Title Page

  • Site Location

  • Conducted on

  • Prepared by

  • Location

Trade Sign Off

IMPORTANT NOTES READ BEFORE PROCEEDING

  • ALL CONTRACTORS MUST COMPLETE APPLICABLE CHECK LISTS & MUST BE SIGNED OFF PRIOR TO COMPLETION OF WORKS AND THE SUBMISSION OF INVOICES. ALL QUESTIONS MUST BE ANSWERED. NO INVOICE WILL BE PROCESSED UNLESS CHECKLIST IS COMPLETED.

Site Cut

  • Site cut to all bench and cut levels and trimmed to all boundaries

  • is driveway bulk excavated to levels

  • is rubble shakedown installed

  • is sediment control measures installed as per control plan

  • Spoil removed from site

  • all vegetation removed

  • Photos

  • completed by

Pool Shell

  • screw piers installed

  • engineers inspection and approved

  • shell poured

  • plumbing and electrical rough ins complete

  • debris and spoil removed from site

  • formwork stripped and removed from site

  • are repairs need to the shell prior to other trades commencing works? if YES, contact site manager immediately.

  • site secure

  • Photos

  • completed by

Concreter Footings

  • engineers inspection approved

  • all debris and washouts moved to bin or nominated area

  • does the surveyor need to return to repeg for block layer. if yes call site manager

  • site left secure

  • Photos

  • completed by

Retaining Blockwork Core Filled

  • all blockwork complete

  • engineers inspection approved

  • core filling complete

  • all debris moved to bin

  • Photos

  • completed by

Waterproofing Retaining Walls

  • membrane installed

  • core flute installed

Suspended Formwork Pool and BBQ Area

  • Scaffold installed and tagged

  • Structural steel installed. if NO call site manager

  • block work complete. if NO call site manager

  • has surveyor completed set out on suspended floor plate

  • penetrations installed

  • set downs installed

  • engineers inspection approved

  • formwork stripped

  • photos

  • completed by

Concreter external slabs

  • suspended formwork complete

  • engineers inspection approved

  • all debris and washouts moved to bin or nominated area

  • site left secure

  • does the surveyor need to return to repeg for block layer. if yes call site manager

  • external stairs complete and approved by engineer

  • Photos

  • completed by

Screw Piers

  • all screw piers installed as per plan

  • debris removed from site

  • are screw piers core filled

  • if not core filled are screw piers capped or covered to stop debris falling in during works

  • site left secure

  • does the surveyor need to regeg for the Plumber. if yes call site manager

  • photos

  • completed by

Plumber Drainage

  • under slab drainage installed

  • temp water to site with hose cock and site shed connected

  • water feed lead in

  • water feed to Jetty

  • Gas mains lead in

  • Gas slab provision to meter

  • Gas slab provisions to other areas

  • stormwater drainage installed

  • are all trenches back filled and excess spoil stock piled in designated area at the front of site for removal

  • all debris in bin or rubbish compound

  • are there markers for locations to avoid damage by other trades

  • does the surveyor need to repeg for concreter. if yes call site manager

  • Photos

  • completed by

Electrical Mains

  • electrical mains lead in complete

  • lead in or conduit to jetty for power. 3 phase

  • temp power to site complete and forms lodged

  • estimated time for live power

  • provision for island bench and all floor mounted power conduits installed

  • NBN and data lead in

  • Location of the steel posts are checked against the conduits

  • Site left secure

  • Photos

  • completed by

Under Slab Termite Barriers

  • all penetrations collared

  • all feed in conduits protected

  • site left secure

  • Photos

  • completed by

Concreter Main GF Slab

  • Formwork in correct positions, relative to survey pins

  • Formwork measurements correct, with adequate bracing

  • Formwork square

  • All formwork level

  • surveyors inspection sign off

  • Slab height as per plans and surveyor height pegs

  • all Step downs installed(as applicable)

  • All footings, beams and slab completely vibrated

  • Engineers inspection and approved prior to pouring

  • concrete strength and slump confirmed correct

  • no cold joints in pour

  • all internal pegs removed

  • Formwork stripped, debris in bin

  • Spoil removed to front of site for easy removal. one pile

  • Wash out in bin

  • site left secure

  • photos

  • completed by

GF Block Work including retaining and garden walls

  • surveyor pinned slab for block set out. if NO call site manager

  • termite treatment barrier installed prior to commencement. if NO call site manager

  • blockwork braced prior to core fill

  • window and door openings confirmed for location as per plans

  • blockwork washed out prior to engineers inspection

  • blockwork completed around structural steel

  • engineers inspection prior to core fill, approved

  • remove all debris to bins provided

  • remove all left over mortar and clean to bottom of slab and remove to bin

  • is blockwork plumb and level. with all core fill cleaned off top course for suspended formwork

  • Slab cleaned

  • concrete pump waste and washout in bin

  • Photos

  • Completed by

Scaffold installation

  • scaffold installed as per scaffold plan

  • scaffold signed off

  • stair bottom step to natural ground no more that 190mm

  • photos

  • completed by

Suspended Formwork 1st Floor

  • Scaffold installed and tagged

  • Structural steel installed. if NO call site manager

  • block work complete. if NO call site manager

  • has surveyor completed set out on suspended floor plate

  • penetrations installed

  • set downs installed

  • engineers inspection approved

  • photos

  • completed by

Concreter Main 1st Floor Slab

  • Formwork in correct positions, relative to survey pins

  • step down and wet area formwork installed to survey pins

  • Formwork measurements correct, with adequate bracing

  • Formwork square

  • All formwork level

  • surveyors inspection sign off

  • Slab height as per plans and surveyor height pegs

  • all Step downs installed(as applicable)

  • All footings, beams and slab completely vibrated

  • Engineers inspection and approved prior to pouring

  • concrete strength and slump confirmed correct

  • no cold joints in pour

  • all internal pegs removed

  • Formwork stripped, debris in bin

  • Spoil removed to front of site for easy removal. one pile

  • Wash out in bin

  • site left secure

  • photos

  • completed by

1st Floor Block Work

  • surveyor pinned slab for block set out. if NO call site manager

  • termite treatment barrier installed prior to commencement. if NO call site manager

  • blockwork braced prior to core fill

  • window and door openings confirmed for location as per plans

  • blockwork washed out prior to engineers inspection

  • blockwork completed around structural steel

  • engineers inspection prior to core fill, approved

  • remove all debris to bins provided

  • remove all left over mortar and clean to bottom of slab and remove to bin

  • is blockwork plumb and level. with all core fill cleaned off top course for suspended formwork

  • Slab cleaned

  • concrete pump waste and washout in bin

  • Photos

  • Completed by

Frames and Trusses

  • all frames plumb and straight

  • all tie down installed

  • all bracing installed

  • all trusses complete with tie down

  • structural steel installed

  • engineers inspection approved

  • all debris removed to bin

  • slab swept clean

  • photos

  • completed by

Metal Roofing

  • all parapet flashings installed

  • all flashing installed

  • lower roofs installed

  • all upper roofing installed

  • DP nozzles and rain heads installed

  • All flashings scribed to roofing profile

  • all debris removed to bin

  • scaffold not removed and as sign off

  • profiles matching plans

  • photos

  • completed by

Window Installation

  • all sub sills installed

  • all windows and doors installed

  • all caulking and sealing complete

  • window frames taped both sides and plastic protection to all glazing both sides

  • photos

  • completed by

Electrical Rough in

  • all lighting wired

  • in floor power and lights

  • all power wired

  • all external GPO's wired

  • all 3 phase wired

  • all data wired

  • jetty 3 phase

  • all security

  • all debris removed to bin including all cable clippings

  • photos

  • completed by

Plumber Rough in

  • water points

  • fridge point

  • external taps

  • jetty

  • all debris removed to bin

  • photos

  • Completed by

HVAC Roughin

  • flexi duct installed

  • solid ducting installed

  • blower units and zoning motors installed

  • all debris removed to bin

  • photos

  • completed by

Plasterboard and Suspended Ceilings

  • suspended ceiling frame complete

  • blocking for all fitments and adaptable fittings

  • insulation installed to walls and ceilings

  • framing as per reflected ceiling plan complete

  • P50 details

  • door jambs installed plumb and level

  • square set jambs and windows

  • level 5 achieved

  • all debris removed to bin

  • floor scrpaed of all plaster

  • floor swept and blown out left ready for fix out

  • photos

  • completed by

Waterproofing Wet Areas

  • water stops installed

  • caulking as required

  • puddle flanges and wonder caps

  • debris removed to bin

  • signage wet waterproofing until.... installed

  • photos

  • completed by

Wet Area Tiling

  • levelling wedges used on floor and walls

  • membrane installed and not damaged at time of tiling. if damaged call site manager immediately

  • caulking complete

  • grout complete

  • falls to wastes

  • debris removed to bins

  • non tiled floor areas used scrapped to remove debris

  • no cement or bedding materials left on the slab. floor scrapped

  • ram board flooring protection installed and taped throughout

  • photos

  • completed by

Main Floor Tiling and Balconies

  • levelling wedges used on floor and walls

  • membrane installed and not damaged at time of tiling. if damaged call site manager immediately

  • caulking complete

  • grout complete

  • falls to wastes

  • debris removed to bins

  • non tiled floor areas used scrapped to remove debris

  • no cement or bedding materials left on the slab. floor scrapped

  • expansion joints as per NCC current standards

  • tiling cleaned, excess grouts etc removed

  • ram board flooring protection installed and taped throughout

  • photos

  • complete by

Timber Flooring

  • floors levelled

  • membrane installed, photos required

  • caulk expansion joints installed

  • ram board flooring protection installed and taped throughout

  • photos

  • completed by

Cladding and Eaves

  • wrap installed and all opening and holes taped

  • debris removed to bin

  • all joints sealed with sealant

  • trims, angles and starters installed

  • are all fixings flush ready for paint

  • photos

  • completed by

Electrical Fit Off

  • light fittings

  • led strip lighting

  • pendant lighting

  • floor lighting

  • recessed lighting

  • external lighting

  • GPO's

  • external GPO's

  • jetty 3 phase

  • pool pump, irrigation and BBQ area

  • 3 phase AC

  • HWS

  • NBN

  • data points

  • WAP system

  • power to curtain remote system

  • security system

  • HVAC

  • appliances connected

  • sub boards and main circuit board

  • commissioning of all systems

  • photos

  • Completed by

Plumber Fit Off

  • all PC items installed and sealed as required

  • leak tested

  • external taps

  • water to jetty

  • irrigation connections

  • appliances connected

  • photos

  • completed by

Carpenter Fixout

  • door handles

  • latches and catches

  • door stops

  • PC items

  • rubbish removed to bin

  • Photos

  • completed by

Joinery and stone

Pool Completion

Landscaping

Carpenter Fix Out

Carpenter Fit Off

Landscaping Soft Scapes

Landscaping Hard Scapes

Window Servicing

Concrete Tilt Up Fencing

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.