  • COPY OF COUNCIL APPROVED DRAWINGS ON SITE

  • DETERMINE COUNCIL CONNECTION POINT

  • DETERMINE GULLEY AND RODDING EYE POSITIONS

  • SETTING OUT BEFORE TRENCHING

  • SITE CLEAN

SEWER INSTALATION

  • ADEQUATE TRENCHING

  • CORRECT JUNCTIONS, BENDS AND GULLEY TRAP

  • SABS MARKINGS VISABLE

  • CORRECT FALLS

  • ADEQUATE BEDDING UNDER AND AROUND PIPES

  • BUILDING INSPECTION AND APPROVED

  • ANY SPECIAL BEDDING REQUIRED

  • RODDING EYES ABOVE NGL AND CAPPED

BACKFILL

  • ADEQUATE BEDDING OVER PIPES

  • BACKFILL IN LAYERS OF 300MM

  • ADEQUATE COMPACTION

  • COMPACTION TEST DONE

GENERAL

  • HOUSEKEEPING – ONGOING, ALWAYS DO PRE WORK CHECK AND REPORT IF WORK AREA IS NOT CLEAN. AFTER WORK HAVE STARTED HOUSEKEEPING FOR WORK AREA IS YOUR RESPONSIBILETY!!!!!

  • REQUIRED PPE

  • SAFETY FILE UP TO DATE

APPROVALS

  • PLUMBING INSPECTOR SIGNATURE

  • BUILDING INSPECTOR SIGNATURE

  • SUBCONTRACTOR SIGNATURE

  • FOREMAN SIGNATURE

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.