Title Page
-
Site
-
Started on
-
Inspected by
-
Subcontractor
-
Foreman
-
Works Certified
-
Completed on
PRE WORK CHECKS
-
TILE WORK COMPLETE
-
DOOR SCHEDULE COMPLETE AND ON SITE
-
DETERMINE CORRECT DOORS FOR EACH FRAME
-
DETRMINE LOCK HEIGHT
-
DETERMINE HINGE SIDE FOR EACH FRAME
-
SITE CLEAN
DOOR INSTALATION
-
DOOR CUT TO CORRECT SIZE, ADEQUATE SPACING ALL AROUND FOR PAINT AND GROUND CLEARANCE
-
HINGES , LOCKS AND STRIKER PLATES FLUSH AND NEAT
-
FIXINGS FOR HINGES , LOCKS AND STRIKER PLATES FLUSH AND NEAT
-
STRIKER BACK BOX INSTALLED
-
CORRECT FIXINGS FOR HANDLES AND EUCUTCHEONS
-
DOOR PLUMB AND LEVEL
GENERAL
-
HOUSEKEEPING – ONGOING, ALWAYS DO PRE WORK CHECK AND REPORT IF WORK AREA IS NOT CLEAN. AFTER WORK HAVE STARTED HOUSEKEEPING FOR WORK AREA IS YOUR RESPONSIBILETY!!!!!
-
REQUIRED PPE
-
SAFETY FILE UP TO DATE
APPROVALS
-
SUBCONTRACTOR SIGNATURE
-
FOREMAN SIGNATURE