Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Inspection of works in relation to Brickwork, Clockwork, and associated sundries
A. Brickwork and Blockwork
-
1. Is the Brick / Blockwork correct to specification bond etc
-
2. Are reveals and corners plumb?
-
3. Are perps to standard specifications?
-
4. Are all joint and beds fully filled?
-
5. Are bricks mixed to manufacturers instructions prior to laying?
B. Fire stopping
-
1. Has the fire breaks been located and installed as per the fire stratedgy design? Please attached design ref
-
2. Have the CB and FB been inspected and signed off by main contractors agreed inspection team?
-
3. Are Cavity fire barriers and closures fitted and per specification and manufacturers recommended instruction? Please attach manufacturer instructions and evidence photos
C. Mortar
-
1. Have the correct reader and plasticisers been used?
-
2. Have the suppliers material test been taken and results confirmed?
-
3. Correct batch, colour, gauge?
-
4. Correct colour and strength to specification?
D. DPC
-
1. Correct to specification?
-
2. Correctly lapped as per details?
-
3. Correctly fitted to Reveals, Cills, Lintels and Cavity trays and as per manufacturer instructions. Please provide instructions and proof photos
E. Ties
-
1. Are the ties and fixing spacings correct to specification? Please add spec and evidence photos
-
2. Are the ties correct to Centres, coursing, fall and levels?
-
3. Are the correct Insulation clips supplied and installed if required?
-
4. 3. Are the win post ties and clips supplied and installed if required to locations, specification and manufacture instructions?
F. Insulation
-
1. Is the insulation correctly fitted as per specification and manufacturer instructions?
G. Cavities
-
1. Clean out debris and close inspection holes?
-
2. Clean ties / Lintels / trays and cavity barriers?
-
3. Clean around windpost?
H. Lintels
-
1.Correct to specification schedule?
-
2. Line, level, bedding and bearing correct?
-
3. DPC installed correctly with returns?
-
4. Wholes installed as specification
I. Frames
-
1. Correct to specification schedule
-
2. Correct fixings
-
3. DPC
-
4. Protection
J. Stone cills
-
1. Correct to specification schedule
-
2. Correctly leveled and lined
-
3. Correctly fitted dpc
-
4. Protection
K. Airvents
-
1. Correct to specification schedule
-
2. Correct location
-
3. Epdm / waterproofed, stepped dpc
-
4. Water tested
L. Masonry support systems
-
1. Correct to specification and location schedule
-
2. Pull test on post fixing if required
-
3. Correct fixings used as per specification
-
4. Correct torque setting used
-
5. Secondary check done on torque by client .
M. Bed joint reinforcement
-
1. Correctly cut and lapped
-
2. Installed as per specification
N. General completion
-
1. Work areas cleared, clean and materials removed
-
2. Tie holes and final snag complete
-
3. Final washdown
-
4. Protection removed
Untitled Page