Information
AUDIT SUMMARY
-
Document No.
-
Prepared by
-
Post audit
-
Number of non conformances
-
Audit Address
-
Meter no
-
Seal no
AUDIT TYPE
-
AMI install
-
Other
-
UED NETWORK
-
Other
-
Formway
-
Other
-
DATE / TIME
United Energy Site Risk Assessment
Job Safety Assessment/Control Measures Taken
-
Any Hazards Identified?
JSA
-
Precautions taken to remove hazards
-
Correct Tools/Equipment to perform the task?
-
Is the correct PPE available to complete task
-
Is a fire extinguisher available
-
Is a first aid kit available <br>
FIELD INSPECTION
METERING
-
1. Has the correct meter been installed at the correct address?
-
2. Has the correct meter been installed for the installation?
-
3. Has the meter been installed at correct level and height?
-
4. Has metering equipment been firmly secured to the board and or structure?
-
5. Have all tamper seals been installed on metering equipment? (Meter, links, fuses)
-
6. Have the correct fasteners been used to secure metering equipment?
-
7.Have terminal connections been secured firmly?
-
8.Is the metering equipment in good working order? E.g. links, fuses, panel.
-
9.Is the condition of the meter board / panel acceptable /enclosure acceptable <br> (does it require to be identified as a defect)<br>
-
9A. Is the condition of the customer meter enclosure acceptable? (does it require to be identified as a customer defect)
-
10.Has meter commissioning requirements been completed?<br>
-
11.Has meter been checked for correct functionality, programming, type, SIR compliance etc.
-
12.Does the metering installation comply with current SIR's?
-
13.Has the IP rating of the meter cabinet been maintained? (When antenna installed)
-
14. Has antenna been programmed when installed
Work Practices
Work practises
-
15.Has Asbestos been identified and steps, procedures followed?
-
16. Has all unused metering cables been removed or terminated?
-
17. Has all unused metering equipment been removed?<br>(e.g. time switch)<br>
-
18. Has non compliant meter wiring been identified as a customer defect?
-
19. Has the work site been left tidy?
Communications
-
20. Was the householder notified by the installer of meter exchange prior meter exchange?
-
21. Was the customer / occupier notified of meter exchange?<br> (by mail)<br>
-
Signature: Auditor: