Title Page
-
Site Location
-
Conducted on
-
Prepared by
-
Location
Trade Sign Off
IMPORTANT NOTES READ BEFORE PROCEEDING
-
ALL CONTRACTORS MUST COMPLETE APPLICABLE CHECK LISTS & MUST BE SIGNED OFF PRIOR TO COMPLETION OF WORKS AND THE SUBMISSION OF INVOICES. ALL QUESTIONS MUST BE ANSWERED. NO INVOICE WILL BE PROCESSED UNLESS CHECKLIST IS COMPLETED.
Site Cut
-
Site cut to all bench and cut levels and trimmed to all boundaries
-
is driveway bulk excavated to levels
-
is rubble shakedown installed
-
is sediment control measures installed as per control plan
-
Spoil removed from site
-
all vegetation removed
-
Photos
-
completed by
Pool Shell
-
screw piers installed
-
engineers inspection and approved
-
shell poured
-
plumbing and electrical rough ins complete
-
debris and spoil removed from site
-
formwork stripped and removed from site
-
are repairs need to the shell prior to other trades commencing works? if YES, contact site manager immediately.
-
site secure
-
Photos
-
completed by
Concreter Footings
-
engineers inspection approved
-
all debris and washouts moved to bin or nominated area
-
does the surveyor need to return to repeg for block layer. if yes call site manager
-
site left secure
-
Photos
-
completed by
Retaining Blockwork Core Filled
-
all blockwork complete
-
engineers inspection approved
-
core filling complete
-
all debris moved to bin
-
Photos
-
completed by
Waterproofing Retaining Walls
-
membrane installed
-
core flute installed
Suspended Formwork Pool and BBQ Area
-
Scaffold installed and tagged
-
Structural steel installed. if NO call site manager
-
block work complete. if NO call site manager
-
has surveyor completed set out on suspended floor plate
-
penetrations installed
-
set downs installed
-
engineers inspection approved
-
formwork stripped
-
photos
-
completed by
Concreter external slabs
-
suspended formwork complete
-
engineers inspection approved
-
all debris and washouts moved to bin or nominated area
-
site left secure
-
does the surveyor need to return to repeg for block layer. if yes call site manager
-
external stairs complete and approved by engineer
-
Photos
-
completed by
Screw Piers
-
all screw piers installed as per plan
-
debris removed from site
-
are screw piers core filled
-
if not core filled are screw piers capped or covered to stop debris falling in during works
-
site left secure
-
does the surveyor need to regeg for the Plumber. if yes call site manager
-
photos
-
completed by
Plumber Drainage
-
under slab drainage installed
-
temp water to site with hose cock and site shed connected
-
water feed lead in
-
water feed to Jetty
-
Gas mains lead in
-
Gas slab provision to meter
-
Gas slab provisions to other areas
-
stormwater drainage installed
-
are all trenches back filled and excess spoil stock piled in designated area at the front of site for removal
-
all debris in bin or rubbish compound
-
are there markers for locations to avoid damage by other trades
-
does the surveyor need to repeg for concreter. if yes call site manager
-
Photos
-
completed by
Electrical Mains
-
electrical mains lead in complete
-
lead in or conduit to jetty for power. 3 phase
-
temp power to site complete and forms lodged
-
estimated time for live power
-
provision for island bench and all floor mounted power conduits installed
-
NBN and data lead in
-
Location of the steel posts are checked against the conduits
-
Site left secure
-
Photos
-
completed by
Under Slab Termite Barriers
-
all penetrations collared
-
all feed in conduits protected
-
site left secure
-
Photos
-
completed by
Concreter Main GF Slab
-
Formwork in correct positions, relative to survey pins
-
Formwork measurements correct, with adequate bracing
-
Formwork square
-
All formwork level
-
surveyors inspection sign off
-
Slab height as per plans and surveyor height pegs
-
all Step downs installed(as applicable)
-
All footings, beams and slab completely vibrated
-
Engineers inspection and approved prior to pouring
-
concrete strength and slump confirmed correct
-
no cold joints in pour
-
all internal pegs removed
-
Formwork stripped, debris in bin
-
Spoil removed to front of site for easy removal. one pile
-
Wash out in bin
-
site left secure
-
photos
-
completed by
GF Block Work including retaining and garden walls
-
surveyor pinned slab for block set out. if NO call site manager
-
termite treatment barrier installed prior to commencement. if NO call site manager
-
blockwork braced prior to core fill
-
window and door openings confirmed for location as per plans
-
blockwork washed out prior to engineers inspection
-
blockwork completed around structural steel
-
engineers inspection prior to core fill, approved
-
remove all debris to bins provided
-
remove all left over mortar and clean to bottom of slab and remove to bin
-
is blockwork plumb and level. with all core fill cleaned off top course for suspended formwork
-
Slab cleaned
-
concrete pump waste and washout in bin
-
Photos
-
Completed by
Scaffold installation
-
scaffold installed as per scaffold plan
-
scaffold signed off
-
stair bottom step to natural ground no more that 190mm
-
photos
-
completed by
Suspended Formwork 1st Floor
-
Scaffold installed and tagged
-
Structural steel installed. if NO call site manager
-
block work complete. if NO call site manager
-
has surveyor completed set out on suspended floor plate
-
penetrations installed
-
set downs installed
-
engineers inspection approved
-
photos
-
completed by
Concreter Main 1st Floor Slab
-
Formwork in correct positions, relative to survey pins
-
step down and wet area formwork installed to survey pins
-
Formwork measurements correct, with adequate bracing
-
Formwork square
-
All formwork level
-
surveyors inspection sign off
-
Slab height as per plans and surveyor height pegs
-
all Step downs installed(as applicable)
-
All footings, beams and slab completely vibrated
-
Engineers inspection and approved prior to pouring
-
concrete strength and slump confirmed correct
-
no cold joints in pour
-
all internal pegs removed
-
Formwork stripped, debris in bin
-
Spoil removed to front of site for easy removal. one pile
-
Wash out in bin
-
site left secure
-
photos
-
completed by
1st Floor Block Work
-
surveyor pinned slab for block set out. if NO call site manager
-
termite treatment barrier installed prior to commencement. if NO call site manager
-
blockwork braced prior to core fill
-
window and door openings confirmed for location as per plans
-
blockwork washed out prior to engineers inspection
-
blockwork completed around structural steel
-
engineers inspection prior to core fill, approved
-
remove all debris to bins provided
-
remove all left over mortar and clean to bottom of slab and remove to bin
-
is blockwork plumb and level. with all core fill cleaned off top course for suspended formwork
-
Slab cleaned
-
concrete pump waste and washout in bin
-
Photos
-
Completed by
Frames and Trusses
-
all frames plumb and straight
-
all tie down installed
-
all bracing installed
-
all trusses complete with tie down
-
structural steel installed
-
engineers inspection approved
-
all debris removed to bin
-
slab swept clean
-
photos
-
completed by
Metal Roofing
-
all parapet flashings installed
-
all flashing installed
-
lower roofs installed
-
all upper roofing installed
-
DP nozzles and rain heads installed
-
All flashings scribed to roofing profile
-
all debris removed to bin
-
scaffold not removed and as sign off
-
profiles matching plans
-
photos
-
completed by
Window Installation
-
all sub sills installed
-
all windows and doors installed
-
all caulking and sealing complete
-
window frames taped both sides and plastic protection to all glazing both sides
-
photos
-
completed by
Electrical Rough in
-
all lighting wired
-
in floor power and lights
-
all power wired
-
all external GPO's wired
-
all 3 phase wired
-
all data wired
-
jetty 3 phase
-
all security
-
all debris removed to bin including all cable clippings
-
photos
-
completed by
Plumber Rough in
-
water points
-
fridge point
-
external taps
-
jetty
-
all debris removed to bin
-
photos
-
Completed by
HVAC Roughin
-
flexi duct installed
-
solid ducting installed
-
blower units and zoning motors installed
-
all debris removed to bin
-
photos
-
completed by
Plasterboard and Suspended Ceilings
-
suspended ceiling frame complete
-
blocking for all fitments and adaptable fittings
-
insulation installed to walls and ceilings
-
framing as per reflected ceiling plan complete
-
P50 details
-
door jambs installed plumb and level
-
square set jambs and windows
-
level 5 achieved
-
all debris removed to bin
-
floor scrpaed of all plaster
-
floor swept and blown out left ready for fix out
-
photos
-
completed by
Waterproofing Wet Areas
-
water stops installed
-
caulking as required
-
puddle flanges and wonder caps
-
debris removed to bin
-
signage wet waterproofing until.... installed
-
photos
-
completed by
Wet Area Tiling
-
levelling wedges used on floor and walls
-
membrane installed and not damaged at time of tiling. if damaged call site manager immediately
-
caulking complete
-
grout complete
-
falls to wastes
-
debris removed to bins
-
non tiled floor areas used scrapped to remove debris
-
no cement or bedding materials left on the slab. floor scrapped
-
ram board flooring protection installed and taped throughout
-
photos
-
completed by
Main Floor Tiling and Balconies
-
levelling wedges used on floor and walls
-
membrane installed and not damaged at time of tiling. if damaged call site manager immediately
-
caulking complete
-
grout complete
-
falls to wastes
-
debris removed to bins
-
non tiled floor areas used scrapped to remove debris
-
no cement or bedding materials left on the slab. floor scrapped
-
expansion joints as per NCC current standards
-
tiling cleaned, excess grouts etc removed
-
ram board flooring protection installed and taped throughout
-
photos
-
complete by
Timber Flooring
-
floors levelled
-
membrane installed, photos required
-
caulk expansion joints installed
-
ram board flooring protection installed and taped throughout
-
photos
-
completed by
Cladding and Eaves
-
wrap installed and all opening and holes taped
-
debris removed to bin
-
all joints sealed with sealant
-
trims, angles and starters installed
-
are all fixings flush ready for paint
-
photos
-
completed by
Electrical Fit Off
-
light fittings
-
led strip lighting
-
pendant lighting
-
floor lighting
-
recessed lighting
-
-
external lighting
-
GPO's
-
external GPO's
-
jetty 3 phase
-
pool pump, irrigation and BBQ area
-
3 phase AC
-
HWS
-
NBN
-
data points
-
WAP system
-
power to curtain remote system
-
security system
-
HVAC
-
appliances connected
-
sub boards and main circuit board
-
commissioning of all systems
-
photos
-
Completed by
Plumber Fit Off
-
all PC items installed and sealed as required
-
leak tested
-
external taps
-
water to jetty
-
irrigation connections
-
appliances connected
-
photos
-
completed by
Carpenter Fixout
-
door handles
-
latches and catches
-
door stops
-
PC items
-
rubbish removed to bin
-
Photos
-
completed by