Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location
  • Procedure Summary

Procedure

Preparation

  • Identify all energy sources connected to machine

  • Notify all affected employees

Shut Down Phase

  • Turn off machine or equipment using the normal operating controls

  • Ensure machine has completely stopped and is no longer operating

Isolate Energy Sources

  • Electrical - Turn off main circuit breaker/disconnect switch

  • Pneumatic - Close valves and bleed off residual pressure

  • Mechanical - Block moving parts/mechanisms with guarding

Apply Lock-Out Devices

  • loto 3.jpg
  • Attach lockout devices as shown. Once attached, take a photo to show device applied correctly

  • Each lock uniquely keyed and assigned to an individual?

  • Tag in good condition, with name of person, date and reason for lockout clearly visible

Verify Isolation

  • Attempt to start machine using the normal startup procedure. Ensure it cannot operate

  • Return controls to "off" position after verification

Sign Off

  • Add signature

Approval

  • Date and time of approval

  • Approver's signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.