Binder Course Inspection
-
Project Reference
-
Project Name and Phase
-
Date
-
Contractor / Subcontractor
-
Inspected by
Binder Coat Surfacing
Carriageway Surfacing Binder Coat
-
-
Carriageway Surfacing
-
Surface Clean and Swept
-
Tack Coat Applied and Dry
-
Material Depth
- 60mm
- 70mm
- 100mm
- Other Depth
-
Road Kerbs Installed
Material Specification
-
DBM 10mm
-
DBM 20mm
-
DBM 28mm
-
Other
Temperatures
-
Air Temperature (at or above 1 Degree's Celsius)
-
Ground Temperature (At or below 2 Degree's Celsius)
-
Wind Speed Table to be used in conjunction with air Temperatures
-
Wagon 1 Vehicle Reg, Temperature on arrival, Temp in Hopper, Temp before Rolling
-
Wagon 2 Vehicle Reg, Temperature on arrival, Temp in hopper, Temp before Rolling
-
Wagon 3 Vehicle Reg, Temperature on arrival, Temp in Hopper, Temp before Rolling
-
Wagon 4 Vehicle Reg, Temperature on arrival, Temp in Hopper, Temp before Rolling
Bitumen Paving Grade
-
40/50
-
70/100
-
100/150
-
160/220
-
Other
Testing
-
Rolling Straight Edge Compliant
-
3 Metre Straight Edge Compliant
-
Griptesting Compliant
-
White lining Complete
-
PQI compliant
-
Sand Patch Test
Certification.
-
Partial Completion Schedule 1
- All Earthworks supporting the Road
- All Boundary Features denoting the lateral extent of the road
- All Highway Drainage
- All other drainage in the road
- All kerb foundations, kerbs and lowering of crossings and pedestrian ramps
- Sub base and binder course to pedestrian ways and cycle ways
- Sub base, Base course and Binder course to carriageways and any structures to the same
- Demarcation of sight lines and clearance of visibility splays
- Operational Street Lighting (As required by the relevant local authority)
- Temporary Street name plates (As required by the Local Authority)
-
Schedule 1 Complete
- All Earthworks supporting the Road
- All Boundary Features denoting the lateral extent of the road
- All Highway Drainage
- All other drainage in the road
- All kerb foundations, kerbs and lowering of crossings and pedestrian ramps
- Sub base and binder course to pedestrian ways and cycle ways
- Sub base, Base course and Binder course to carriageways and any structures to the same
- Demarcation of sight lines and clearance of visibility splays
- Operational Street Lighting (As required by the relevant local authority)
- Temporary Street name plates (As required by the Local Authority)