Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

General

  • Weather Conditions?

  • Which water authority will be responsible for works once the maintenance period is over?

  • Which authority accredited contractor has been nominated to complete sewer reticulation works?

  • Does the sewer contractor have the correct revision of "issued for construction" drawings on site?

  • Describe the section of works audited with reference to sewer manhole numbers &/or subdivision street names?

  • Is the section of works audited trafficable or non-trafficable?

OH&S

  • Site personnel wear appropriate personal protective equipment as required? I.e high visibility clothing, hard hats & foot ware.

  • Where trench depth exceeds 1.5m Contractor has installed trench shoring or benching as required?

  • Safe access & egress, to & from trenches has been made available for site personnel? I.e ladder or other means.

  • Trenches are fenced off or barricaded when trench is left open?

  • Suitable lifting equipment is available for the works being carried out?

  • Traffic Management has been installed as required?

Sewer Reticulation Works

  • Commencement of sewer reticulation works?

  • Are trench widths adequate for pipe size/type? Refer to standard drawing SEW-1201-V pipe embedment & trench fill typical arrangements.

  • Is the bedding material installed in accordance with design documentation & standard drawing SEW-1202 standard embedment flexible & rigid pipes?

  • Has the trench floor been excavated or compacted to provide a flat firm base to support bedding material & minimise pipeline settlement?

  • Are pipes installed in accordance with design documentation & relevant authority specifications?

  • Does trench backfill material comply with design documentation & relevant authority standard drawings?

  • Are required clearances to other services being maintained as per relevant authority specifications?

  • Is mechanical compaction being carried out in accordance with authority specification? Particularly within the support zone & around manholes, maintenance shafts & inspection shafts.

  • Sewer manholes constructed as shown on design documents?

  • Are lids & covers installed in accordance with with design documentation?

  • All plugs have been removed from stage sewer reticulation works?

Status of water authority tests

  • Has ovality testing of sewer reticulation works been completed?

  • Has successful vacuum testing of sewer reticulation works been completed?

Status of Authority Verification Forms

  • Status of authority Development Deed Document?

  • Status of authority Pre-commencement Verification Form?

  • Status of testing of sewer reticulation works?

  • Status of authority Construction Verification Form?

  • Status of authority as-constructed verification form?

  • Status of authority EDLP Verification Form?

  • Any additional information for the status of Verification Forms, testing &/or construction activities?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.