Title Page
-
Document No.
-
EOTF Intrusive Survey Catering Equipment
-
Client / Site
-
Conducted on
-
Prepared by JAC Electrical Service UK Ltd
-
Personnel
-
Site name & Number
-
Select date
-
Site Drawings Received? Note Drawing Reference<br><br>If no request a copy from Main Contractor
-
Does existing equipment require repair and/or replacement?<br>If yes please indicate<br>Make<br>Model<br>Serial<br>Further information regarding repair
-
Fry Station 1 APS Check if APS is present
- in chase
- in ceiling
- on Roof with extract duct
-
Photo of APS position if possible And Fry Station
-
Fry Station 1 Gas Supplies Check for gas supplies to island
- yes Main contractor to arrange cap off and removal
- none to island
- NA
-
Is Fry Station being replaced?<br>If a 4 vat is being installed note for Fry Lead extensions<br>add notes that may be relevant
-
Fry Station 2 APS Check if APS is present
- in chase
- in ceiling
- on Roof with extract duct
-
Photo of APS Position if possible and Fry station 2
-
Fry Station 2 Gas Supplies Check for gas supplies to Island
- yes Main contractor to arrange cap off and removal
- none to island
- NA
-
Is Fry Station being replaced?<br>If a 4 vat is being installed note for Fry Lead extensions<br>add notes that may be relevant
-
CFP Station APS Check if APS is present
- in chase
- in ceiling
- on Roof with extract duct
-
Photo of APS Position if possible and CFP Station
-
CFP Station Gas Supplies Check for gas supplies to island
- yes Main contractor to arrange cap off and removal
- none to island
- NA
-
Is Fry Station being replaced?<br>If a 4 vat is being installed note for Fry Lead extensions<br>add notes that may be relevant
-
Is there any fixed refrigeration equipment on the CFP Station
-
Grill Station APS Check if APS is present
- in chase
- in ceiling
- on Roof with extract duct
-
Photo of APS Position if possible and Grill Station
-
Grill island Gas Supplies Check for gas supplies to island
- yes Main contractor to arrange cap off and removal
- none to island
- NA
-
Is there any fixed refrigeration equipment on the Grill Station
-
Is Grill hood being replaced
-
If yes will Grill(s) require 3 lead to single 7 pin appliance adaptor plug conversion<br><br>Please provide photos of existing power arrangements <br><br>Please provide number of Grills
-
Are any new Grills being Installed<br>
-
What Model of Grill if known and will electric conversion be required for new 3 platen grill's
-
Prep Line will a new water line be required for steamers
-
Are New UHC HD units being installed<br>If yes will a USB update be required for programming
-
Is there a 3rd IP Station being installed<br>If yes please note approximate length of water line required and fittings<br>
-
Is there any fixed refrigeration to the Centre Island
-
Are existing Drinks towers being re used<br>Please add photos of existing Drinks towers and any notes that are relevant
-
Will existing pythons require extending<br>If yes please indicate approximate length and route<br>please add any additional information and photos you consider relevant
-
Will existing pythons require removal <br>If yes please indicate approximate length and route<br>please add any additional information and photos you consider relevant
-
If New Pythons are being installed please indicate approximate length and route<br>Please add any additional information and photos you consider relevant
-
Will any new or relocated equipment require16a plugs <br>(new hoods, chases only have 16a sockets)<br>If yes list equipment<br><br>please add any additional information and photos you consider relevant
-
Are existing coffee lines labelled accordingly?<br>(If NO please add any additional information you consider relevant)
-
Are existing coffee lines easy to isolate ?<br>( If NO please add any additional information you consider relevant)
-
Do any coffee lines require replacement<br><br>If yes please indicate approximate length and route<br>please add any additional information and photos you consider relevant
-
Do Britta / WMF filters require relocating?<br>(If yes please add any additional information you consider relevant)
-
Are existing coffee machines being refitted<br><br>
-
Are existing coffee machines being refitted If yes please identify which company will be re installing and identify if any faults with machines at time of survey
- Existing machines to be refitted by JAC Electrical
- WMF for new WMF machines only
- United coffee for new B&W machines only
-
Are any additional water lines required for future or additional coffee machines
-
Will Blended Ice machine services require repositioning or removal during work,<br>If so will they require extending please give details below
-
Is a chilled water line required for the Blended Ice Machine<br>If yes please indicate approximate length of run to Drinks tower position
-
Will any other equipment with filtered water or Co2 / Air services require removal or repositioning<br>If yes give details below
-
Is Ice Machine being relocated<br>If yes note if new water line is required<br>Note if drain pipe work will need replacing and size and quantity required<br>Note Make and model of unit <br>Check unit is operational <br>Check date of last clean if possible
-
Will attending engineers require CSCS qualification?
-
Is the use of ladders permitted on site?<br>( if No podiums will be required) please add any additional information you consider relevant
-
Please determine who commissioning stock requests should be sent to and supply name , contact number & email address
-
Will electrical support be required from main contractor?<br>If yes please add any additional information you consider relevant
-
Will Portable Appliance Test (PAT) be required?
-
Portable Appliance test company
- JAC Electrical Services
- Main contractors company
-
Any special requirements / further comments?<br>If yes please add any additional information you consider relevant
-
Add signature