Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • WEATHER

  • SITE CONDITIONS

  • TRAFFIC MANAGEMENT

  • FENCING & HSE SIGNAGE

1.0 PRE-COMMENCEMENT

  • Have lot pegs/stakes and TBM's been installed

  • Have drawings been approved and issued for construction

  • Have the EMP, TMP and PMP been submitted to the relevant authority to asset and approval to commence construction works granted?

  • Has pre-commencement meeting occurred with representatives from the Contractor, Charlton Degg and relevant authorities on site?

2.0 Preliminaries : Establishment, Stripping, Bulk Excavation, Vegetation Removal/Protection

  • Vegetation Removal/TPZ's installed in accordance with approved plans?

  • Demolition / Stripping status

  • Bulk Earthworks, Cut / Fill status

  • Road Boxing Status

  • Topsoiling/Reinstatement Status

2.1 Preliminaries - Establishment, Earthworks, Excavation

  • Are truck / scraper routes on site clearly designated and separated from public access areas.

  • Is fill being placed in layers and compacted under Level 1 supervision

  • Are compaction tests being conducted to specified Level by NATA registered tester.

2.2 Safety - Earthworks, Excavation

  • Does the contractor have utilities / services plans on site.

  • Does plant and equipment have suitable warning lights and reversing beepers

  • Are personnel in the vicinity of operating plant wearing high vis clothing and helmets where required.

2.3 Environmental - Earthworks, Excavation.

  • Is there provision to minimize dust / mud from leaving the site.

  • Do stockpiles have adequate silt runoff protection.

  • Are environmental No Go/TPZ's fenced where required.

  • Are silt traps in place to prevent silt build up in previously installed drainage system.

3.0 SEWER

  • Sewer Sub Contractor Onsite

  • Does the sewer contractor have issued for construction drawings and the latest revision

  • Has the specific sewer construction audit been completed?

4.0 Potable and Non Potable Water

  • Water Sub Contractor Onsite

  • Does the water contractor have issued for construction drawings and the latest revision

  • Are materials stored correctly on site

  • Has the specific Potable and Non Potable construction audit been completed?

5.0 Drainage Works

  • Drainage Sub Contractor Onsite

  • Telstra / NBN Sub Contractor Onsite

  • Electrical Sub Contractor Onsite

5.1 Works - Trenching, Pipelaying, Backfill, Surface Fittings

  • Drainage Works Status

  • Is there an accredited pipe layer on site.

  • Are trench widths adequate for pipe size/ type

  • Is the bedding material & thickness within tolerance and being compacted correctly

  • Are pipes being installed in accordance with design specification and manufacturers recomendations.

  • Are clearances to other services being maintained as per specification.

  • Does trench backfill material comply with standard drawings and specifications

  • Are lids / covers as per design and set correctly.

  • Endwall / Headwall Status

5.2 Safety - Trenching, Pipelaying, Backfill, Surface Fittings

  • Does the contractor have utilities / services plans on site.

  • Does plant and equipment have suitable warning lights and reversing beepers

  • Is ground support suitable for the ground conditions and depth of excavation

  • Are workers provided with a ladder or other means of access and egress where required.

  • Is appropriate PPE being worn by workers where required

  • Are trenches barricaded and made safe when left open.

  • Is lifting equipment suitable for the works being carried out.

Telecommunications & Electrical Reticulation

  • Telecommunications/NBN Status

  • Electrical Retic Status

6.0. PAVEMENT

  • Sub grade improvement status

  • Cap layer Status

  • Conduits / AG Status

  • Class 3 FCR Status

  • Class 2 FCR Status

  • Asphalt Works Status

  • Wearing Course Asphalt Status

6.1 Works - Pavement

  • Has Council inspected and approved the subgrade/sub grade improvement?

  • Are conduits and AG drains at correct depth

  • Does trench backfill material comply with standard drawings and specifications

  • Does pavement material comply with plans, standard drawings and specifications.

  • Is compaction equipment adequate to achieve specified results.

  • Is crushed rock being placed in layers and compacted as per specification.

  • Are compaction tests being conducted to specified Level by NATA registered tester.

  • Is the weather suitable for priming or placing asphalt.

6.2 Safety - Pavement

  • Does plant and equipment have suitable warning lights and reversing beepers

  • Is appropriate PPE being worn by workers where required

7.0. Concrete Works

  • Kerb and Channel Status

  • Footpath and vehicular access Status

  • Threshold treatment status

7.1 Works - Concrete

  • Are weather conditions suitable for placing concrete.

  • Are access routes for trucks clearly defined

  • Is boxing depth and crushed rock bedding as per specification

  • Is form work adequate for the structure being constructed.

  • Is reinforcing as per specification and installed correctly.

  • Are kerb markings for services being installed.

7.2 Safety - Concrete

  • Is appropriate PPE being worn by workers where required

  • Does plant and equipment have suitable warning lights and reversing beepers

8.0. Rock Work / MIscellaneous

  • Rock Wall Status

  • Rock Endwall / Headwall Status

  • Rock Beaching Status

8.1 Works - Rockwork, Miscellaneous

  • Are rocks suitable for intended purpose and of appropriate size/ grading.

  • Are rocks sitting on concrete cushions over pipe ends

  • Are rocks being placed to specification and grouted as required.

  • Is reinforcing being installed as per specification.

8.2 Safety - Rockwork, Miscellaneous

  • Is appropriate PPE being worn by workers where required

  • Does plant and equipment have suitable warning lights and reversing beepers

COMMENTS / PROGRESS / INSTRUCTIONS.

  • COMMENTS

  • PHOTOS

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.