Orangeburg School District Daily Report
-
Daily Report Date
-
Daily Report Document #
-
Prepared by
-
Sites with Active Subcontractor Work Today
- Add names of sites
Weather/Site Conditions
-
General Weather
- Sunny - Clear Skies
- Partially Cloudy
- Overcast
- Partial Rain
- Thunderstorms
- All Day Rain
- Snow/Sleet
-
Temperature
Safety Review
-
Safety Tool Box Talk with Subcontractor for the site you visited. If they are not providing, please encourage to do so.
- PPE
- Slip/Trip/Fall
- Working from Heights
- Traffic Control on Site
- Emergency Evacuation
- Electrical
- Heat/Cold Stress
- Handling/Storage of Materials/Equipment
- Chemicals
- Hygene
- Hand Tools
- Specific Equipment
- Stand Down
-
By Whom and Reason
-
Safety High Risk Activities Identified for Today's Scope. Crane picks and the like are considered high risk. Be sure to have the necessary AHAs, Lift Plan and staff training as well as safety talks daily to maintain a Safe environment
-
Safety Risk Desription
-
Safety Impact to Schedule, Scope or Cost
- Schedule
- Scope
- Cost
- None
-
# of Days
-
Recovery Plan in Place
-
Describe Impact to Scope
-
Workaround
-
Describe Workaround
-
AHA provided
-
Crane lift plan provided
-
Certifications received
-
Safety talk provide at beginning of day
Housekeeping Review
-
ABM and Subcontractor Rep. to walk work area
-
Remind Subcontractor of Good Housekeeping
-
Reminder of the importance of Final Cleanup
-
Photos of Existing Conditions if Damage to Finishes (Walls, Floor, Ceiling) , Equipment, Furnishings
-
If Existing Conditions Damaged - Describe
-
Area and Description
Mechanical Controls
-
Controls Tech working a which locations today if known
- Add names of sites
Lighting Today and Upcoming
-
Lightserve active on site this week
-
Site(s) Superintendent Visited
- Add names of sites
-
Work being performed as planned
-
Site(s) with issues needing resolution
- Add names of sites
-
Scope Concerns
-
Resolution
-
Schedule Concerns
-
Resolution
-
Material Concerns
-
Resolution
-
Other Concerns - Describe
-
Percentage Complete (Estimated)
-
Interior
-
Emergency Egress
-
Other sites with known activity today
- Add names of sites
Water Conservation
-
Pedal Valve active on site this week
-
Site(s) Superintendent Visited
- Add names of sites
-
Work being performed as planned
-
Impacts to Scope
-
Resolution
-
Impacts to Schedule
-
Resolution
-
Other Impacts
-
Resolution
-
Other sites with known activity
- Add names of sites
Coil Cleaning and Coating
-
Aeroseal active on site this week
-
Site Superintendent Visited
- Add names of sites
-
Work being performed as planned
-
Impacts to Schedule
-
Resolution
-
Impacts to Scope
-
Resolution
-
Other Impacts
-
Other sites with known activity
Mechanical/Electrical and Controls Today and Upcoming
-
LA Heating and Air
-
Package Unit(s) Installed Today
-
Location of Unit(s)
- Add names of sites
-
Wall Unit(s) Installed Today
-
Location of Unit(s)
- Add names of sites
-
Split System Unit(s) Installed Today
-
Location of Unit(s)
- Add names of sites
Rocks in the Road
-
Rocks in the Road Considerations
-
Schedule
-
Scope
-
Other
Materials Delivered to Site
-
Deliveries
- Material
- Equipment
- Other
-
Mechanical
- Delivered to Storage Off Site
- Delivered to School Site
- Other
-
Location(s)
-
Lighting
-
Location(s)
- Add names of sites
-
Water Fixtures
- Delivered to Storage Off Site
- Delivered to School Site
- Other
-
Location(s)
- Add names of sites
Inspection/Testing
- Type of Inspection/Testing
-
Quality Control Inspection
-
Installation Inspected
- Lighting
- Water Conservation
- Coil Cleaning
- Mechanical
- Controls
-
Outcome
-
Outcome
-
Explain
-
Was sub notified of deficiencies?
-
Sampling for M&V/Cx
-
Sampling for M&V/Cx
-
Other Inspection/Testing
Visitors to Site
-
Visitor(s) to Site Name and Company
-
Name and Company
-
Name and Company
-
Name and Company
Additional Photos
-
Add media