Personnel
-
Do personnel have the correct personal safety gear?
-
Is all safety equipment checked to ensure it is in working order, serviced and calibrated?
-
Personnel are aware of accident and hazard reporting?
-
Are safety provisions in place and adequate? (Traffic control, site safety, confined spaces entry)
-
Is a first aid kit on site and in good condition/complete?
-
Fire extinguisher on site and serviced?
-
Storage and handling of materials to standard?
-
Chemicals/Fuel - Labeled- Correct Containers-Storage?
-
Are the Asbethos handling procedures being followed?
-
Has the relevant service authority been notified? (E.g OSH)
-
Are H&S plans, Quality plans, Traffic plans, etc on site and being followed?
-
Do personnel have health & safety issues to be raised and actioned?
-
Plant and vehicles to be within certification period /COF/WOF/Road user charges/Hubodometer/Speedometer, to be in credit?
-
Does the contract have environmental considerations?
-
Has an environmental safeguard checklist been used (silt, slurry, noise, dust control)? Are all controls sufficient?
-
Are personnel aware of environment protection, objectives and targets?
-
Have actual or potential hazardous conditions / impact to people or the environment been assessed, eliminated, isolated or minimised?
-
Have hazardous materials; flammable, toxic gases, and other substances been assessed, and eliminated isolated or minimized?
-
Are silt, slurry, noise, dust, etc, controls in place?
-
Have residents been notified of work where necessary?
-
Sufficient personnel on the job to ensure effective completion?
-
Have there been any customer complaints?
-
Is the site safe and tidy for the public/owner?
-
Are materials (pipes, manholes, fittings, invert connectors, bedding, grille etc) compliant with COP?
-
Is method of contruction and workmanship (welding for PE, single/multi riser manhole, backfill compaction, grassing etc) complaint with requirements?
-
Is testing (visual, air test, water test) satisfactory?
-
Do personnel have any ideas for improvement of work methodology or procedures?
-
Tap to enter information
-
Date of Audit
-
Address
-
Name of contractor
-
Job
Health and Safety Audit
-
Do personnel have correct personal safety gear?
-
Is all safety equipment checked to ensure it is in working order, serviced and calibrated?
-
Personnel are aware of accident and hazard reporting?
-
Are safety provisions in place and adequate? (Traffic control, Site Safety, Confined Space Entry)
-
Is a first aid kit on site and in good condition/complete?
-
Fire extinguisher on site and serviced?
-
Storage and handling of materials to standard?
-
Chemicals/fuel-labeled-correct containers-storage?
-
Are the asbesthos handling procedures being followed?
-
Has relevant service authority been notified? (E.g OSH?)
-
Are H&S plans, Quality plans, Traffic plans on site and being followed?
-
Do personnel have any H&S issues to be raised and actioned?
-
Plant and vehicle to be within certification period/COF/WOF/Road user charges/hubodometer/Speedometer to be in credit?
-
Notes
Environmental Audit
-
Does the contract have Environmental considerations?
-
Has an Environmental Safeguard checklist been used (silt, slurry, noise, dust, control)? Are all controls sufficient?
-
Are personnel aware of environmental protection objectives and targets?
-
Have actual or potential hazardous conditions/impact to people/or the environment been assessed, eliminated, isolated or minimised?
-
Have hazardous materials; flammable, toxic gases, and other substances been assessed and eliminated , isolated or minimised?
Tap to enter information
-
Are silt/slurry/noise/dust, etc controls in place?
-
Notes
Quality Control Audit
-
Have residents been notified of work where necessary?
-
Sufficient personnel on the job to ensure effective completion?
-
Have there been any customer complaints?
-
Is the site tidy and safe for the public/owner?
-
Are materials (pipes, manholes, fittings, invert connectors, bedding, grille, etc) compliant with COP?
-
Is method of construction and workmanship (welding for PE, single/multi riser manhole, backfill compaction, grassing etc) compliant with requirements?
-
Is testing (visual, air test, water test) satisfactory?
-
Do personnel have any ideas for improvement of work methodology or procedures?
-
Notes: