Section 1. The Facility
-
Is authorised access required to enter the facility.
-
Is the door self closing. Does door closer mechanism work correctly.
-
Door not held open at time of inspection.
-
Are there emergency contact details posted on the entrance door.
-
Is there hazard signage in place on the entrance door.
-
Are the filters for the natural ventilation grille changed regularly.
-
Is the mechanical ventilation tested on a regular basis and is it linked to the BMS.
-
Is the facility clean and tidy.
-
Has the floor been swept.
Section 2. Oxygen Monitoring System
-
Is there an Oxygen display before entering the facility. Was the readout within acceptable limits.
-
Were there any audible alarms sounding.
-
Does the internal display correspond with the external display.
-
Is the system calibrated
When was it last calibrated. -
Is the oxygen monitoring system linked to the BMS.
-
Is a method available to shut off nitrogen delivery to the facility.
Is the system checked regularly.
Section 3. PPE
-
Are face shields, gloves, ear muffs and apron available in the facility.
-
Were staff wearing correct PPE at time of inspection.
Section 4. Equipment
-
Is the internal nitrogen pipeline regularly inspected.
-
Is the nitrogen level of the tanks checked manually and records kept.
-
Is the liquid level displayed on the controller compatible with the manual readout
-
Are steps available on tanks.
-
Is there a preventative maintenance contract on the tanks.
-
If there is no maintenance contract how are they maintained and checked to be in good working order.
Is documentation available. -
Are the small nitrogen dewars in good condition.
-
Is the cryocart maintained to be in good working order.
Section 5. Training and Records
-
Is there staff training for safe handling of liquid Nitrogen.
Are records available. -
Are there standard operating procedures documented for:
-Collection of liquid nitrogen
- transport of liquid nitrogen from the facility
-Depositing or retrieving samples.
-disposal of liquid nitrogen -
For dewars used outside the facility has their filling and use been risk assessed.
-
Are risk assessments available on line.
Section 6. Sign off
-
Laboratory Operations Officer
-
Cryogenic Representative