Title Page

  • Document nr

  • Description QA

  • Conducted on

  • Site conducted

  • Prepared by Manager

  • Site Location

Location-Building-Elevation-Zone-Floor-Grid Line

  • Location-Building-Elevation-Zone-Floor-Grid Line

QAC-Inspection Checklist

  • 1.Subcontractor Name,CSCS Card,Pictures Evidence

  • 2.Linked Drawings & Details Drawings used BTS_XX_DET_TBS , Data Sheet & installation guide checked

  • 3. Housewrap Breather Membrane Tyvek Firecurb to spec seal /tape all joints with Tape. Horizontal laps should be at least 100 mm and vertical laps 150 mm. Vertical laps should be staggered wherever possible. External corner min 300mm

  • 4. C`Channel & Top Hat fixed to SFS studs, GL/Datum; fixings to spec, max 600mm centres

  • 5. Vertical Bracket AXL-HB90-S-TP . SINGLE BRACKETS FIXED TO "C" Channel or SFS WALL USING 2 No FX1. FIXING CENTRES ARE TYPICALLY 600mm HORIZONTAL AND 750mm MAX VERTICAL, ALL WITH THERMAL ISOLATOR PADS. (SUBJECT TO CALCS) Fixing 2 x S-SKT0550400.A2 - 5.5x40mm (on single bracket)

  • 6. DOUBLE BRACKETS FIXED BACK TO "C" Channel or SFS WALL USING 2 No FX1. FIXING CENTRES ARE TYPICALLY 600mm HORIZONTAL AND 750mm MAX VERTICAL, ALL WITH THERMAL ISOLATOR PADS (SUBJECT TO CALCS) Fixing 4 x S-SKT0550400.A2 - 5.5x40mm

  • 7.RWA45 Rockwool Insulation, Rainscreen Duo Slab 100 mm Insulation Rockwool Duo Slab U-Value 0.24 W/M2k or check project spec, fix with Textured outer face of the slab, Close butt the slabs at all vertical and horizontal joints, Stagger the horizontal joints min 100mm, Fixings min 1 no metal and 2 no polypropylene per board, @ max 500 cnts, minimum head diameter of<br>70mm. check project spec<br>

  • 8. VFB-RV CAVITY BARRIER MUST take priority over RH<br>Install abutting cavity barriers tightly together making sure there are no gaps. - Inspection of vertical cavity barriers (FB) FULL FILL CAVITY BARRIER TO SUIT CAVITY 10 mm compression check project spec. Brackets RV Method 1, 1. Bend Brackets set at 600mm 2. Fix to wall 3. Install RV must penetrate the firestop by 75% at mid thickness, using non-combustible fixings at 600mm centres, Making a small incision at bracket locations is required<br>

  • 9. HFB-Horizontal Cavity Barriers - check project spec, Min 25mm Ventilation GAP and max 44 mm gap, Min 2 fixings brackets, max 200mm from the edge and max 400 cntrs between. <br> 3 Brackets are required per length, with nominal 400mm centres.<br>2 brackets are required per length between 100mm and 800mm.<br>AVOID lengths less than 100mm.<br>

  • 9.1Horizontal Cavity Barrier 90min insulation and 30min Integrity (RH25G-90/30) with<br>OSCI/1220-100 Cassette insert Bracket fixing using JT3-6-5.5 x 50 S16

  • 10. VERTICAL Vertical L-Rail AXL-L 60x40x2.2 Aluminum ( or Mullion RAILS, Bracket/Mullion Fixing, Horizontal Adapter Bracket, Support Angle) to spec Fixings Rail to Bracket Fixing 2 x SS-LS22<br>

  • 11. Windows Cills & Flashings Aluminium Cleat Support,Aluminum Retainer Cill Bracket 3 mm thick– B#Insect mesh @ Bottom & Top of the Cladding - check project spec B# Aluminium PPC: Jamb Closer, PPC Ventilation,Corner , Drip flashing – project spec

  • 11.1 Cills -2 mm thick Aluminum Window Cill PPC RAL 9007 Matt Tightly fitted RWA45 Rockwool Insulation,DF3-SSA4-P(L)-S10-5.5 x 35 @ 600mm Ctrs Max. RAL 9007 Matt RSH-AS-LAC-4.8 x 11-W - RAL 9007 Matt, Fixing DF3-SS-P-5.5 x 30

  • 12.Copings for Aluminium Cladding_ VariAL-CF-3 _SYSTEM

  • 13. Inspection of Aluminium Cladding_ VariAL-CF-3 _SYSTEM Ash&Lacy Aluminum Cladding System 3mm thick<br>(Finish Colour PPC RAL 9007 Matt

  • 14.Subcontractor Installers & Supervisor name,pictures, cscs cards

  • 15. Invoice no & Mark up Drawing (BTS Reference )

Comments

  • COMMENT Reference & Descrition

  • Comments Reference & Description date when closed (BUILD THERM)

Hand Over Joint Inspection

  • Hand Over -Cladding free from damage-Facades to be viewed as per the BBA, in daylight from a distance of not less than 10m. Some variation in colour and texture of external walls is inevitable and in certain cases is a feature. A façade for instance should be inspected for scratches or minor imperfections from a distance of min 5m, if a scratch cannot be seen from that distance then it is not a defect except if a scratch has gone through the full depth of the coating exposing the raw metal below.

  • On behalf of Build Therm (name)

  • On behalf of Main Contractor (name)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.