Information

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • What type of asbestos containing material is being worked on?

  • What is the approximate extent of the works?

  • What planned control measures will be used and how will the works be supervised and monitored(Taken from ASB5)

Preliminaries

  • Contract supervisor (is supervisor on site listed in the plan of work)?

  • Is the number of operatives (inc supervisor) on site less or equal to that stated on ASB5?

  • Is the scope of works adequately described in the plan of work?

Site Documentation

  • Is there a copy of the current valid asbestos licence available for inspection?

  • Is there a job specific plan of work/ assessment on site?

  • Is the POW being followed?

  • Does the plan of work detail when the work is to be carried out? (including start/finish times and weekend variations)

  • Does the plan of work detail the person or company providing the 4 stage clearance and to whom they are contracted?

  • Does the plan of work detail the type of asbestos involved? (i.e amosite, chrysotile, crocidolite)

  • Does the plan of work detail the condition of the asbestos containing the material being removed(e.g good, fair, poor)

  • Does the plan of work (or standard procedure) detail who is authorised to amend the plan of work?

  • Has a tool box talk been given regarding any changes?

  • Does the plan of work (or standard procedures) detail the type of respirators to be used?

  • Does the plan of work detail the air monitoring arrangements for the duration of the works?

  • Does the plan of work (or standard procedures) detail the arrangements for smoke testing & witnessing?

  • Does the plan of work (or standard procedures) detail the construction method for enclosures and airlocks?

  • Does the plan of work detail the asbestos removal technique to be used?

  • Does the plan of work (or standard procedures) detail the decon entry and exit procedures?

  • Is there a set of risk assessments on site and available for inspection for activities other than asbestos removal? (hot work, working at height, hand tools etc)

  • Is there a set of COSHH assessments on site?

  • Is the site diary/log available for inspection and up to date?

  • Is there documented evidence on site confirming current insurance cover for both employers liability and public liability?

Site operatives or supervisors

  • Supervisor Name

  • Current Medical Certificate

  • Current Training Certificate

  • Face Fit Test Cert for RPE

  • Inspection record for RPE?

  • Emergency Procedure Awareness?

  • Record for RPE

  • Clean Shaven

  • Awareness

  • Additional comments

  • Operative name

  • Current Medical Certificate

  • Current Training Certificate

  • Face Fit Test Cert for RPE

  • Inspection record of RPE?

  • Emergency Procedure Awareness?

  • Record for RPE

  • Clean Shaven

  • Additional comments

  • Is each viewing panel (where applicable) at least 600 x 300

  • Are there adequate warning signs which comply with the signs and signal regs?

  • Is there a suitably stocked first aid kit available on site?

Plant on site certification

  • Are there at least 2 H type vacuums on site?

  • Are current DOP test certificates (or copies) available and relevant to each vacuum on site?

  • Does to number and capacity of the NPU's in use correspond with that stated in the plan of work?

  • Are current DOP test certificates (or copies) available and relevant to each NPU on site?

  • Is there current DOP test certificate (or copy) available on site for the NPU within the dirty end of the DCU?

Enclosure / Airlocks

  • Is the enclosure in sound condition and constructed as to prevent the spread of asbestos? (i.e 1000 gauge visqueen)

  • Add media

  • Are the enclosure inspection and smoke test records available for inspection?

  • Is the airlock free from visible asbestos debris?

  • Is a bucket and sponge or similar available for decontamination of respirator?

  • Are the airlock openings either oval or rectangular in shape?

  • Do the flaps cover the airlock openings adequately?

  • Are all of the airlock flaps weighted?

  • Is each stage of the airlock at least 1m x 1m x 2m (height)?

  • Does the inner stage of the airlock have a viewing panel at least 600 x 300mm?

  • Is there a personal H Type Vac in the air lock complete with cleaning tools?

Air Extraction Equipment

  • Is the extract sited in relation to ideal air management?

  • Is the extract capable of giving a minimum of 8 air changes per hour?

  • Is the extract vented to outside atmosphere where practical?

Observed Work Practices

  • Is the pre-filter the only part of the NPU exposed to the working area? (ie NPU sheeted out if inside enclosure)

  • RPE and filter used as stated in plan of work? (ie suitable)

  • RPE identifiable as a complete kit? (i.e mask, blower, and battery all uniquely identified as one kit)

  • Are colours of coveralls as stated in the plan of work or standard procedures?

  • Are all items of necessary PPE being properly worn? (e.g overall hood over head straps, overalls not tucked into boots etc)

  • Does the dust suppression method being used match that stated in the plan of work?

  • Is the dust suppression method suitable for the type of work or material? (if needle injection machine being used, please state manufacturer)

  • Has the waste been appropriately bagged? (e.g immediately and single bagged if still in enclosure and are the bags wet?)

Hygiene Facility

  • Is the unit positioned in relation to the work area as stated in the plan of work?

  • If the unit is not directly connected to the enclosure, would it have been reasonably practicable to do so?

  • Is the transit route as short as possible and away from occupied areas?

  • Is the unit functional/in working order? (water, ventilation, heating, lighting, water filter, drains etc)

  • Are the internal doors and external door to the dirty end all fully self closing?

  • Is there an adequate number of showerheads for operatives?(i.e at least one for every 4 operatives)

  • Is there a nailbrush provided in the shower area?

  • Is the unit is good condition and clean so far as is reasonably practicable?

  • Is there a clearance test certificate from the previous job, for the dirty end and shower compartment of the hygiene unit?

  • Are the clean end and dirty end doors marked (including prohibited entry and mandatory PPE signage where required)?

  • Are towels provided?

Waste

  • Are the waste disposal arrangements as described in the plan of work

  • Are the baglock and waste transit routes free from residual waste?

  • Has a separate baglock been provided

  • Is each stage baglock at least 1m x 1m x 2m (height)?

  • Does the inner stage of the baglock have a viewing panel at least 600 x 300mm?

Miscellaneous

  • Are disposable working coveralls and transit coveralls Category 3 Type 5/6

  • Are contractors vans reasonably tidy and with minimal risk of the spread of asbestos?

Scaffolding

  • Has the asbestos removal contractor any scaffolding on site?

  • Does the scaffold form part of the enclosure or was it liable to disturb asbestos when erected?

  • Was a sub contractor used to erect the scaffolding?

  • Handover Certificate/Sign off available to hand?

Further Comments / Observations / Workforce Feedback

  • Additional comments

  • Actions required

  • Auditors Name

  • Asbestos Supervisor

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.