Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Operative being assessed
Tools and equipment
-
Pipe pushing equipment
-
Pipe insertion protection
-
Pipe coil trailer
-
Pipe rollers
-
Butt fusion control unit
-
Electrofusion control unit
-
Re-rounding clamps, scraper and marker pen
-
Stoppers
-
PE pipe cutter
General requirements: Insertion
-
Dead mains insertion is an integrated process for flow stopping, decommissioning, PE main <br>insertion, testing and commissioning followed by service transfer as applicable. In some cases, the<br>Operational Manager may decide to test individual, pipe strings or coils before insertion. Where <br>required the pipe string must be anchored temporarily because then pipe may straighten or snake <br>when pressurised. Warning signs advising the pressure testing is in progress must be placed at<br>either end of the site. An air test of not greater than 50mbr must be applied, all joint(s) must be<br>tested immediately using an approved leak detection fluid, which must be washed off with clean <br>water. Following successful testing, the air test should be slowly released.
-
A number of excavations launch and receive pits and main to service connection excavations have <br>to be completed prior to commencing insertion
-
The main must be pushed in using a pushing machine
-
During the insertion process the PE main is to be inspected for visible damage
-
For pipe string, the free end must be controlled to prevent injury/damage as a result of whipping
-
For pipe coils the lead end must be mechanically restrained until it is securely fastened in the push<br>machine.
-
Insert flow stop equipment on section to be inserted as per Section B2, (SGN/WI/ML/2). use twin <br>sets of equipment at either end e.g. 8 bags in total.
-
Carry out the Decay test as per Section H5, (SGN/WI/ML/2) if satisfactory decommission main to <br>be inserted. If unsatisfactory the Operational Manager consulted to determine course of action to<br>be taken.
-
Cut out section of main at either end ensuring the pipe is cut square, fit cap ends as appropriate <br>with anchorage on the remaining live end(s).
Gauging of existing main
-
Confirm that the parent metallic main is clear of obstructions a proving length of the main should <br>be inserted, pulled through and inspected for damage at each intermediate excavation.
-
The launch/receive excavation should be kept to a minimum. Figure 4, (SGN/WI/ML/2) provides guidance on sizes of excavation of launch pits but an assessment of site conditions must be undertaken.
- Yes
- No
- N/A
-
Intermediate excavation at bends refer to Figure 5, (SGN/WI/ML/2) siphons, valves or other<br>intermediate points must be long enough to enable the fitting to be cut out and for the inspection <br>pipe to go through.
-
Surface damage must not exceed 10% of the pipe wall thickness. Where this occurs, the pipe must <br>not be used. If deep scratching of the pipe has occurred, further investigation of the parent main<br>must be undertaken before continuing with the operation.
-
Typical insertion layouts are shown in Figures 4 and 5, (SGN/WI/ML/2).
Preparation for insertion of first pipe string
-
The PE pipe to be inserted must be protected from sharp edges of the existing parent main at each <br>point of entry.
-
Fit a nose cone to the leading end of the pipe.
-
Rollers or other suitable packing must be adequately positioned at road level and in the launch excavation to guide the PE pipe into the metallic parent main.
- Yes
- No
- N/A
-
The position and adequacy of guide rollers to assist to negotiate any bends must be checked at this<br>stage.
Insertion general
-
The preferred method of PE insertion is to push the pipe under controlled conditions from the <br>launch pit.
-
Each pipe/coil must be marked at appropriate intervals as it is inserted to indicate the remaining<br>length to be inserted, this will ensure the PE insertion head can be located, should there be an <br>obstruction.
-
For each added pipe string the new butt fused joint must be allowed to cool and the bead removed. The bead must be inspected as per Appendix E, (SGN/WI/ML/2) and passed to the Operational Manager
- Yes
- No
- N/A
-
During the insertion process the passage of the pipe should be checked at the intermediate <br>excavations for damage
-
Where the inserted PE pipe is required to change direction pipe rollers should be adequately <br>positioned and the lead end of the PE pipe should slowly and carefully guide into the main <br>opening.
-
During the and on completion of the insertion process, the surface of the lead pipe should be <br>examined for damage.
System integrity test
-
Sufficient surplice pipe must be available left at either end for final connection.
-
The ends of the inserted main must be capped using PE end caps fused onto the main.
-
A pressure test must be applied to the new main in accordance with Section G1, (SGN/WI/ML/2)
Sign off
-
Name of assessor
-
Pass or refer for further training