Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location
  • Weather at the Time of Report

Works Undertaken

  • Drawings Highlighted Area of Works

  • Confirmation of the Area that is Being Inspected. Please use Gridline and Floor no's that confirm the highlighted section on the drawing above.

Removal

  • Images to be taken prior to removal of any materials

  • Any Damage to the Immediate Area (if so images to be taken)

  • Any Damage Caused by Removing Rain Screen Covering?

  • Have all Required Materials Been Removed?

  • Is there any Evidence of Damage or Remedials Required to the Inner Wall or Existing Construction?

Sign off

  • Warden Representative Sign Off

  • Clerk of Works Sign Off

Installation of New System (Timber Facade)

Mineral Wool Installation

  • Has the Correct Mineral Wool Been Installed?

  • Has the Correct Fixings Been Installed?

  • Correct Number / Location of Fixings?

Sheathing Board & Membrane

  • Has the Correct Sheathing Board Been Installed?

  • Correct Number / Location of Fixings?

  • Has the Correct Membrane Been Installed?

Helping Hand Bracket

  • Has the Correct Helping Hand Been Installed?

  • Has the Correct Torque Setting Been Used? (Contractor to demonstrate that fixing has been installed in line with manufacturers guidance)

  • Has the Helping Hand Bracket Been Installed in the Correct Location?

Ventilation Zone / Cavity, Fire Barrier Installation

  • Has The Correct Type Fire Barrier Been Installed?

  • Has the Correct Fixing Method Been Used for The Fire Barrier?

  • Is The Fire Barrier Going to Fore Fill its Requirements? (Correct Tolerances around the Fire Barrier)

  • Is the Cavity Free of Debris Ahead of Closing Out?

Timber Façade

  • Has The Correct Façade Been Installed?

  • Has The Correct Fixings Been Installed?

  • Has the Correct Number of Fixings Been Used?

  • Has the Correct Torque Setting Been Used? (Contractor to demonstrate that fixing has been installed in line with manufacturers guidance)

  • Is the Installation Satisfactory?

Completion of Area

  • Is The Overall Installation Acceptable?

  • Are There Any Works Outstanding?

Sign off

  • Warden Representative Sign Off

  • Clerk of Works Sign Off

Installation of New System (Stone Facade)

Partial Fill Insulation

  • Has the Correct Insulation Been Installed?

  • Has the Correct Fixings Been Installed?

  • Correct Number / Location of Fixings?

New Steel Supports (To Support Stone Work)

  • Has The Correct Steel Supports Been Used?

  • Has The Correct Fixings Been Installed?

  • Has the Correct Number of Supports Been Used?

  • Has the Correct Torque Setting Been Used? (Contractor to demonstrate that fixing has been installed in line with manufacturers guidance)

  • Is the Installation Satisfactory?

Cavity, Fire Barrier Installation

  • Is the Existing Steel Support System in a Reusable Standard?

  • Has The Correct Type Fire Barrier Been Installed?

  • Has the Correct Fixing Method Been Used for The Fire Barrier?

  • Is The Fire Barrier Going to Fore Fill its Requirements? (Correct Tolerances around the Fire Barrier)

  • Is the Cavity Free of Debris Ahead of Closing Out?

  • Has the Cavity Train Been Installed?

  • Has the Cavity Tray Been Installed in the Correct Location?

Stone Work

  • Has the Correct Stone Been Installed In the Correct Location as Per the Drawings?

  • Has the Weep Holes Been Installed?

  • Has The Stone Been Installed / Laid To A Satisfactory Standard? (Correct Mortar Bedding, Joints Pointed, Plumb & Level)

Completion of Area

  • Is the Overall Installation Acceptable?

  • Are There Any Works Outstanding?

Sign off

  • Warden Representative Sign Off

  • Clerk of Works Sign Off

Installation of New System (Brick)

Partial Fill Insulation

  • Has the Correct Insulation Been Installed?

  • Has the Correct Fixings Been Installed?

  • Correct Number / Location of Fixings?

Steel Supports (To Support Brickwork Work)

  • Is the Existing Steel Support System in a Reusable Standard?

Cavity, Fire Barrier Installation

  • Has The Correct Type Fire Barrier Been Installed?

  • Has the Correct Fixing Method Been Used for The Fire Barrier?

  • Is The Fire Barrier Going to Fore Fill its Requirements? (Correct Tolerances around the Fire Barrier)

  • Is the Cavity Free of Debris Ahead of Closing Out?

  • Has the Cavity Train Been Installed?

  • Has the Cavity Tray Been Installed in the Correct Location?

Brick Work

  • Has the Correct Bricks Been Installed In the Correct Location as Per the Drawings?

  • Has the Weep Holes Been Installed?

  • Has The Stone Been Installed / Laid To A Satisfactory Standard? (Correct Mortar Bedding, Joints Pointed, Plumb & Level)

Completion of Area

  • Is the Overall Installation Acceptable?

  • Are There Any Works Outstanding?

Sign off

  • Warden Representative Sign Off

  • Clerk of Works Sign Off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.