Title Page
-
Site
-
Started on
-
Inspected by
-
Subcontractor
-
Foreman
-
Works Certified
-
Completed on
PRE WORK CHECKS
-
CORRECT SANWARE AS PER SCHEDULES
-
SITE CLEAN
PLUMBING BATH INSTALATION
-
BATH POSITION CORRECT
-
BATH SQUARE & LEVEL
-
WATE, TRAP & OVERFLOW INSTALLED CORRECTLY & TESTED
PLUMBING FINAL FIX
-
ADEQUATE FIXINGS USED FOR VANITIES
-
VANITIES PLUMB AND LEVEL
-
ADEQUATE FIXINGS FOR BASINS TOILETS AND ZINK
-
WASTES, TRAPS AND PAN CONECTORS LEAK FREE
-
ANGLE VALVES AND FLEXI CONNECTORS LEAK FREE
-
SOLAR PANNEL/HEATPUMP INSTALATION CORRECT
-
SHOWER ARMS AND ROSES SECURE
-
ADEQUATE FIXINGS FOR MIXERS AND TAPS
-
MIXER AND TAP COVERS SECURED WITH SILICONE
-
ADEQUATE SEAL WORK ON ALL BASINS AND BATHS
-
ALL PLUMBING PRESSURE TESTED
-
SEWER INSPECTED AND FLUSHED
-
RODDING EYES INSTALLED TO NGL
-
COC ISSUED
GENERAL
-
HOUSEKEEPING – ONGOING, ALWAYS DO PRE WORK CHECK AND REPORT IF WORK AREA IS NOT CLEAN. AFTER WORK HAVE STARTED HOUSEKEEPING FOR WORK AREA IS YOUR RESPONSIBILETY!!!!!
-
REQUIRED PPE
-
SAFETY FILE UP TO DATE
APPROVALS
-
PLUMBING INSPECTOR SIGNATURE
-
SUBCONTRACTOR SIGNATURE
-
FOREMAN SIGNATURE