Site Information
-
Location
-
Conducted on
-
Prepared by
-
Concreter's Name
Slab QA
-
Has the earth stake installed
-
Driveway Gradient does not exceed 1:5
-
Waffle Pods installed as per Engineering
-
Boxing square (Site and measure if required)
-
Check number of sewer pipe penetrations are correct and in correct locations
-
Check number of stormwater pipe penetrations are correct in correct locations
-
Is the service conduit installed for kitchen sewer & power?
-
Has the sewer/stormwater services been checked by camera pre pour?
-
Has building surveyor approved slab for pouring?
-
Has pod pickup been booked in?
-
Has the slab clean been booked in?
-
Has termite treatment been booked in?
-
Check rebate widths are correct for external cladding.
-
Have star picket caps been installed?
-
Take photos of slab boxing from all angles showing boxing and services