Project Information
-
Document No.
-
Part No.
-
Revision No.
-
Client Name
-
Project Name
-
Inspection Started
-
Prepared by
-
Location
Test Details
-
Drawings Supplied
-
Drawing Number
-
Drawing Revision
-
Drawing Date
-
Drawing Approval RPEQ
-
Specifications Required
-
Pipelines to be Tested
Pipeline
-
Water Fire Hydrant Type
- Potable Water Main
- Recycled Water Main
- Potable Internal Plumbing
- Recycled Internal Plumbing
- Dedicated Fire Main
-
Residual Hydrant Identification Details
-
Achieved static pressure (kPa)
-
Achieved pressure at 5L/s (kPa)
-
Achieved pressure at 10L/s (kPa)
-
Achieved pressure at 15L/s (kPa)
-
Achieved pressure at 20L/s (kPa)
-
Achieved pressure at 25L/s (kPa)
-
Achieved pressure at 30L/s (kPa)
-
Achieved pressure at maximum flow (L/s, kPa)
-
Photo of Residual Hydrant
-
Outlet Hydrant Identification Details
-
Photo of Outlet Hydrant
Test Procedure
Confirm Project Information
-
Hydrants to be tested and their details
-
Testing specification requirements
Initial Work Area Inspection
-
Is test area barricaded off or sufficiently delineated?
-
Is traffic control established?
-
Has a Safe Work Method Statement been completed and all control measures followed?
-
Environmental controls installed as and if required
Inspection Steps
-
Install Local Authority registered metered standpipe into outlet spring top hydrant
-
Install blank standpipe hydrant into residual spring top hydrant
-
Connect gauge assembly to bleed point on blank standpipe
-
Release metered standpipe tap until required flow rate is achieved and record pressure results at blank standpipe
Disassemble Steps
-
Turn off at standpipes, remove gauge assembly and release standpipes from hydrant
-
Replace hydrant lids, remove barricading and return all items to test unit
Final Demobilisation
-
Notify client of result and to contact TestX office to arrange further testing or reports
-
Calibrated gauge numbers used
-
Inspector's remarks
-
I declare that the inspection procedure was followed in accordance with the nominated specifications
-
Inspection Completed
-
Report Issue Date