Information
-
Customer Name
-
Field Manager Name
-
Date of Visit
-
Customer Name
-
Address / Postcode
-
Order number
-
Franchisee Trading title
Customer Feedback
-
Is the Customer Present?
-
Ask for feedback around Installation:
-
Were there any Gas Works?
-
Is an isolation valve accessible for a gas hob?
-
Is the area directly behind the gas hob clear or flammable materials i.e. upstands
-
Were there any Electrical works?
-
Is an RCD installed?
-
Is 10mm earth bonding in place for the gas supply and main water stopcock?
-
Has the customer received the correct electrical certificate?
-
Did we carry out any plastering
-
Is the plastering completed to the required standard? Edging used where required and customers property protected during the process?
-
Has the waste been collected?
-
Comment
-
Were there appropriate dust sheets or protection to the customers property?
-
Are the units all level and all doors correctly aligned?
-
Are all units correctly fitted to the wall?
-
Has any customisation been carried out to the required standard? Are all infills cut & fitted to a professional standard?
-
Has all lighting been installed correctly with cables clipped and out of sight
-
Were the units cleaned out at the end of the installation and prepared for use by the customer?
-
Have all holes for pipework been passed through the minimum sized holes possible? Is the sink base unit neat & tidy with the mid-shelf installed?
-
Have isolation valves been fitted and are accessible?
-
Has the customer been shown where the stop-cock is and how to operate?
-
Are all pipes tidy and clipped correctly and is all waste pipe of the same colour?
-
What type of worktops were installed?
-
Is the customer happy with the work carried out by Sheridans
-
Are the worktops joined with 3 bolts per joint?
-
Are all cutouts sealed with PVA/silicone?
-
Have the worktops been oiled on both sides as per manufacturer's instructions?
-
Have the worktops been installed with slotted brackets / over-sized holes to allow movement of the timber.
-
Have the worktops been installed as per manufacturers instructions?
-
Was any floor tiling being carried out?
-
Was the floor been suitable prepared using 12mm ply for wooden floor and screed for concrete?
-
Are the tiles flat with no protruding edges?
-
Did we carry out any wall tiling?
-
Are the tiles ceramic, Travertine, Porcelain or Natural stone?
-
Have the tiles been sealed as per manufacturer's instructions?
-
Have the tiles been set out to a plan i.e. starting at a window with no "tiny" cuts in corners? all tiles flat with no protruding edges?
-
Has the grout been cleaned off and the tiles polished?
-
Was any laminate flooring being installed?
-
Has the floor been laid correctly? i.e. NOT under unit legs and not tight to edges/skirting boards etc to allow movement? Has the floor been suitably prepared i.e. leaving no excessive "bounce" in sections of floor?
-
Installation Rating?
-
Field Manager feedback/Follow up/action agreed
-
Is any remedial work required to complete this installation to an acceptable standard?
-
Is any stock required to complete the installation?
-
Detail of any work required to complete the installation
-
Field Manager Signature
-
Customer Signature
-
Images of Installation if required.