Title Page

  • lot 10 8870 the point circuit sanctuary cove

  • Conducted on

  • Prepared by

  • Location

Trade Sign Off

IMPORTANT NOTES READ BEFORE PROCEEDING

  • ALL CONTRACTORS MUST COMPLETE APPLICABLE CHECK LISTS & MUST BE SIGNED OFF PRIOR TO COMPLETION OF WORKS AND THE SUBMISSION OF INVOICES. ALL QUESTIONS MUST BE ANSWERED. NO INVOICE WILL BE PROCESSED UNLESS CHECKLIST IS COMPLETED.

1st Floor slab suspended reinforcement

  • has surveyor pinned locations of wet areas

  • is the scaffold suitable for works

  • formwork installation complete

  • are penetrations for plumbing and electrical visible

  • are all the starter bars installed for blockwork

  • are all the starters installed for off form concrete

  • are there any outstanding items

  • has the engineer signed off and approved all the steel installation

  • remove all debris platform and blown clean, ensure all off cuts and strappings etc are in bin

  • is the area ready for next trade

  • completed by

  • Site Manager Sign off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.