Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Air Source Heat Pump and Cylinder
-
Location of Air Source Heat Pump
-
Make and Model
-
Image of Air Source Heat Pump Fitted
-
Image of Data Badge clearly showing serial number
-
Location of Hot water cylinder
-
Capacity of cylinder - Litres
-
Image of cylinder
-
Image of cylinder serial number
Heat Pump Commissioning Electrical
-
Installed as per manufacturers instructions
-
Electrical supply
-
Resistance to earth (L-E)
-
Short circuit test (L-N)
-
Visual condition of installation
-
All sensors checked and reading correctly
Heat Pump Control parameters
-
Running mode
-
Comp start (min):
-
Heat curve setting
-
Collector pump setting
-
Max flow temp
-
CH pump setting
-
Max outdoor temp
-
DHW start temp
-
Min flow temp
-
DHW stop temp
-
Min outdoor temp
-
Legionella cycle temp
-
Heat stop temp
-
Legionella cycle heat source
-
Max Auxiliary power
-
Auxiliary heat meter reading
-
Legionella frequency
-
Type of auxiliary heating
-
Auxiliary bi-valent point
Absorber
-
Antifreeze make and type
-
Type
-
Freeze protection
-
Correct clearance around unit
-
Installed on suitable base/bracket
-
Anti-vibration feet fitted where required
-
Condensate drainage suitable
-
Evaporator clear of debris
-
Insulated and vapour free
-
Clearence to back of unit
-
Clearance to front of unit
-
Clearance to right hand side of unit
-
Clearance to left hand side of unit
Central Heating System
-
Emitter types
-
Number of radiators fitted
-
System pressure - bar
-
Strainers filter cleared
-
Expansion vessel charge - bar
-
Safety relief valve setting - barK
-
Heating system flushed and cleaned
-
Cleaner used
-
Heating system water treated
-
Circulation pump setting
-
Inhibitor/anti-freeze used
-
DHW cylinder volume - Litre
-
System installed as per design
-
Do all emitters heat up evenly with a similarly across flow and return
Heating controls
-
Type of heating controls
-
Type
-
Have the controls been set-up as per design
-
Have the controls been demonstrated and explained to the customer
-
Has the customer been provided with all documents required by MIS 3005 and MIS3005-I
Additional Images Required
-
Radiator 1 - Bypass
-
Radiator 2 and TRV
-
Radiator 3 and TRV
-
Radiator 4 and TRV
-
Radiator 5 and TRV
-
Radiator 6 and TRV
-
Radiator 7 and TRV
-
Radiator 8 and TRV
-
Radiator 9 and TRV
-
Radiator 10 and TRV
-
Radiator 11 and TRV
-
Radiator 12 and TRV
-
Radiator 13 and TRV
-
Radiator 14 and TRV
-
Radiator 15 and TRV
-
Image of Heating controls Thermostat
-
Image of heating controls clock
-
Image of Heating controls 3
-
Mid install image 1
-
Mid install image 2
-
Mid install image 3
-
Mid install image 4
-
Mid install image 5
-
Grant Heat Pump Commissioning document
-
Grant Cylinder Commissioning document
Signatures
-
Engineer
-
Customer
-
Time and date