  • WTG # and Exhibit:

  • Conducted on

  • Prepared by

  • Project Name: Baffin Wind Project

  • Project Number: 13140009

  • WTG #:

  • Date:

Concrete

  • Pedestal & Base concrete have reached minimum break strength (2,000 psi)

  • Necessary forming materials have been removed

  • No visible voids from shrinkage cracks or poor stabilization

  • If cracks or poor consolidation, repaired with an engineer approved method and product

Electrical Conduit

  • All conduit placed according to design specification and fully open as necessary

  • All conduit ends have been located on side of base & pedestal

  • All conduit ends covered

WTG Grounding System

  • Exhibit F-7 is active (started to be filled out):<br>If no, do not proceed with backfilling

  • Grounding cable pulled through each grounding conduit

Excavation Condition

  • All debris removed from excavation

  • Backfill material is not frozen

  • Excessive water (>1") has been removed prior to start of backfill process

  • Rocks (if allowed to be buried), are outside of foundation footprint

  • Final grade of backfill material is visible on pedestal

  • Notes / Observations:

  • Photos:

  • Pre-Backfill Inspection complete with no NCN's

  • If no, are they closed

  • Mortenson QA/QC Representative:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.