Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location
  • Operative being assessed

Tools and equipment

  • Pipe pushing equipment

  • Pipe insertion protection

  • Pipe coil trailer

  • Pipe rollers

  • Butt fusion control unit

  • Electrofusion control unit

  • Re-rounding clamps, scraper and marker pen

  • Stoppers

  • PE pipe cutter

General requirements: Insertion

  • Dead mains insertion is an integrated process for flow stopping, decommissioning, PE main <br>insertion, testing and commissioning followed by service transfer as applicable. In some cases, the<br>Operational Manager may decide to test individual, pipe strings or coils before insertion. Where <br>required the pipe string must be anchored temporarily because then pipe may straighten or snake <br>when pressurised. Warning signs advising the pressure testing is in progress must be placed at<br>either end of the site. An air test of not greater than 50mbr must be applied, all joint(s) must be<br>tested immediately using an approved leak detection fluid, which must be washed off with clean <br>water. Following successful testing, the air test should be slowly released.

  • A number of excavations launch and receive pits and main to service connection excavations have <br>to be completed prior to commencing insertion

  • The main must be pushed in using a pushing machine

  • During the insertion process the PE main is to be inspected for visible damage

  • For pipe string, the free end must be controlled to prevent injury/damage as a result of whipping

  • For pipe coils the lead end must be mechanically restrained until it is securely fastened in the push<br>machine.

  • Insert flow stop equipment on section to be inserted as per Section B2, (SGN/WI/ML/2). use twin <br>sets of equipment at either end e.g. 8 bags in total.

  • Carry out the Decay test as per Section H5, (SGN/WI/ML/2) if satisfactory decommission main to <br>be inserted. If unsatisfactory the Operational Manager consulted to determine course of action to<br>be taken.

  • Cut out section of main at either end ensuring the pipe is cut square, fit cap ends as appropriate <br>with anchorage on the remaining live end(s).

Gauging of existing main

  • Confirm that the parent metallic main is clear of obstructions a proving length of the main should <br>be inserted, pulled through and inspected for damage at each intermediate excavation.

  • The launch/receive excavation should be kept to a minimum. Figure 4, (SGN/WI/ML/2) provides guidance on sizes of excavation of launch pits but an assessment of site conditions must be undertaken.

  • Intermediate excavation at bends refer to Figure 5, (SGN/WI/ML/2) siphons, valves or other<br>intermediate points must be long enough to enable the fitting to be cut out and for the inspection <br>pipe to go through.

  • Surface damage must not exceed 10% of the pipe wall thickness. Where this occurs, the pipe must <br>not be used. If deep scratching of the pipe has occurred, further investigation of the parent main<br>must be undertaken before continuing with the operation.

  • Typical insertion layouts are shown in Figures 4 and 5, (SGN/WI/ML/2).

Preparation for insertion of first pipe string

  • The PE pipe to be inserted must be protected from sharp edges of the existing parent main at each <br>point of entry.

  • Fit a nose cone to the leading end of the pipe.

  • Rollers or other suitable packing must be adequately positioned at road level and in the launch excavation to guide the PE pipe into the metallic parent main.

  • The position and adequacy of guide rollers to assist to negotiate any bends must be checked at this<br>stage.

Insertion general

  • The preferred method of PE insertion is to push the pipe under controlled conditions from the <br>launch pit.

  • Each pipe/coil must be marked at appropriate intervals as it is inserted to indicate the remaining<br>length to be inserted, this will ensure the PE insertion head can be located, should there be an <br>obstruction.

  • For each added pipe string the new butt fused joint must be allowed to cool and the bead removed. The bead must be inspected as per Appendix E, (SGN/WI/ML/2) and passed to the Operational Manager

  • During the insertion process the passage of the pipe should be checked at the intermediate <br>excavations for damage

  • Where the inserted PE pipe is required to change direction pipe rollers should be adequately <br>positioned and the lead end of the PE pipe should slowly and carefully guide into the main <br>opening.

  • During the and on completion of the insertion process, the surface of the lead pipe should be <br>examined for damage.

System integrity test

  • Sufficient surplice pipe must be available left at either end for final connection.

  • The ends of the inserted main must be capped using PE end caps fused onto the main.

  • A pressure test must be applied to the new main in accordance with Section G1, (SGN/WI/ML/2)

Sign off

  • Name of assessor

  • Pass or refer for further training

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.