Check List

  • Blockwork built to nails and photographed.

  • 15n blocks used.

  • Service holes in the right location and size and heights.

  • Heads smooth side down with correct bearing.

  • Fill joints between blocks.

  • No holes.

  • Brush blockwork.

  • Tie party walls to outterleaf

  • Party walls filled with mortar

  • Party walls built to design depending on step.

  • Thresholds built with light blocks, kept 110ml in from outterleaf, kept down 25ml

  • For the finished floor, allow 50ml wider to door size.

  • Padstones right height and location.

  • No joints bigger that 20ml.

  • Top coarse level, (6ml tolerance). straight to the eye, no dips ,no screeds.

  • Last coarse on outterleaf should be built as design i.e. Concrete brick,150ml

  • Down from FFL, level and straight to the eye.

  • Leave access in correct location for hockey sticks etc and install.

  • Build all gossip walls. Highlight if not dug out.

Photos to be taken

  • BUILT TO NAILS

  • HOCKEY STICK IN PLACE

  • TOP COARSE INCASE ITS KNOCKED

  • JACKWALLS TIED IN

  • ALL HOLES FILLED

  • HOUSE KEEPING INCASE OTHERS THROW BLOCKS AROUND.

  • UPLOAD SIGN OFF TO ZUTEC.

Signature Page

  • Nial Mallon

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.