Information
-
WTG # and Exhibit:
-
Conducted on
-
Prepared by
-
Project Name: Baffin Wind Project
-
Project Number: 13140009
-
WTG #:
-
Date:
Concrete
-
Pedestal & Base concrete have reached minimum break strength (2,000 psi)
-
Necessary forming materials have been removed
-
No visible voids from shrinkage cracks or poor stabilization
-
If cracks or poor consolidation, repaired with an engineer approved method and product
Electrical Conduit
-
All conduit placed according to design specification and fully open as necessary
-
All conduit ends have been located on side of base & pedestal
-
All conduit ends covered
WTG Grounding System
-
Exhibit F-7 is active (started to be filled out):<br>If no, do not proceed with backfilling
-
Grounding cable pulled through each grounding conduit
Excavation Condition
-
All debris removed from excavation
-
Backfill material is not frozen
-
Excessive water (>1") has been removed prior to start of backfill process
-
Rocks (if allowed to be buried), are outside of foundation footprint
-
Final grade of backfill material is visible on pedestal
-
Notes / Observations:
-
Photos:
-
Pre-Backfill Inspection complete with no NCN's
-
If no, are they closed
-
Mortenson QA/QC Representative: