Items to be checked
-
No public safety hazards are evident
-
Active site has mandatory toilet and bin/cage on site
-
Site sign in place with address displayed
-
Emergency Nos. & Hospital details displayed
-
OHS Co-ordination Plan Displayed
-
Housekeeping is adequate with clear access provided
-
Temporary fencing safe with gates and panels closed when site is not active
-
Electrical meter box is stable with RCD tested and current
-
Electrical equipment is in safe condition and is tested & tagged
-
House frame structural stability and temporary propping adequate
-
Roof edge protection in place (where required)
-
Scaffolding is in safe condition with safe access provided
-
Trestles are in safe condition with legs not sitting on bricks
-
Ladders being used on site are industrial rated (120kg) and in safe condition
-
Trenching shored and barricaded (where applicable)
-
Protruding pipes and star pickets are safely capped or protected
-
PPE in use and UV protection being used (where required)
To be checked on double storey homes
-
Stair void platform is compliant and installed prior to any frame works continuing on the first floor level
-
First floor edge protection in place prior to flooring being installed
-
Two plank system is in place with safe access provided
Contractor compliance
-
Have contractors and their workers received DFC Induction
-
Are all contractors carrying their CI cards
-
Can contractors produce their SWMS and are all workers signed into it