Title Page

  • Conducted on

  • Prepared By

  • Project

  • Main Contractor

  • Block

  • Floor Level

  • Area/Room

Internal Partitions & Lining : Spec & Inspection

Internal Partitions Description.

  • Partition Type

  • Fire Rating in accordance with FCD

  • Acoustic Rating

  • Type of Floor & Ceiling Channel

  • Type Of Stud

  • Stud Centres

  • Deflection

  • Type of Plasterboard per Partition Type :

  • Acoustic Sealant required

  • Insulation Type

Partition 1st Fix construction

  • Inspection of metals approved & CE marked.

  • Datum & Grid Lines are given by the Main Contractor.

  • Are the partitions set out As per Layout Drawings & Spec?

  • Base tracks Installed As per Layout Drawings & Partition spec, including fixings centres.

  • Partition Head Tracks Installed As per Layout Drawings & Partition spec.

  • Correct Studs are installed & checked to be level and plumb ensuring deflection tolerance is correct.

  • Door opes are installed as per Door Schedule/Layout Drawings.

  • All Mechanical services requiring grounds have been marked on metal studs.

  • Grounds are installed on level and plumb to the correct height as required.

  • All service penetrations are framed as per the markups/Builders Opes Drawings.

2nd Fix Partitions

  • Closure cert issued by the Main Contractor.

  • The correct type of boards used as per drawings & specs to both sides of the partition.

  • Boards are installed to ensure correct deflection requirements are achieved.

  • Correct drywall screws length are used for each layer of board installed

  • Correct acoustic insulation installed in partitions as per spec and secured in place?

MF Ceilings

1st Fix MF ceiling

  • Fire tape was installed as per the Manufacturers Installation Guide.

  • Inspection of all metal approved.

  • Datum & Grid Lines given by the Main Contractor

  • The MF Ceiling is installed at the correct height as per the latest RCP drawings.

  • The MF6A perimetral channel is installed as per the Manufacturers Installation Guide.

  • The MF7 main bar is installed as per the Manufacturers Installation Guide.

  • Hangers installed as per the Manufacturers Installation Guide.

  • The MF5 primary channel is installed as per the Manufacturers Installation Guide.

  • Ceiling metal set out and ready for marking of any ground required and avoiding clashes with light fittings where possible?

  • Grounds installed as required by M&E onsite markings.

2nd Fix of MF ceiling

  • Void Closure cert issued by the Main Contractor?

  • Ceilings are boarded using the correct boards as per drawings & specs?

  • Correct number of fixings installed as per the Manufacturers Installation Guide.

Partition & Ceiling Finishes

Finishing to Partition & Ceiling systems

  • Corner / Stop beads installed correctly and plumb.

  • Plasterboard joints on Partitions & Ceilings are filled as per the Manufacturers Installation Guide.

  • Tape & Joint / SkimCoat installed as per the Manufacturers Installation Guide.

Waste management

Waste Management

  • 1 - Debris and waste cleared out

  • 2 - Work area cleaned

  • 3 - Waste segregated as per guidelines

  • Any other issues?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.