Title Page
-
Site name (eg. Henderson trade branch)
-
Prepared by
-
Location
-
Personnel
-
Conducted on
Health and Safety Meeting Minutes
-
Are meeting minutes covering content in each section?
-
Have meeting minutes been distributed to the Regional HSER Advisor and Regional Manager?
-
Are meeting minutes up to date for the last meeting?
Training Matrix
-
What is the current completion percentage on the training matrix?
-
Is the training matrix saved to the intranet?
SOP training records
-
Review a number of training files, are they up to date?
Staff recognition
-
Are staff being recognised for the right action and behaviour? If so, list the details.
Fire evacuations
-
Is the fire service approval scheme letter or exemption letter accessible on the intranet?
-
Is the fire action notice, along with the site plan next to each and every alarm call point?
-
Is there also a copy of the fire action notice, along with the site plan on the staff noticeboard?
Health and Safety Nominations and Elections (if relevant)
-
Is the paperwork being kept and up to date?
-
Are fire warden training records being kept up to date?
Health and Safety Representatives
-
Are copies of representative certificates being kept and up to date?
Health and Safety Constitution
-
Has this been completed and rolled out to staff?
Vehicle Checks
-
Are vehicle, forklifts, trucks, trailers, light vehicles checks and log books being completed in full?
Other Check Sheets
-
Are ladder, bench saw and racking checks being completed?
Contractor Management
-
In advance of works have contractors been pre-qualified and documentation available as evidence?
-
During the works have contractors been monitored and documentation available as evidence?
-
Following the works have contractors been reviewed and documentation available as evidence?
Annual and Quarterly Site Performance Reviews
-
Is there 12 months of clear evidence showing quarterly and annual reviews?
-
Is there an appropriate amount of goals within the annual plan - more than 5?
Investigations
-
For full investigations, are they being completed on time (within 10 days)?
-
For simple investigations, are corrective action (s) effective in managing the risk? Could more be done?
-
Have events been communicated to staff in person, via email, toolbox talk, staff meeting to close out the feedback loop?
RiskProfile / Register
-
Is this up to date and uploaded to the EHRS website?
Emergency Plan
-
Is the layout as per the Emergency Site Plan for the site
-
Does the Emergency Site Plan follow the template document on the intranet? Does it have all of the appropriate symbols?
Traffic Management
-
Is the traffic management up to date against any recent changes?
-
Is there evidence that the traffic management plan been communicated and consulted with affected staff / parties?
-
Is the traffic management map (2.4 x 1.2m sign) displayed at the main entrance?
-
Have all relevant staff signed a motor vehicle policy?
-
When a loading process is underway, is the driver in the safety zone - leaving the forklift operator as the only person in the zone?
-
Whilst observing normal forklift operations on site, is the 3 m exclusion zone being maintained from staff, customers and visitors?
Truck Paperwork Packs
-
Are these in each truck and up to date? <br>Check that strops and chains are up to date and of good condition <br>Check that log books are being used correctly against NZTA requirements
Disaster Recovery Plan
-
Is this up to date and reflecting staff changes?
Health and Safety Noticeboard
-
Is this in accordance with the HSER Template (as from the Intranet)?
Housekeeping
-
Is the general housekeeping of the site acceptable?
-
Is the site sign in book as per the Intranet Template, with appropriate up to date information?
-
Are all emergency exits and routes clear?
Asbestos Register
-
Is this up to date?
-
Is all being done to eliminate or minimise the risk? If no asbestos on site, select N/A
Risk Manager Actions
-
Have all Risk manager actions been completed on time?
Claims Privacy
-
Is all claim information being appropriately managed?
Area Manager Site Review
-
In reviewing the latest area manager site review, are there any actions outstanding?
Change Management
-
Where a change has occurred within the workplace, is there evidence in place showing consultation with affected parties?
Storage Review
-
Has this been completed?
Mezzanines
-
Are the gates being locked and secure?
-
Does the site have the HCP on display at the entrance and is it correct?
Racking, Stacking and Storage
-
Are 150 mm clearances being achieved on cantilever racking?
-
Is product being strapped above 2 metres?
-
Is any product being stacked in an un safe manner?
Services Safety
-
Is it possible to open electrical cabinets, is it possible to touch cabling with a finger?
-
Is the cabinet clean in and around? Has a corrective action been added in Risk Manager for a regular clean down?
-
Is there a isolation lock out board available for use and with appropriate tags, locks and clasps?
-
Are there lock out processes for all powered equipment on site?
-
For identified powered equipment above, are there emergency stops in place?<br>Where not appropriate, list N/A. Provide recommendations if one should be added.
-
Speaking with 2 staff on site, ask them to show how to isolate the plant they are working on. Are they able to detail a safe and correct process?
Work on section - no weighting to these elements
-
When truck loading and unloading is occurring, are truck drivers keeping off truck decks? Focusing on pre-slinging?
-
Has the first aid assessment been completed?
-
Is there a PPE register for expiring equipment (Risk Manager)
Close out section
-
Any other observations, comments or feedback? Remember to be positive too :)
-
Sign to close out this inspection :)