Hand over process.
-
Has an ARUP QA report been previously issued?
-
Has the school received the Operations and Maintenance manuals?
-
Has the school been issued with the as build drawings?
-
Has the school received a copy of the Certificate of Occupancy?
-
Is the C of O displayed in the foyer?
-
Has the school been issued with all the warranties, guarantees, and contractor contact information?
-
Has the keys for the new building been keyed to the school system?
-
Has the contractor provided spares? Locks x1, ceiling tiles x 10m2, Carpet tiles x 10m2
-
Have all school raised outstanding issues been resolved?
-
Has the school signed the final Certification?
Roof
-
Is the use of mastic appropriate?
-
Has the drainage and overflow been installed to the plans and specifications?
-
Are rivets free of rushing?
-
Is the roof free from construction debrie?
-
Are the roof sheets free from rusting?
-
Are the open ends of the roof sheets filled in?
-
Are ends of the roof sheets turned down?
-
Is the cutting and trimming of the roof sheets well executed?
-
Is the flashing detail well executed?
-
Are leaf guards present?
-
Are roof fixings free of over tightening?
-
Are all down pipes correctly supported?
-
Is the mosquito mech installed to the rainwater tank?
-
Is there a first flush system fitted and is it accessible for maintenance?
-
Other roof observations?
-
Other roof observations?
-
Other roof observations?
-
Other roof observations?
-
Other roof observations?
External works
-
Have all hot water pipes been lagged?
-
Are external paving areas laid with suitable fall?
-
Are weep holes above external paving level?
-
Is concrete paving acceptable?
-
Has the Ableflex been installed between the building and paving?
-
Has Ableflex joints been finished with calking?
-
Has all construction derbies been removed from site?
-
Other external works observations?
-
Other external works observations?
-
Other external works observations?
-
Other external works observations?
Internal Works
-
Is the BMS operating correctly?
-
Have hand trapes been installed on large sliding doors?
-
Have all external doors been installed with correctly adjusted door seals?
-
Have all outlets, switches, emergency/exit lights, and data outlets been individually identified and or numbered?
-
Has an emergency lighting log-book been provided and completed with initial discharge tests?
-
Have RCD's been tested with trip times and inserted into a logbook?
-
Other internal observations
-
Other internal observations
-
Other internal observations
-
Other internal observations
-