Title Page
-
Conducted on
-
Prepared by
-
Location
Untitled Page
Audit sheet
-
· Site Supervisor Name
-
· Contractor
-
· Project Number
-
· Date & time
-
1. Have all operatives signed the risk assessment
-
2. Are all operatives wearing the correct PPE
-
3. Operative have the correct SA001 SA002 qualification & in date with SWQR S3 through to S7
-
5. Does the team have access to safe dig prints
-
Images
Live site Civils & Cable
-
1. Are all signs suitable at site set up Chapter 8
-
2. Safety Zone in place
-
3. Are Barriers linked together
-
4. TM required
-
5. Pedestrian Crossing required/ ped walkway
-
6. Back fill apparatus surround and marker tape in place
-
7. Is there backfill materials onsite and suitable for use
-
8. Is Type1 onsite
-
9. Has Edge sealant been applied
-
10. Is bedding sand delivered to site and stored correctly
-
11. Courtesy board displayed correctly
-
12. Backfill base in place
-
13. Has entry points into BT chambers made good and to spec
-
14. BTs boxes left clean & Site Tidiness
-
15. Are all fuels labelled and stored safely in line with COSH
-
Images of the live site
Equipment
-
1. Gate guards / GDU in place
-
2. CAT 4 with Genny
-
3. Cable dispenser
-
4. A frame for Back rope
-
5. Are cable guides in place for pulling of cable & subduct
-
6. Cable lubricant maybe required when pulling equipment through Openreach infrastructure
-
7. Vehicle fit for purpose
Comments to highlight great working practices
Signed
-
Signed by Auditor