Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location

Air Source Heat Pump and Cylinder

  • Location of Air Source Heat Pump

  • Make and Model

  • Image of Air Source Heat Pump Fitted

  • Image of Data Badge clearly showing serial number

  • Location of Hot water cylinder

  • Capacity of cylinder - Litres

  • Image of cylinder

  • Image of cylinder serial number

Heat Pump Commissioning Electrical

  • Installed as per manufacturers instructions

  • Electrical supply

  • Resistance to earth (L-E)

  • Short circuit test (L-N)

  • Visual condition of installation

  • All sensors checked and reading correctly

Heat Pump Control parameters

  • Running mode

  • Comp start (min):

  • Heat curve setting

  • Collector pump setting

  • Max flow temp

  • CH pump setting

  • Max outdoor temp

  • DHW start temp

  • Min flow temp

  • DHW stop temp

  • Min outdoor temp

  • Legionella cycle temp

  • Heat stop temp

  • Legionella cycle heat source

  • Max Auxiliary power

  • Auxiliary heat meter reading

  • Legionella frequency

  • Type of auxiliary heating

  • Auxiliary bi-valent point

Absorber

  • Antifreeze make and type

  • Type

  • Freeze protection

  • Correct clearance around unit

  • Installed on suitable base/bracket

  • Anti-vibration feet fitted where required

  • Condensate drainage suitable

  • Evaporator clear of debris

  • Insulated and vapour free

  • Clearence to back of unit

  • Clearance to front of unit

  • Clearance to right hand side of unit

  • Clearance to left hand side of unit

Central Heating System

  • Emitter types

  • Number of radiators fitted

  • System pressure - bar

  • Strainers filter cleared

  • Expansion vessel charge - bar

  • Safety relief valve setting - barK

  • Heating system flushed and cleaned

  • Cleaner used

  • Heating system water treated

  • Circulation pump setting

  • Inhibitor/anti-freeze used

  • DHW cylinder volume - Litre

  • System installed as per design

  • Do all emitters heat up evenly with a similarly across flow and return

Heating controls

  • Type of heating controls

  • Type

  • Have the controls been set-up as per design

  • Have the controls been demonstrated and explained to the customer

  • Has the customer been provided with all documents required by MIS 3005 and MIS3005-I

Additional Images Required

  • Radiator 1 - Bypass

  • Radiator 2 and TRV

  • Radiator 3 and TRV

  • Radiator 4 and TRV

  • Radiator 5 and TRV

  • Radiator 6 and TRV

  • Radiator 7 and TRV

  • Radiator 8 and TRV

  • Radiator 9 and TRV

  • Radiator 10 and TRV

  • Radiator 11 and TRV

  • Radiator 12 and TRV

  • Radiator 13 and TRV

  • Radiator 14 and TRV

  • Radiator 15 and TRV

  • Image of Heating controls Thermostat

  • Image of heating controls clock

  • Image of Heating controls 3

  • Mid install image 1

  • Mid install image 2

  • Mid install image 3

  • Mid install image 4

  • Mid install image 5

  • Grant Heat Pump Commissioning document

  • Grant Cylinder Commissioning document

Signatures

  • Engineer

  • Customer

  • Time and date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.