Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Weather at the Time of Report
Works Undertaken
-
Drawings Highlighted Area of Works
-
Confirmation of the Area that is Being Inspected. Please use Gridline and Floor no's that confirm the highlighted section on the drawing above.
Removal
-
Images to be taken prior to removal of any materials
-
Any Damage to the Immediate Area (if so images to be taken)
-
Any Damage Caused by Removing Rain Screen Covering?
-
Have all Required Materials Been Removed?
-
Is there any Evidence of Damage or Remedials Required to the Inner Wall or Existing Construction?
Sign off
-
Warden Representative Sign Off
-
Clerk of Works Sign Off
Installation of New System (Timber Facade)
Mineral Wool Installation
-
Has the Correct Mineral Wool Been Installed?
-
Has the Correct Fixings Been Installed?
-
Correct Number / Location of Fixings?
Sheathing Board & Membrane
-
Has the Correct Sheathing Board Been Installed?
-
Correct Number / Location of Fixings?
-
Has the Correct Membrane Been Installed?
Helping Hand Bracket
-
Has the Correct Helping Hand Been Installed?
-
Has the Correct Torque Setting Been Used? (Contractor to demonstrate that fixing has been installed in line with manufacturers guidance)
-
Has the Helping Hand Bracket Been Installed in the Correct Location?
Ventilation Zone / Cavity, Fire Barrier Installation
-
Has The Correct Type Fire Barrier Been Installed?
-
Has the Correct Fixing Method Been Used for The Fire Barrier?
-
Is The Fire Barrier Going to Fore Fill its Requirements? (Correct Tolerances around the Fire Barrier)
-
Is the Cavity Free of Debris Ahead of Closing Out?
Timber Façade
-
Has The Correct Façade Been Installed?
-
Has The Correct Fixings Been Installed?
-
Has the Correct Number of Fixings Been Used?
-
Has the Correct Torque Setting Been Used? (Contractor to demonstrate that fixing has been installed in line with manufacturers guidance)
-
Is the Installation Satisfactory?
Completion of Area
-
Is The Overall Installation Acceptable?
- Yes
- No
- N/A
-
Are There Any Works Outstanding?
Sign off
-
Warden Representative Sign Off
-
Clerk of Works Sign Off
Installation of New System (Stone Facade)
Partial Fill Insulation
-
Has the Correct Insulation Been Installed?
-
Has the Correct Fixings Been Installed?
-
Correct Number / Location of Fixings?
New Steel Supports (To Support Stone Work)
-
Has The Correct Steel Supports Been Used?
-
Has The Correct Fixings Been Installed?
-
Has the Correct Number of Supports Been Used?
-
Has the Correct Torque Setting Been Used? (Contractor to demonstrate that fixing has been installed in line with manufacturers guidance)
-
Is the Installation Satisfactory?
Cavity, Fire Barrier Installation
-
Is the Existing Steel Support System in a Reusable Standard?
-
Has The Correct Type Fire Barrier Been Installed?
-
Has the Correct Fixing Method Been Used for The Fire Barrier?
-
Is The Fire Barrier Going to Fore Fill its Requirements? (Correct Tolerances around the Fire Barrier)
-
Is the Cavity Free of Debris Ahead of Closing Out?
-
Has the Cavity Train Been Installed?
-
Has the Cavity Tray Been Installed in the Correct Location?
Stone Work
-
Has the Correct Stone Been Installed In the Correct Location as Per the Drawings?
-
Has the Weep Holes Been Installed?
-
Has The Stone Been Installed / Laid To A Satisfactory Standard? (Correct Mortar Bedding, Joints Pointed, Plumb & Level)
Completion of Area
-
Is the Overall Installation Acceptable?
- Yes
- No
- N/A
-
Are There Any Works Outstanding?
Sign off
-
Warden Representative Sign Off
-
Clerk of Works Sign Off
Installation of New System (Brick)
Partial Fill Insulation
-
Has the Correct Insulation Been Installed?
-
Has the Correct Fixings Been Installed?
-
Correct Number / Location of Fixings?
Steel Supports (To Support Brickwork Work)
-
Is the Existing Steel Support System in a Reusable Standard?
Cavity, Fire Barrier Installation
-
Has The Correct Type Fire Barrier Been Installed?
-
Has the Correct Fixing Method Been Used for The Fire Barrier?
-
Is The Fire Barrier Going to Fore Fill its Requirements? (Correct Tolerances around the Fire Barrier)
-
Is the Cavity Free of Debris Ahead of Closing Out?
-
Has the Cavity Train Been Installed?
-
Has the Cavity Tray Been Installed in the Correct Location?
Brick Work
-
Has the Correct Bricks Been Installed In the Correct Location as Per the Drawings?
-
Has the Weep Holes Been Installed?
-
Has The Stone Been Installed / Laid To A Satisfactory Standard? (Correct Mortar Bedding, Joints Pointed, Plumb & Level)
Completion of Area
-
Is the Overall Installation Acceptable?
- Yes
- No
- N/A
-
Are There Any Works Outstanding?
Sign off
-
Warden Representative Sign Off
-
Clerk of Works Sign Off