Fire stop inspection
-
Client: Wates
-
Job title: Wembley Park-NW07-NW08
-
MPrice inspection
-
Location
-
Block or phase
Fire breaks areas
-
Have the fire stops been installed under the doors and windows correctly RV120/120
-
Is firebreak installed to correct areas?
-
Have the balcony brackets been sealed between joints/gaps with the fire mastic.? Dc 800 fire stop
-
Are correct fixings used and fixings spaced out correctly to 600mm-300mm as specified ?<br>
-
Is firebreak installed to correct detail?
-
Is firebreak damage free?
-
Are joins correctly foiled taped?
-
Is fire stops under correct compression on C/W FS120
-
Has correct fire rated mastic been used Dc 800 fire stop on gaps
-
Is mastic neat and damage free, forming a continuous unbroken seal?
-
Have the GS -Fs120/20 been used behind brackets?
Cavity fire stop areas
-
Have the correct horizontal fire barrier been used ? (120min) RV120/120
-
Have the vertical fire stop been used ? RV 90-30
-
Has the correct fixings and brackets been used. With the correct centres?300mm-600mm
-
Is the party wall RV/90-30 been done to correct locations?
-
Is firebreak damage free?
-
Has the brackets been trimmed to the minimum amount +10mm to +50mm?
-
Are joins correctly foiled taped?
-
Have the brackets been split and folded correctly.?
-
Make sure the air gap don't exceed more than the required amount ?<br>(GREEN 25mm) (RED 50mm)
Duo slab insulation.
-
Has the correct size slab been used ? 75mmx2
-
Has the joints been off set?
-
Has the correct fixings been used ? Refer to data sheets
-
Is the duo clean and damage free?
-
Is duo slab free of gaps?
Photo of firebreak and components
-
Photo of firebreak
-
Photo of elevations location checked.
Comments
-
Any comments