Cladding backing structure

  • Site: Wembley Park NW07-NW08

  • Client: Wates

  • Checked on behalf of MPrice

  • Location

  • Block/phase

Requirements

  • Are relevant drawings available on site?

Checklist

Brackets

  • Are the helping hand brackets correct with isolation packer?

  • Are the helping hand brackets fitted plum?

  • Are the correct 8mm/50mm tek fixings with rubber washer used?

Rails

  • Are backing rails fitted correctly and plum?

  • Have the correct fixing been used to fix the rails to the helping hand brackets?

  • Are the gaskets installed on rail ?

Waterproofing/sealing

  • Has relevant waterproofing been fitted?

  • Is the waterproofing sealed and damage free?

  • Has foil tape been used correctly on joints to ensure there are no exposed joints or edges?

Insulation

  • Has the correct size/type of insulation been used?

Brick work areas

Ancon channels

  • Have the ancon channels been correctly fitted?

  • Has the correct kingspan been used and edges sealed with foil tape?

  • Have the correct fixings been used and covered with foil tape ?

Photos of Inspected works

  • Photos of cladding backing structure

Comments

  • Are there any comments?

Signature

  • Checked on behalf of MPrice

  • Checked on behalf of Wates (deemed accepted if not returned by 1700 2 days after offered by MPrice)

End of inspection

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.