Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
WEATHER
-
SITE CONDITIONS
-
TRAFFIC MANAGEMENT
-
FENCING & HSE SIGNAGE
1.0 PRE-COMMENCEMENT
-
Have lot pegs/stakes and TBM's been installed
-
Have drawings been approved and issued for construction
-
Have the EMP, TMP and PMP been submitted to the relevant authority to asset and approval to commence construction works granted?
-
Has pre-commencement meeting occurred with representatives from the Contractor, Charlton Degg and relevant authorities on site?
2.0 Preliminaries : Establishment, Stripping, Bulk Excavation, Vegetation Removal/Protection
-
Vegetation Removal/TPZ's installed in accordance with approved plans?
-
Demolition / Stripping status
-
Bulk Earthworks, Cut / Fill status
-
Road Boxing Status
-
Topsoiling/Reinstatement Status
2.1 Preliminaries - Establishment, Earthworks, Excavation
-
Are truck / scraper routes on site clearly designated and separated from public access areas.
-
Is fill being placed in layers and compacted under Level 1 supervision
-
Are compaction tests being conducted to specified Level by NATA registered tester.
2.2 Safety - Earthworks, Excavation
-
Does the contractor have utilities / services plans on site.
-
Does plant and equipment have suitable warning lights and reversing beepers
-
Are personnel in the vicinity of operating plant wearing high vis clothing and helmets where required.
2.3 Environmental - Earthworks, Excavation.
-
Is there provision to minimize dust / mud from leaving the site.
-
Do stockpiles have adequate silt runoff protection.
-
Are environmental No Go/TPZ's fenced where required.
-
Are silt traps in place to prevent silt build up in previously installed drainage system.
3.0 SEWER
-
Sewer Sub Contractor Onsite
- None
- Califam
- Pescatore
- Azzona
- Delplant
- Harris Civil
-
Does the sewer contractor have issued for construction drawings and the latest revision
-
Has the specific sewer construction audit been completed?
4.0 Potable and Non Potable Water
-
Water Sub Contractor Onsite
- None
- Comdain
- Tunney & Houlihan
- Mooroolbark Exc
- Yarra Valley Exc
- Jayelle
- Sands Plumbing
- Delplant
- DR & JP Stevens
-
Does the water contractor have issued for construction drawings and the latest revision
-
Are materials stored correctly on site
-
Has the specific Potable and Non Potable construction audit been completed?
5.0 Drainage Works
-
Drainage Sub Contractor Onsite
- None
- Winslow
- Symon Bros
- Delplant
- Jaydo
- Nasi
- Lojac
- Maw Civil
-
Telstra / NBN Sub Contractor Onsite
-
Electrical Sub Contractor Onsite
5.1 Works - Trenching, Pipelaying, Backfill, Surface Fittings
-
Drainage Works Status
-
Is there an accredited pipe layer on site.
-
Are trench widths adequate for pipe size/ type
-
Is the bedding material & thickness within tolerance and being compacted correctly
-
Are pipes being installed in accordance with design specification and manufacturers recomendations.
-
Are clearances to other services being maintained as per specification.
-
Does trench backfill material comply with standard drawings and specifications
-
Are lids / covers as per design and set correctly.
-
Endwall / Headwall Status
5.2 Safety - Trenching, Pipelaying, Backfill, Surface Fittings
-
Does the contractor have utilities / services plans on site.
-
Does plant and equipment have suitable warning lights and reversing beepers
-
Is ground support suitable for the ground conditions and depth of excavation
-
Are workers provided with a ladder or other means of access and egress where required.
-
Is appropriate PPE being worn by workers where required
-
Are trenches barricaded and made safe when left open.
-
Is lifting equipment suitable for the works being carried out.
Telecommunications & Electrical Reticulation
-
Telecommunications/NBN Status
-
Electrical Retic Status
6.0. PAVEMENT
-
Sub grade improvement status
-
Cap layer Status
-
Conduits / AG Status
-
Class 3 FCR Status
-
Class 2 FCR Status
-
Asphalt Works Status
-
Wearing Course Asphalt Status
6.1 Works - Pavement
-
Has Council inspected and approved the subgrade/sub grade improvement?
-
Are conduits and AG drains at correct depth
-
Does trench backfill material comply with standard drawings and specifications
-
Does pavement material comply with plans, standard drawings and specifications.
-
Is compaction equipment adequate to achieve specified results.
-
Is crushed rock being placed in layers and compacted as per specification.
-
Are compaction tests being conducted to specified Level by NATA registered tester.
-
Is the weather suitable for priming or placing asphalt.
6.2 Safety - Pavement
-
Does plant and equipment have suitable warning lights and reversing beepers
-
Is appropriate PPE being worn by workers where required
7.0. Concrete Works
-
Kerb and Channel Status
-
Footpath and vehicular access Status
-
Threshold treatment status
7.1 Works - Concrete
-
Are weather conditions suitable for placing concrete.
-
Are access routes for trucks clearly defined
-
Is boxing depth and crushed rock bedding as per specification
-
Is form work adequate for the structure being constructed.
-
Is reinforcing as per specification and installed correctly.
-
Are kerb markings for services being installed.
7.2 Safety - Concrete
-
Is appropriate PPE being worn by workers where required
-
Does plant and equipment have suitable warning lights and reversing beepers
8.0. Rock Work / MIscellaneous
-
Rock Wall Status
-
Rock Endwall / Headwall Status
-
Rock Beaching Status
8.1 Works - Rockwork, Miscellaneous
-
Are rocks suitable for intended purpose and of appropriate size/ grading.
-
Are rocks sitting on concrete cushions over pipe ends
-
Are rocks being placed to specification and grouted as required.
-
Is reinforcing being installed as per specification.
8.2 Safety - Rockwork, Miscellaneous
-
Is appropriate PPE being worn by workers where required
-
Does plant and equipment have suitable warning lights and reversing beepers
COMMENTS / PROGRESS / INSTRUCTIONS.
-
COMMENTS
-
PHOTOS