Blockwork built to nails and photographed.
-
15n blocks used.
-
Service holes in the right location and size and heights.
-
Heads smooth side down with correct bearing.
-
Fill joints between blocks.
-
No holes.
-
Brush blockwork.
-
Tie party walls to outterleaf
-
Party walls filled with mortar
-
Party walls built to design depending on step.
-
Thresholds built with light blocks, kept 110ml in from outterleaf, kept down 25ml
-
For the finished floor, allow 50ml wider to door size.
-
Padstones right height and location.
-
No joints bigger that 20ml.
-
Top coarse level, (6ml tolerance). straight to the eye, no dips ,no screeds.
-
Last coarse on outterleaf should be built as design i.e. Concrete brick,150ml
-
Down from FFL, level and straight to the eye.
-
Leave access in correct location for hockey sticks etc and install.
-
Build all gossip walls. Highlight if not dug out.
Photos to be taken
-
BUILT TO NAILS
-
HOCKEY STICK IN PLACE
-
TOP COARSE INCASE ITS KNOCKED
-
JACKWALLS TIED IN
-
ALL HOLES FILLED
-
HOUSE KEEPING INCASE OTHERS THROW BLOCKS AROUND.
-
UPLOAD SIGN OFF TO ZUTEC.