Information
Project Details (Completion of all of the following fields is mandatory. Forms submitted without all fields completed will not be assessed.)
-
Audit Title/Project Description
-
Design Pack ECB Link ID (eg. ABC-1234)
-
Work Parcel/Contract No.
-
Separable Portion No.
-
Order No.
-
Site Address
-
Project Manager
-
Team Manager
-
Authority Number
-
Installer Name
-
Installation Date
Section 1
Superstructure
-
a. Wall bars correct height
-
b. Superstructure isolation material installed correctly
-
c. Superstructure correctly mounted and assembled
-
d. Top iron/tie bar spacing correct and aligned over centre line of suite
-
e. Suite support frames mounted at correct intervals & vertical (within 5 mm)
-
f. Protectors fitted to U bar ends
-
g. Cable runway mounted correctly
-
h. Power cable tray mounted correctly
-
i. Lighting correctly installed
-
j. Metal chips, dirt etc cleaned from work area
-
k. Surface treatment of superstructure undamaged
-
Ref: TM00011 CN1234 CSD 26203
-
*Mandatory photo required - Fairly wide shot of the whole rack, may need to use arrows to highlight where your rack is.
Section 2
Superstructure Safety Rails
-
a. Safety Rail Installed correctly
-
b. Landing gate self closes
-
c. “helmet ”warning plate attached
-
d. Access ladder correctly installed
-
Ref: TM00011 CN1234 CSD 26203
-
*Mandatory photo required - Superstructure access ladder
Section 3
Type 04 Rack DWDM TERMINAL CORE (Vendor Value Add)
-
Photo of rack before installation of S/Rs.
-
a. Correct Rack Layout delivered eg, Layout 244
-
b. No damage to rack (structural /paint /plating)
-
c. Subrack mounting rails in the 170mm mid-mount position
-
d. All cage nuts installed as per rack layout
-
e. PDP installed as per rack layout
-
f. Fibre storage tray/s as per rack layout
-
g. Subrack support bar installed as per rack layout
-
h. ESD socket installed in SU15 RHS only
-
i. Correct Earth tree fitted
-
Ref: Design Pack TM00046 Iss 6 TAF0001-232593[1]_Installation Addendum TAF0001-118783(8) Rack Layouts
-
*Mandatory photo required - Rack photo showing rack at delivery.
Section 4
Type 04 Rack DWDM Terminal CORE Top photo
-
a. Scratches, exposed rivets covered with supplied patches
-
b. Rack installed in the correct floor position
-
c. Rack installed at the same s/structure height as adjacent racks
-
d. Rack level and plumb (check with spirit level)
-
e. Rack securely attached to superstructure or wall using correct mounting kits and earthing practices
-
f. High superstructure kit “thick washers installed below RH C-channel”
-
g. SDH / Non SDH racks isolated (undamaged paint provides insulation) <br>
-
h. Rack earthed to SRPP or MSRPP cable via flying lead & IPC connectors correctly torqued
-
i. Rack connected to site optic ducting with 2 x 50mm convoluted tubes (LHS)
-
j. Rack ducting / Convoluted tubing correctly mounted and as straight as possible secured with minimal cable ties
-
k. Convoluted tube enters rack by approximately 65mm (clears the top tongue of the rack optic duct) and is tied to the rack optic duct using both anchor points<br>
-
l. Rack labelled with SRPP label
-
m. Rack labelled with rack header label
-
Ref: Design Pack TM00046 Iss 6 TAF0001-232593[1]_Installation Addendum
-
*Mandatory photo required - Photo of Terminal Core rack top half with superstructure connection
Section 5
Type 04 Rack DWDM Terminal CORE Bottom photo
-
a. Vertical Rack optic duct position adjusted to 80mm
-
b. Hook & Loop pads fitted to the rear of the rack optic ducts as per Rack Layout
-
c. Fibre storage tray guide clips installed in correct positions
-
d. Rack correctly located over floor tiles (raised floor only)
-
e. Rack securely bolted to floor, using supplied anchors & feet set at 45 degree angle to frame edges
-
Ref: Design Pack, TM00046 Iss 6, TAF0001-232593[1]_Installation Addendum
-
*Mandatory photo required - Photo of Terminal Core rack bottom half.
Section 6
HC-PDP (Vendor Value Add)
-
a. HC-PDP installed in the correct position and secured correctly
-
b. 32A CBs installed to power subrack
-
c. Secondary power terminations secure with no bare copper exposed
-
d. Secondary power cables labelled in HC-PDP, label has correct orientation away from termination point
-
Ref: TM 00046 A01
-
*Mandatory photo required - Photo of HC-PDP at delivery. Alarm wires are not Vendor Add.
Section 7
HC-PDP
-
a. Anderson connectors for each primary feed RF1 & RF2 cable tied to prevent accidental pulling apart<br>
-
b. Correct alarm cable and colour code
-
c. Alarm cables terminated correctly on Krone Terminations
-
d. Alarm priority switches set to correct position
-
e. No Excessive Cable Lengths in HC-PDP
-
f. No permanent alarms on HC-PDP
-
g. HC-PDP Subrack label correct size
-
h. Label subrack Position correct format
-
i. RF1 & RF2 , Fuse / Breaker Location correct format
-
j. Circuit Breaker designation for relevant subracks
-
k. Correct ACCADS/TESAMS alarm IDF location
-
l. ACCAD/TESAMS Alarm IDF labelled
-
Ref: TM 00046 A01
-
*Mandatory photo required - Close up Photo of front cover label and panel
Section 8
Rack Primary Feed Cables
-
a. Rack power cables correct size (16mm2)
-
b. Rack power cables segregated from the LOD Primary Power 150 mm2 cables
-
c. Rack power cables contained within the power tray
-
d. Cables not damaged/ against a sharp edge
-
e. Rack feed A& B fed from different s/racks/planes but same CB position (unless specified in Design Pack)
-
f. Power cable lugs crimped correctly/ securely at LOD
-
g. Heatshrink on all lugs
-
h. LOD CBs correct type and rating
-
i. LOD CBs securely fitted on “Din” rail
-
j. LOD CB Locking clip is in the “closed” position
-
k. Rack feed cables labelled at APDP end (RF1 & RF2)
-
l. Rack feed cables labelled at LOD
-
m. LOD labelled for correct CB allocation
-
Ref: CSD 26204
-
*Mandatory photo required - Photo of primary connections at distribution point
Section 9
DWDM Terminal CORE Subrack
-
a. Subrack installed in correct position as per rack layout
-
b. Power cables run correctly down RHS of rack.<br>
-
c. Bridge cables run correctly down RHS of rack
-
d. Subrack label location and data correct
-
e. Laser warning labels fitted to outside of hinged fibre cover
-
f. Fibre pinching warning labels fitted to inside hinged fibre cover
-
g. Subrack earthed correctly
-
Ref: TAF0001-232593[1]_Installation Addendum
-
*Mandatory photo required -Photo of Terminal CORE subrack
Section 10
DWDM Terminal Core Subrack RHS LTU area
-
a. Power Cables not too long/short at LTU end
-
b. Subrack power terminations correct and secure
-
c. Bridge cabling routing correct, neatly run & secured with cable ties (cut flush)
-
d. Card modules securely installed in the correct slot as per supplied Inventory sheets
-
Ref: TAF0001-232593[1]_Installation Addendum
-
*Mandatory photo required - Photo of power and bridge cable connection fields – Upper and Lower shelves.
Section 11
DWDM Terminal CORE Subrack Optical Fibres
-
a. Optic cords correctly run and maintained at the rear of the rack optic duct with Velcro ties
-
b. Minimum bending radius of 30mm maintained for all optic cord bends
-
c. Fibres run correctly in S/R fibre trays – no extra length stored at this point.
-
d. Line/External optical fibres labelled with port number and direction, EQ IN or OUT
-
e. Internal interconnect optical fibres labelled with correct factory labelling
-
f. All optic interfaces checked for cleanliness
-
Ref: TAF0001-232593[1]_Installation Addendum
-
*Mandatory photo required - Photo of subrack and fibres
Section 12
DWDM Terminal CORE DCM Unit
-
a. Subrack installed in correct position as per rack layout
-
b. Subrack label location and data correct
-
c. Optic cords correctly run and maintained at the rear of the rack optic duct with Velcro ties
-
d. Minimum bending radius of 30mm maintained for all optic cord bends
-
e. Fibres labelled with correct factory labelling
-
f. All optic interfaces SC checked for cleanliness
-
Ref: TAF0001-232593[1]_Installation Addendum
-
*Mandatory photo required - Photo of filter units
Section 13
Secure Drawer
-
a. Secure drawer installed as per rack layout (1st in rack only)
-
b. Secure drawer alarm cable has sufficient cable to allow the drawer to be removed from rack for maintenance purposes
-
c. “Secure Drawer” Label attached 50mm from drawer
-
d. Correct gooseneck on rear of drawer
-
e. Secure drawer alarm cable terminations correct
-
f. First in Secure drawer contents correct as per attached spare list
-
Ref: TAF0001-232593[1]_Installation Addendum
-
*Mandatory photo required - Photo of secure drawer
Section 14
MSRPP / SRPP
-
a. Single Point of Connection Bar marked as “SPC”
-
b. MSRPP / SRPP connected to the building earth only at one point SPC
-
c. CCB Bar mounted on insulated spacers
-
d. MSRPP/ SRPP has no direct electrical contact with non-SDH earth planes
-
e. Mechanical rack supporting is electrical insulated from superstructure
-
f. SDH superstructure is temporarily earthed for safety by a dedicated conductor to the SPC (typically16 mm2) Note: This to be removed once the first NON SDH rack has been installed and bolted to the superstructure
-
g. Bare copper ends of MSRPP / SRPP covered with heat shrink end caps
-
h. Common Collector Bar labelled with “MSRPP / SRPP”
-
i. Internal Common Collector Bar in Small Station SDH rack labelled with SRPP
-
j. MSRPP / SRPP label on Either End of CCB to SPC connecting cable
-
k. MSRPP / SRPP label at 1 Metre interval above/below equipment racks
-
l. MSRPP / SRPP label on either end of the SUITE cable
-
Ref: CSD 26204, 007334 Sect 5 Paper 1
-
*Mandatory photo required - Photo of rack earth connection.
Section 15
Optic Ducting
-
a. Duct installed as per design
-
b. Overhead fibre ducting correctly mounted
-
c. Duct level and centred above suite (where possible)
-
d. All joints fully pushed home and secure
-
e. No broken slots
-
f. All ducting is secure and supported both Horizontally & Vertically with no lateral movement
-
g. No internal protrusions
-
h. Ramp drop-offs correctly installed
-
i. ODF/OFDP drop-off correctly positioned
-
j. Ducting within alignment +- 5 mm
-
k. No Refuse/litter in ducting
-
l. Duct capacity not exceeded (50mm in 100,200 & 300mm duct)
-
m. Warning signs present
-
Ref: CSD 26203, TM00138 A01
-
*Mandatory photo required - Optical ducting
Completion
-
General Comments
-
This is the end of Photo Audit. Your audit result can be found under "Audits" menu. You can edit, preview and send your result via Email