Documentation

  • Is the CPP/PSP current and in line with current work scope, Signed by all employees and displayed?

  • Is the TMP current and in line with current work scope, Signed by all employees and displayed?

  • Is the ERP current and in line with current work scope, Signed by all employees and displayed?

  • Is the EMP current and in line with current work scope, Signed by all employees and displayed?

  • Is the Fire Risk Assessment current (Reviewed Monthly), Signed by all employees and displayed?

  • Are RAMs available for all work activities being completed on site?

  • Is the F10 displayed in the Site Office and/or Canteen?

  • Is the Health & Safety Law Poster displayed?

  • Are First Aiders contact details displayed in Site Office/Canteen?

  • Is there a Project Organogram displayed in Site Office/Canteen?

  • Has a Daily Co-ordination Meeting held and recorded?

  • Has a Point of Work Risk Assessment (POWRA) been completed prior to work activities beginning?

  • Has the Site Manager completed a Weekly Site Inspection?

  • Have copies been taken of all Scottish Power Authorisation Certs., available for inspection and verification?

  • Is there a Induction Register available?

Welfare Facilities

  • Is the site compound located a safe distance from workplace hazards

  • Are Welfare Facilities a suitable size for the number of site workers?

  • Is the site Compound secure, suitable perimeter fencing erected with signage (Construction Site, Keep Out) displayed?

  • Is there suitable segregation of pedestrians and Plant/Vehicles?

  • Are welfare toilet facilities clean and hygienic?

  • Is there hot and cold water available (Including Drinking Water)?

  • Is there a suitable area to rest, prepare food and change clothing, etc?

  • Is there Heating and Light available?

  • Is there a First Aid Kit and an Eye Wash Station available?

  • Is the Fire Extinguishers available in Welfare Facilities?

  • Is there a Designated Smoking Area?

  • Is Information displayed for Site Workers (F10, H&S Law Poster, Employers Liability Insurance, Policies, etc.)?

Site Conditions

  • Is the housekeeping of the site acceptable?

  • Is the site secured to protect against unauthorised access?

  • Is there a Hazard Board displayed in a suitable location warning all persons of Site Hazards?

  • Is there a Safe Access/Egress Route identified (Red cones (up to 10m apart) with a Orange Rope 10mm) on the high side of the yellow cross arm (Higher side of cross arm defines the safe side)?

  • Is the Safe Working Area identified (Red cones (up to 7m apart) with two Orange ropes 10mm on each side of Yellow cross Arms, Cross Arms raised to define the safe side and Green Cones (up to to 6M apart) on the safe side?

  • Are Safety Distances being adhered to (33kV - 0.8M, 132kV - 1.4M, 275kV - 2.4M, 400kV - 3.1M)?

  • Is there adequate Site Supervision for the number of Site Workers?

  • Is there suitable Danger Notices, Markers and Signage defining safe areas and those which are not?

  • Site Security, have checks be completed by the Authorised Key Holder with Substation buildings and surrounding compound. Fencing undamaged with 'Danger of Death' Signage displayed?

  • Are barriers being used to segregate workers/pedestrians from excavations and/or other work areas?

Plant/Equipment

  • Has Field Equipment Earthing applied to all mobile Plant or constructed access equipment to protect against Induced or Impressed voltages?

  • Are Safety Distances for Plant/MEWP's etc, being adhered to (33kV - 2.75M, 66kV - 3M, 132kV - 3.4M, 275kV - 4.6M, 400kV - 5.5M)?

  • Are trained and competent Plant Vehicle Marshalls/Banksmen (Orange Vests) in control of all Plant/Vehicle movements, Deliveries, Reversing manoeuvres, etc?

  • Is Plant/Vehicle manoeuvres compliant with the Traffic Management Plan (TMP), Speed restrictions, Direction, etc?

  • Are all Vehicles/Plant over 2.3M, movements personally supervised by an Authorised Person?

  • Are all drivers wearing seatbelts where mandatory, Flashing Beacons turned 'On', Keys removed and secured when not in use?

  • Are Plant/Equipment and all Hand Tools in good order, Inspected/Calibrated, PAT Tested, Suitable for the task?

  • Is all electrical tools and equipment 110V (No 240V electrical equipment allowed on site)?

  • Are all extension cables free from damage and positioned, so not present a trip hazard?

  • Are Cable Avoidance Tools (CAT) and Signal Generator available and being used to track the position of underground services?

  • Are 'Long Objects', any items capable of breeching the minimum safe distances of various Voltage levels, constructed of a Non-conductive material, stored appropriately and transported through the site at waist height to prevent contact with live surroundings?

  • Are Trigger times being recorded on all tools/equipment that generate vibration, Vibro-plates, Whackers, Road-breakers, etc?

  • Is water suppression/extraction being used to control dust from cutting/drilling of concrete or other dust creating materials?

  • Lifting Equipment & Operations, is there a Lift Plan, Thorough Examinations for Equipment/Accessories and a Responsible Person on site?

Environmental

  • Have all Environmental Aspects and Impacts been assessed including the presence of Asbestos, PCBs or Lead Paint, etc?

  • Has an Asbestos Survey been completed with a Register available, have site workers been made aware of ACM locations, has Asbestos Awareness training been completed?

  • Is there a COSHH Register and Assessments available, detailing Use, Storage, Accidental Release Measures, etc. Signed by workers to confirm they have read and understood the assessment?

  • Is there a suitable COSHH Cabinet located on site to store hazardous substances?

  • Has a suitable location for refuelling been identified, on a Plant Nappy to prevent Oil, Fuel, and other Chemicals escaping into the environment, with a Spill Kit available?

  • Are Plant Nappies in use under machinery where there is the risk of spillage, oil leaks or other hazardous substances leaking?

  • Is there a suitable Skip available for contaminated soil/waste, with appropriate signage ,identifying 'Special Waste'?

  • Is there enough light on site for site workers to carry out tasks safely and walk through the site?

  • Is dust being adequately controlled on site (Water Suppression, Alternative techniques/Materials, etc.)?

  • Is there excessive noise being produced due to site activities?

Emergency Preparedness

  • Has the emergency procedures been explained in the site induction to all visitors/site workers?

  • Is there a suitable number of Fire Extinguishers available at relevant areas, Welfare Facilities, Refuelling area, Hot Works Activities, Designated Smoking area, etc.)?

  • Is there a suitable number of Spill Kits available at relevant areas, Refuelling area, COSHH Cabinet, Plant room, etc.?

  • Has the Muster Point been located in a safe area and communicated in the site induction?

  • Is there a way to alert all site workers of an emergency?

  • Are First Aider contact details available to all Site Workers?

  • Has a First Aid needs assessment been completed for the project?

  • Has an Emergency Response Plan been developed specifically for the project. Have all site workers read, understood and signed the document to confirm this?

  • Are High Risk activates such as Hot Works, or Excavations controlled under a Permit To Work System?

Culture Indicators

  • Operatives Signing In/Out Site?

  • Is there evidence of good interaction between workers recorded on Daily Co-ordination Meeting?

  • Are Weekly Toolbox Talks being communicated?

  • PPE Compliance, (Hard Hat, Hi-Viz Vest, Safety Boots, Gloves, and suitable Eye Protection)?

  • Are all site workers (Including Sub-contractors) working safely, in compliance with approved SSoW/RAMs and using best practices?

  • Has there been any Safety Observation Reports (SORs) submitted?

  • Have previous Inspection Actions/Observations been actioned/completed?

  • Have all Sub-contractors on-site submitted their RAMs, signed in and compliant with SKED Construction Policies and the clients Contractor Safety Performance Requirements (CSPR)?

  • Has random Drug & Alcohol testing been carried out on at least 10% of the workforce on site in the last Month?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.