Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Personnel
-
Concessionaire
-
Terminal
-
Project Details
-
RU No / Location
-
Contractor
-
Sub Contractor
Part 1 - Site Set-Up
Hoarding
-
Brick boxes and cleats installed on all panels
-
Vision panel installed
-
Digi lock fitted & code changed once shop staff have de-merchandised
-
Door rebate fitted
-
Door closers fitted
-
Doors open inwards
-
Double door set fitted
-
Safe mobile phone area displayed internally on the hoarding with hatched area
-
Site contact list installed
-
Terminal facing hoardings to have graphic's installed (Require Heathrow approval)
-
Mat to be provided at hoarding doors to prevent dust engress into terminal concourse
-
Hoardings without graphics to have cover strips, skirting and painted.
-
If hoarding has been installed by Thomas Interiors Limited has Principle Contractor accepted its condition and have a signed acceptance letter.
Internal H&S Board to Display (As a Minimum)
-
F10
-
Heathrow Permit to Work
-
Sprinkler Isolation Permit
-
Fire Alarm Isolation Permit
-
Hot Works Permit
-
PPE Requirements/Site Rules
-
Fire Evacuation Plan
-
First Aid Contacts & Procedures
-
Emergency Numbers to be displayed inc Heathrow Emergency No: 222 or 02087591212
-
Heathrow Detailed Design Approval Letter
-
Health & Safety Law
Site Rig and Temporary Lighting
-
Electrical Services Isolated
-
Site Rig Installed
-
Site Rig condition acceptable (No loose wiring, glands in place etc.)
-
110V Florescent type lighting installed
-
110V Emergency light installed
Fire Point
-
Fire Extinguishers installed
-
Fire Extinguishers in date and not used
Health and Safety File (As a Minimum)
-
Signing In Book
-
Accident Book
-
Site Rig Installation Certificate
-
F10
-
Heathrow Permit to Work
-
Sprinkler Isolation Permit
-
Fire Alarm Isolation Permit
-
Hot Works Permit
-
Fire Evacuation Plan
-
First Aid Contacts & Procedures
-
Waste Away Procedures
-
Logistics
-
Risk Assessments (Principle Contractor & Sub Contractor)
-
Method Statements (Principle Contractor & Sub Contractor)
-
Tool Box Training
-
Heathrow Detailed Design Approval Letter
Safety Arrangements
-
Is there safe access/egress on and around site?
-
Is there suitable signage around the workplace?<br>
-
Are suitable exclusion zones set up?
-
Is work at height properly managed?
-
Is scaffolding suitable and inspected in accordance with statutory requirements?
-
Are adequte electrical safety arrangements in place (PAT testing, cable management etc)
-
Are there adequate arrangements for the management of noise and vibration risk?
-
Is housekeeping suitable in welfare and office areas?
-
Is housekeeping suitable in equipment and material storage areas?
-
Is housekeeping suitable on site?
Part 2
Outstanding Issues
-
Principal Contractor must agree to resolve all items listed below within the timescales detailed. Failure to comply will lead to all work on site to cease.
-
Priority A - Urgent. Action Immediately
Priority B - Action within 24 hours
Priority C - Action within 48 hours
Priority D - Action within 10 days
Part 3
Sign Off
-
Appointed Contractor
-
Commercial Delivery Manager
-
Guidance:
This document should be completed for all Heathrow Retail Concessions Projects as evidence that the site set up is complete before any site commences.
If the principle contractors fail to all outstanding items within the agreed timescales the site will be closed until all items are completed.
The hard copy form is intended to be a live document that should be available for inspection at any time